1. DOCUMENT REVIEW
Technical Specification &
1.1. Review procedures, technical specifications and contract document Verify Approved Tech. Approved Procedures R R/A N/A
Proc., Contract Documents
2. MATERIAL
3. PILING WORK
PP-0512GN-CL-002
3.1 Marking all pile at 1 feet or 30 cmm Visual Inspection Pile Driving Record W SW N/A
( Construction Procedure for Pilling )
3.2 Surveying Coordinate of pipe piling centre line points of the piles Measurement Project Spec. & Proce. 3 inchi Survey Report W SW N/A
PP-CI-GG-003
3.4 PDA Test ( if requaired ) Measurement RESULT OF PDA TEST PDA Report W SW N/A
( Pilling Test Procedure )
3.6.1 Fit up : Groove , Root face, Gap Visual Inspection WPS / PQR WPS / PQR VISUAL WELDING REPORT W SW N/A
Measurement
SP-CI-CC-002 ( Concrete Pile
- Visual Welding
Specification ),PP-CI-GG-003 VISUAL WELDING & PENETRAN
3.6.2 Welding Inspection & NDT - LPT (Liquid Penetrant W SW N/A
( Pilling Test Procedure ) AWS D1.1 REPORT
test) every 10 % for random
AWS D1.1
location
Blows / Feet
PP-CI-GG-003 - Steel pipe pile ø 6" is 5
- Power Pole Mesurament Pile Driving Record W SW N/A
( Pilling Test Procedure ), Drawing - Steel Pipe Pile ø 8" is 13
- Steel pipe pile ø 12 " is 20
PP-CI-GG-003
- Pipe Suport Mesurament - Steel Pipe Pile ø 8" is 10 Pile Driving Record W SW N/A
( Pilling Test Procedure ), Drawing
Blows / Feet
PP-CI-GG-003 '- Steel pipe pile ø 6" is 3
- Power Pole Mesurament Pile Driving Record W SW
( Pilling Test Procedure ), Drawing - Steel Pipe Pile ø 8" is 5
- Steel pipe pile ø 12 " is 7
Blows / Feet
PP-CI-GG-003
- Bridge Mesurament '- Steel Pipe Pile ø 8" is 13 Pile Driving Record W SW
( Pilling Test Procedure ), Drawing
- Steel pipe pile ø 12 " is 28
DISCIPLINE = ALL
INSPECTION AND TEST PLAN PILING ITP N = PP-0512-GN-GG-004-0
PP-0512GN-CL-002
3.8 Pile cut of elevation Check Measurement 1 inchi Survey Report W SW N/A
( Construction Procedure for Pilling )
PP-0512GN-CL-002
3.9 Pipe pile dimensional check after cut of Visual Inspection Drawing Dimensional Report W SW N/A
( Construction Procedure for Pilling )
4. DOCUMENTATION
Contract Documents
4.1 QA/QC Review of site generated handover document Verify Site Instruction Form Scope of Approved Documents Turn-over Documents P/R R/A N/A
Work