You are on page 1of 1

BLOCK / BRICK MASONRY Report No:

AS PER IS 2572:2005
CHECKLIST Date:

Customer : Project : Project Code:


Sub- Contractor : WO No & Amndt, If any.:
Manufacturer : PO No & Amndt, If any.:
Item Description: Identification No.
Location : Sub Location:
Package: Drg No & Rev No :

FQP No. & Rev No. RFIC No.

Qty: Grid No & Level:

Sl.No. Description of Check Points Checked Remarks


Yes No NA
A Pre Masonry Work

1 Approved drawing is available.


2 Make is approved by client
3 Method Statement is approved by client

Ensure cleaning done in all the areas of entire floor before starting the line-out of
3
masonry & cement slurry applied.
4 Ensure higher grade concrete or DPC course on RCC done & cured as specified.
Ensure hacking of RCC column surface is done / bonding agent applied as per
5
manufacturer's specification
6 Ensure green mortar dash coat is applied to RCC surface.
7 Ensure Blocks made wet by sprinkling water as before start of work
8 Ensure Bricks are immersed in water prior to use.
9 Ensure Metal / GI tray is available at work location for mixing of mortar
10 Ensure availability of measurement boxes for batching of sand.
Ensure all type of tools such as Mason's trowel, plumb bob, line thread, spirit
11
level, right angle, measuring tape, etc., are available with mason.
12 Ensure all measuring equipment/ tools are in good condition
13 Interface between Architectural, Structural & MEP works is checked.
B During Masonry Checks
Ensure dimensions and diagonals of room are checked after completion of first
14
layer.
15 Ensure mortar prepared is used within initial setting time
Ensure alignment & plumb of block work is within tolerance limit as per
16
specification
17 Horizontal/vertical joint thickness is uniformly maintained as per specification
18 Ensure raking and simultaneous brooming of joints is done
19 Ensure height of masonry constructed in a day is not more than 1m.
Ensure RCC band / Wire mesh is placed in masonry at 1m (applicable for 4”
20
thickness wall) as specified.

Ensure joint between RCC frame & masonry is kept 20 mm and filled with metal
21
packing as per specification
22 Ensure Lintel anchorage & bearing is adequate as per approved drawing
23 Ensure Anchoring of holdfast is as specified.
C Post Masonry Checks
24 Ensure Date of Block work is mentioned
Ensure curing of block masonry carried out for a minimum 7-10 days after
25
construction.
26 Chasing and finishing of grooves done as specified.

27 Ensure electrical boxes not to be fixed back to back in 4’’ wall


Remarks :

Signature of Sub - Contractor & Date Signature of TPL-FQE & Date Signature of Customer / Inspection Authority & Date
Format No.08.03.05-FMT-C-BRK-CL-001-R00

Page: 1of1

You might also like