Professional Documents
Culture Documents
2 INSPECTION
2.1 Inspect Foundation As per Foundation Drawing H S
2.2 All Elements / Components / Fittings. Installed as per drawing . Approved Drawing H R
2.3 Inspection of Level , Allignments and Plumbness. Project Specification H S
3 Painting
3.1 paint touch-up Senet Specification H S
5 Handover Package
5.1 hand over to Client Complition certificate DS R
Legends
Approvals
CQC: Contractor Quality Control
CIA: CIA: Client Inspection Authority SENET: Name: Signature: Initial as used in this document:
SENET: SENET Quality Representative
S: Surveillance Date:
Vis: Visual
D: Dimensional ATC Name: Signature: Initial as used in this document:
V: Verify
W: Witness Date:
H: Hold
DS: Document Submission CLIENT Name: Signature: Initial as used in this document:
R: Review
X: Execute Date:
A: Approval
Page 1 of 1