CCAD – ONCOLOGY CENTRE
Page 1|5
A. NIGHT SHIFT MANPOWER (08.05 – 08.06)

Trade Numbers
DBB
Site Engineer 1
Safety Officer 1
Male nurse. 1
Foreman 1
Security 2
SSH Inspector 1 1
Indirect Prod (Rigger, Crane Operator 17
etc.)
Labour – Direct Prod
Mason 10
Carpenter 2
Steel Fixer 1
Helper 1
BK GULF
Supervisor (Electrical) 0
Electricians 0

Total Manpower 38

B. ACTIVITIES:

1. Screed Casting at GF approx. 16 cum


2. Screed Casting at P2 approx. 3 cum
3. Stiffener Beam and Column casting at Level P1 and P2 approx. 3 cum
4. Material Shifting and Offloading

Notes:
Concreting: Start Time: 08.07.2021; 9:00 PM I End Time: 08.08.2021; 4:50 AM

C. Photographic Evidence of Night Site works (Floor-wise)

1. Level P3: No activity


CCAD – Oncology Centre
Night Shift Report 08.07.21 – 08.08.21
Rev 01/ Page 2|7

2. Level P2:
Screed Casting: ~ 3 cum; Stiffener beam and column Casting

3. Level P1
Casting of Stiffener beam and column
CCAD – Oncology Centre
Night Shift Report 08.07.21 – 08.08.21
Rev 01/ Page 3|7

4. GF – Parapet Wall Casting


Screed Casting ~ 16 cum; Material Shifting

5. Level 1 – No Activity

6. Level 2 – No Activity
CCAD – Oncology Centre
Night Shift Report 08.07.21 – 08.08.21
Rev 01/ Page 4|7

7. Level 3 – No Activity

8. Level 4 – No Activity

9. Level 5 – No Activity

10. Level 6 – No Activity


CCAD – Oncology Centre
Night Shift Report 08.07.21 – 08.08.21
Rev 01/ Page 5|7

11. Roof – No Activity

D. QUALITY OBSERVATIONS:

1. Improper Material Storage for Glazing Panels:

a. Glass panels should be secured from both sides to prevent sliding and/or falling by the wayside.
b. It is also a best practice to secure the panels to the A frame with a ratchet strap.
c. The storage area has to be cordoned off physically with signage

2. Unprotected storage for AHU at Level 05

a. It is advisable to relocate the AHU away from the access route to avert any incidental collision during
general manual material shifting.
b. Identify a good location to store the MEP equipment preferably distant from general access and egress
c. Provide physical barriers and signage
CCAD – Oncology Centre
Night Shift Report 08.07.21 – 08.08.21
Rev 01/ Page 6|7

E. SAFETY OBSERVATIONS:

1. Combustible materials i.e. wood, cartons accumulating in typical floors particularly in GF heightens fire load
and fire risk hence to be removed immediately from site.

2. Manual Handling training to be provided for the workers especially on the night shift as the concreting in
lower levels are mostly done by concrete buckets and skips due to access contraints.

3. General external periphery and internal illumination at site needs to improve.

F. GOOD PRACTICE

1. Concrete cube sampling and testing for the screed performed as per standard
CCAD – Oncology Centre
Night Shift Report 08.07.21 – 08.08.21
Rev 01/ Page 7|7

2. Finishing of concrete prior initial setting time

SIGNATURES
Signature: Julius Sanorjo
HSEQ Engineer
Ellisdon