Date 04/11/2018
1)
EHS Concerns:
2)
Shutdown Progress :
Actual : 30% Vs Expected : 30%
ONGOING ACTIVITIES:
Areas of Concern:
NO INTERNET AND NO PHONE LINE
Recommendations:
Completed work
1
Unbolted Turbine Compartment Ventilation ducts and Removed
Removed Roof
Remove instrumentation wiring and conduit in turbine Compartment and on roof
Removed pig tails piping
Removed fuel nozzles
Removed compartment side doors R/H/S & L/H/S
Remove Combustion instrumentation Spark plugs flame Scanners
Look Ahead:
Remove spool Hubs Turbine end and load gear box end
Remove turbine compartment piping cooling & sealing and gas maniffolds
Removed combustion can doors
Remove crossfire tubes and liners
Remove combustion AFT cans
Take 6 point on R,0
Take rotor 6 point checks
Manpower resources #
BHGE FSE Paul Willoughby & Lamberto D’Intino
Foreman
Mechanical Fitter 2 Mechanical Fitters
Mechanical helper 4 Helpers
E&I helper
E&I
Rigger 1 Rigger
…………..