Project Major Inspection GT2 (Tender No. 8620) Subject DAILY PROGRESS REPORT Date TUESDAY 27 Sept 2022 Prepared by: Akhilan Ganesan Outage Day 21 Note: Day 1 (6 Sept 22) Day 45 (21 Oct 22) Progress Note : DAILY PROGRESS REPORT C – Complete DAY (21) TUESDAY 27 Sept 22 IP – In Progress S - Scheduled
A. Safety, Health, Environment and Security
Item Activity Remarks 1 Toolbox Talk. a. Briefing by Turbine Technical Advisor on work to be carried on gas turbine today and the hazards related, risk controls, manpower required, PTW, access and exits, isolation, equipment, tools PPE, work environment, F&B, responsibilities, communications, ER and EHSS.
B. Turbine Work GT2
Item Activities Progress Remarks 1 Activities 27 Sept (Today) • Inspection and Checking bearing no.1 and no.2 clearence C • Removal of bearing housing no.1 and no.2 C • Preparation work for rotor removal IP • Removal of 2nd stage nozzle IP
2 Activities 28 Sept (Tomorrow)
• Removal of rotor and placing on rotor stand S • Removal of 2nd stage nozzle S • Removal of 3rd stage nozzle S SB/OM/KTMI/DDPR/SEPT22
Plant SESB Kubota Power Plant, Tawau
Project Major Inspection GT2 (Tender No. 8620) Subject DAILY PROGRESS REPORT Date TUESDAY 27 Sept 2022 Prepared by: Akhilan Ganesan Outage Day 21 Note: Day 1 (6 Sept 22) Day 45 (21 Oct 22)
C. Instruments & Electrical Work
Item Activity Progress Remarks 1 Activities 27 Sept (Today) • Verification of Exhaust Thermocouple IP