Adnan Safarini 3B+G+1+M+6+P


PROPOSED LUXURY HOTEL (OASIS) -

REQUEST FOR SNAGGING

REF. No. CR18G-RFS 071


Contract No.
Date: 1 Nov 2022
From ChinaRailway 18th Bureau
To Adnan Saffarini - Consultant
Engr.
Room Title: Relevent:
Zone Level Room No. CR18G-RFS-071 Rev.: 1
4 4 A04 Standard Room RFS No.
Date of RFS:
Date of Inspection No. 2 Inspector Name Disciplinea
Architectural
L Nov 2022 Engr. Saif Wasef

CR18G QA/QC: Roald


EAS Representative: Re-Inspection Record
Accepted ( ) Rejected (x)
Inspection Comments
Item
(2) (3)

The rectification works are still not completed for the wall paint
Undulation issues for the gypsum celing
3 The installation works for the sockets and switches are not completed
4 Loose bathroom accessories
Cleaning the floors and the walls

Silicon works for the sanitary wares are not completed


Poor installation and finishing for the wooden cornice
8 Poorinstallation and finishing for the wooden skirting
clean for the toilet marble
9 The grout works must be
skisting H)
The grout works must be clean for balcony
the

11 Undulating and joint issues for the carpet

12 The joinery works are not installed


13 Mattress and divan are still not delivered
4 Non-slip coating to be applied for the bathroom marble
15 Minibars are still not delivered
16 TV still not delivered
17 GRMS glass panels still not installed
works for the doors are still not completed
18 The finishing
19 The installation works for the ironmongery are still not completed

SuJ d d Commn

|inspection No.:

|CR18G Construction Manager

EAS Rep
Contractor's QA/QC
Roald
po ECETVEN
21 N 2022
Eng Adnan Saffarini
20-11-22
Page 1 of 1
BY:- .-- A04.