You are on page 1of 1

Report No:

ACP CLADDING INSTALLATION


CHECKLIST Date:

Customer : Project : Project Code:


Sub- Contractor : WO No & Amndt, If any.:
Manufacturer : PO No & Amndt, If any.:
Item Description: Identification No.
Location : Sub Location:
Package: Drg No & Rev No :

FQP No. & Rev No. RFIC No.

Make: Grid No & Level:


Checked
Sl.No. Description of Check Points Remarks
Yes No NA
1 Approved drawing is available.

2 Make, shade & related accessories are approved by client

3 Third party test reports are available as applicable

4 All preceeding works are completed

5 Vendor for ACP works is pre qualified and approved

6 Mockup is done & approved by client

7 Method Statement is approved by client

8 All tools & equipment are available at work location

9 Proper scaffolding arrangement is done


Thickness, Shape, Size & Squareness of ACP panel is as per
10
drawing.
Co-ordinates with Total Station checked & found satisfactory as
11
per drawing
12 Levels checked & found satisfactory as per drawing
Support system in the form of brackets or angles installed with
14
proper alignment as per drawings.
Horizontal & vertical alignment of the runners ensured and found
15
satisfactory
Fixing of ACP to the runners with horizontal & vertical alignment
16
ensured
PVC packing provided between MS and ACP is as per approved
17
drawing.
18 Backer rod & Silicon sealant is provided as per approved drawing.

All joints & overlaps are as per specification and ensured no


19
ingress of water.
Remarks :

Signature of Sub - Contractor & Date Signature of TPL-FQE & Date Signature of Customer / Inspection Authority & Date
Format No.08.03.05-FMT-C-CLD-CL-001-R00

You might also like