Preliminary Schedule – Hospital (C04), Project Duration 18 Months

2022 2023 2024 2025


Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2

50% DD Finalization 08Aug22


6M 100% DD Finalization 15Nov22

1M Construction Documents 31Dec22


IFC Issuance 30Jan23
RFP Issuance 15Feb23 2M Tender Duration 15Apr23
Tender Evaluation & Contract Award 15May23 1M Commence MEQ/Medical Equip. Contract 01June23

Project Start 15May23 Project Finish 15Nov24

1M Mobilization 15Jun23

6M Engineering 15Nov23

7M Main Contractor Procurement 15Jan24

Final Design – Medical Equipment's & FFE 15Aug23 1 9M Procurement – Equipment's & FFE – 15May24

16.5 M Finish 15Nov24

1.5M Enabling Works 15Aug23

2.5M Sub Structure 30Sep23

3.5M 2 Super Structure 31Dec23

9M MEP & Finishing Works 15Aug24

Access to Equipment’s Installation 15May24 3 3M 4 Installation of Medical Equipment’s 15Aug24

Testing & Commissioning MEP Services &


4M Medical Equipment 15Nov24

Authority Approvals &


1M 5 Project Completion 15Nov24
(*Built Up Area: 20,849 M2)

Key: Milestone Mobilization Authority Approvals Mobilization Engineering Procurement Construction T&C