ITP Details
Inspection & Test plan for Grounding &Bonding
Verification
Action
Specification Personnel
Item No Activity Descripation Project Phase Acceptance Criteria and/or Frequency Verifying Document
Drawing No.
ITL A CL/SC
1 Document Review
Grounding & bonding Insallation Method of Document Approved Grounding & bonding Insallation Method of
1.1 Statement Review NFPA 70 ,SBC&IEEE N/A N/A N/A RH R
Statement .
Document
Review NFPA 70 ,SBC&IEEE N/A N/A N/A RH RH
1.2 Earth Resistance Tester Calibration Certificate
2 RECEIVING INSPECTION
Ground Rod, Grounding Cable & Bare Copper
conductor & accessories Material Receiving NFPA
Material NFPA
2.1 70 ,SBC&ELECT-TIC- Consultant N/A H W NFPA 70 ,SBC&Checklist:ELECT-TIC-7.1
Receiving 70 ,SBC 100% Inspection
7.1
on delivery.
3 INSTALLATION
NFPA
Installation of grounding system,Grounding and
3.1 Installation 70 ,SBC&ELECT-TIC- NFPA All approved Consultant N/A H W NFPA 70 ,SBC&Checklist:ELECT-TIC-7.2
Bonding Accessories
7.2 70 ,SBC grounding rod
4 FINAL TESTING
Legends
H HOLD(Signature Reqquired to proceed) S Survillance(Random attendance ,No Signature) I Independence Testing Lab