You are on page 1of 1

Report No:

INSTALLATION OF FLOW METER


CHECK LIST Date:

Customer : Project: Project Code:

Sub- Contractor : WO No & Amndt, If any.:

Manufacturer : PO No & Amndt, If any.:


Item Description: Identification No.
Location : Sub Location:
Package: Drg No & Rev No :
FQP No. & Rev No. RFIC No.

Total Inspected & Total Inspected &


Total offered Quantity:
Accepted Quantity: Rejected Quantity:

Checked
Sl No Description of Check Points Remarks
Yes No NA
1 Approved Location drawing is available Drg No :
2 Approved P & ID is available Drg No :
3 Approved Data Sheet is available Doc No :
4 Approved Typical drawing is available Drg No :
5 Make & type of Flow Meter is approved by client
6 Sub Contractor is pre qualified and approved
7 Method Statement is approved by client
8 Ensure valid calibartion of Flow Meter
Ensure the Location and tapping point is verified as per approved P&ID &
9
Location Drawing
10 Ensure the Flow Meter is free from damages / defects

11 Ensure Supplied Flow Meter specifications match with approved Data Sheet.

12 Ensure Tag plate is correct as per approved Drawings


Ensure the mechanical clearance is available for installing the metering unit
13
with process pipe flanges

14 Ensure the direction of Flow is verified with respect to flow meter

Ensure the correct type and size of gasket is used in between process line
15
flange and metering unit flange
Ensure the specified type and grade of stud and nut used for tightening the
16
metering unit with process line

Ensure Transmitter stand / stanchion installed as per typical drawing and


17
identified location is having gap /clearance with adjacent pipe/equipment

18 Ensure the Stand is secured on the ground / platform

19 Ensure the grouting is done in between the base plate and ground

Ensure the Flow Meter's Transmitter is installed with mounting bracket and is
20
at operation height as per drawing
Ensure Instrument display orientation is accessible for termination purpose
21
and visible to operator.

Ensure the sensor cable between transmitter and metering unit is laid and
22
without blocking the access way

23 Ensure the Transmitter canopy is installed

Note : This format can also be used for FLOW METER (VORTEX / CORIOLIS /ULTRASONIC /DOPPLER / ROTAMETER / MAGNETIC)

Remarks:

Signature of Sub - Contractor & Date Signature of TPL-FQE & Date Signature of Customer / Inspection Authority & Date
Format No. 08-03-05-FMT-I-FMI-CL-004-R00

Sh:1of1

You might also like