A. NIGHT SHIFT MANPOWER (08.02 – 08.03)
Trade Numbers
DBB
Site Engineer 1
Safety Officer 1
Male nurse. 1
Foreman Absent-Sickness
Security 2
SSH Inspector 1 1
Indirect Prod (Rigger, Crane Operator 16
etc.)
Labour – Direct Prod
Mason 9
Carpenter 2
Steel Fixer 1
Helper 1
BK GULF
Supervisor (Electrical) 1
Electricians 9
Total Manpower 45
B. ACTIVITIES:
Notes:
Concreting: Start Time: 08.02.2021; 10:30 PM I End Time: 08.02.2021; 5:00 AM
Total Concrete Quantity: 6 cum = (2 Truck Mixers: 1st truck: 3 cum; 2nd Truck: 3 cum)
1. Level P3
Civil Works: No Activity; Electrical: Installation of Cable trays
CCAD – Oncology Centre
Night Shift Report 08.02.21 – 08.03.21
Rev 01/ Page 2|5
2. Level P2
Casting of Stiffener beams and columns
3. Level P1
Casting of Stiffener beam and columns
4. GF – Rubbish Removal
5. Level 1 – No Activity
CCAD – Oncology Centre
Night Shift Report 08.02.21 – 08.03.21
Rev 01/ Page 3|5
6. Level 2 – No Activity
7. Level 3 – No Activity
8. Level 4 – No Activity
9. Level 5 – No Activity
CCAD – Oncology Centre
Night Shift Report 08.02.21 – 08.03.21
Rev 01/ Page 4|5
D. QUALITY OBSERVATIONS:
Lateral Ties/Stirrups: T8
2. No reference grid line or plumb line to ensure the aluminium Curtain Wall bracket Installation is aligned and
as per the correct setting out. – Update: Not Resolved
3. HDG Steel Aluminium brackets – Quality Issues: Zinc coating must be verified upon delivery through MIR. DFT
o be randomly done to ensure minimum of 85 microns is achieved as per BS EN ISO 1461/ASTM A 153. –
Update: Not Resolved
4. Missing bolts (Quality & Safety Non-compliance). Verify the termination between the face of the wall/slab
with the bracket. No notching/cut-out was done. – Update: Not Resolved
5. Unsafe fixation of the mullion to the bracket. Some mullions don’t have any fixation and some only have a
single scree as shown in the picture. – Update: Not Resolved
E. SAFETY OBSERVATIONS:
1. Refer to No. 4 and No. 5 in the above Quality Observations – Major Risk
2. Leaving load on the cantilever loading platform. No valid 3rd independent certificates displayed showing the
design SWL capacity. The inspection report/receipt received from 3rd party doesn’t mention in effect the safe
/fit to purpose status of the CLP and have not mentioned the safe working load to guarantee safe working
order.
CCAD – Oncology Centre
Night Shift Report 08.02.21 – 08.03.21
Rev 01/ Page 7|5
F. GOOD PRACTICE
1. Fresh concrete physical tests have been conducted as per standard requirements
SIGNATURES
Signature: Julius Sanorjo
HSEQ Engineer
Ellisdon