TAMIMI PEB INSPECTION CHECKLIST ITP NUMBER DATE WIR NO

Backfilling and Concrete Tiles Installation ELECT-TIC-1.4

PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

Triple Bay Construction Village


TPEB-T691-0920-69 TPEB
Main Construction Village
BUILDING NAME AND LOCATIONS WORK PERMIT REQUIRED?

SCHEDULED TEST DATE AND TIME EQUIPMENT DESCRIPTION

ACTUAL INSPECTION DATE & TIME

ITP NUMBER ACTIVITY NUMBER


ACCEPTED
CONTRACTOR INSPECTION LEVEL CLIENT INSPECTION LEVEL
REJECTED

ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.

A Backfilling and Concrete Tiles Installation

Backfilling and reinstatement of the trench shall be in


A1 Approved SD
accordance with the requirements of approved Shop drawing

Inspect cables for physical damage and proper connection in


A2 Approved SD
accordance with single line diagram.

Cables shall be installed in accordance with approved Shop


A3 drawings, SASO, IEC reference standards and the guidance Approved SD
notes published by the Institute of Electrical Engineers.

Minimum bending radius for all cables shall not be exceeded as


A4 Approved SD
set out in SASO and IEC reference standards

The Contractor shall secure the manufacturers instruction with


respect to:
A5 1. Cable temperature prior to installation. Approved SD
2. Cable temperature during installation.
3. Handling, installation, jointing and termination.

Cast-in-Place or Directly-Buried PVC Conduit - Trench Bottom -


The trench base shall be smooth and free of any debris that (NEC 110.3 (b) - NEMA
A6 may be detrimental to the duct or impede the positioning of TCB 2, Sec 5(a))
spacers.

Red Concrete Tiles Shall be used above direct buried cable or


A7 Approved SD
direct buried Conduit .

Damaged Concrete tiles shall not be used above direct buried


A8 Approved SD/General
cable or direct buried Conduit .

Concrete Tiles Shall be fully covered above direct buried cable


A9 Approved SD/General
or direct buried Conduit .

Concrete tiles shall be arranged properly above direct buried


A10 Approved SD/General
cable or direct buried Conduit .

200x400x50mm Red Concrete tiles shall be used above direct


A11 Approved SD/General
buried cable or direct buried Conduit .

Page 1 of 2
TAMIMI PEB INSPECTION CHECKLIST ITP NUMBER DATE WIR NO

Backfilling and Concrete Tiles Installation ELECT-TIC-1.4

PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

Triple Bay Construction Village


TPEB-T691-0920-69 TPEB
Main Construction Village
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.

Joints in cables will not generally be permitted unless specifically


A12 General
detailed elsewhere.

Where Electrical Power and Instrument Cables are routed in the


A13 same trench minimum separation of 300mm between these cables Approved SD
shall be maintained.

Installed Concrete Tiles as per approved SD Direct buried Cable


A14 Approved SD
Installation General drawing

Direct Buried Cable Trench - Cushioning dry sand shall be clean


A15 Approved SD
and free of stones and rubbl

Cable trench route shall be identified route marker posts positioned


A16 Approved SD
at 30m intervals on straight runs and at any change in direction

REMARKS:

REFERENCE DOCUMENTS:
1- NFPA 70
2- Project Spec
3- Shop Drawings

Contractor / Client
Construction Representative QA/QC SUPERVISOR / MANAGER
Name: Name:

Signature: Signature:

Date: Date:

Contractor QC Inspector Client’s Representative


Name: Name:

Signature: Signature:

Date: Date:

Page 2 of 2