Subject Daily Report

FSE Name Paul Willoughby


Machine Type GT Frm 5001 –
Unit Customer Tag MT001C / GE NP# G06744

Date 04/11/2018

Work Permit (WP) WP Issuing WP Expiring


# 17131 Work order NO
03-11-2018 - Time: 07.00am 04-11-2018 - Time: 18.30
3664913 GT C

1)
EHS Concerns:
2)

Shutdown Progress :
Actual : 30% Vs Expected : 30%

ONGOING ACTIVITIES:

1. Permits received 07.30am


2. Rotor alignment checks to be carried out
3. Cleaning all parts for rebuild

Areas of Concern:
NO INTERNET AND NO PHONE LINE

Recommendations:

Shortages (materials & tools):

GE Tooling container now on site

Completed work

1
Unbolted Turbine Compartment Ventilation ducts and Removed
Removed Roof
Remove instrumentation wiring and conduit in turbine Compartment and on roof
Removed pig tails piping
Removed fuel nozzles
Removed compartment side doors R/H/S & L/H/S
Remove Combustion instrumentation Spark plugs flame Scanners  

Look Ahead:

Remove spool Hubs Turbine end and load gear box end
Remove turbine compartment piping cooling & sealing and gas maniffolds
Removed combustion can doors
Remove crossfire tubes and liners
Remove combustion AFT cans
Take 6 point on R,0
Take rotor 6 point checks

Please prepare all new parts for combustion inspection

Manpower resources #
BHGE FSE Paul Willoughby & Lamberto D’Intino
Foreman
Mechanical Fitter 2 Mechanical Fitters
Mechanical helper 4 Helpers
E&I helper
E&I
Rigger 1 Rigger
…………..