You are on page 1of 1

Arvind Smartspaces Ltd. RECORD NO.

CONCRETE POUR CARD BUILDING

LOCATION

PROJECT : PHASE : DATE

NAME OF CONTRACTOR : SHEET NO

FLOOR: MEMBER

REF GFC ARCH DRAWING : QTY[CUMT]

REF GFC STRCTURAL DRAWING : GRADE

Pour Started ……………………………………………….. Pour Completed………………………… WEATHER

Theoretical Cement Bags.................................Actual Cement Bags Consumed.............................


A BEFORE STARTING THE CONCRETING Yes No. REMARKS
1 Checklist for Reinforcement approved.
2 Checklist for formwork and scaffold approved.
3 Checklist for Electrical conduiting work approved.[For slab]
4 Plumbing sleeves are at place as required.
Materials like Coarse Aggregates ,Fine aggregates,cement, Plastisizer,water are adequate in
5
stock.
6 Mix Design Board on display and visible at mixer location.
7 Grade of concrete to be checked based on structural drawing

8 Machineries like Batching plant, lift,mixer ,vibrator , needles are checked and found in working
condition.
9 Pouring Height known
10 Slump cone and cube moulds are at mixer plant .[ 9 cube sample to be taken per job ]
11 Manpower found ok as per the pour qty for the job.
12 Mixer speed checked [ 20-22 RPM ]Mixer blade gap welded adjusted to 30mm.
13 Batch entry Card at place.
B CONCRETE POURING
14 Buttering of mixer done before 1st batch .
15 Every batch mix should be mixed upto 1.5 minutes.
16 Admixture doze specified.
Slump Test done and the Required slump checked as per the mix design. [ Column – 80-100,
17
Slab/beams – 90-100 ]
18 Concrete placing observed and compaction by needle vibrator is satisfactory.
19 Stopper placed at,where the concrete is to be stopped for construction joint.
20 Check whether admixture are properly added to concrete
21 Cube Samples taken as per the method.
C INSPECTION AFTER FINAL FINISH
22 Deshuttering Started as per the IS - 456 2000 SPECS.[Page -25]
23 Hacking started [ at least 1.5" appart and 4mm deep with min 80 nos per sqft range.
Honey-combing found within acceptable limit : Loose aggregates removed and grouting done as
24
per the specs.
25 Honey-combing seen beyond the acceptable limit . Asked to dismantle the member and to recast.
Slab broom finished as per th instruction. Any shrinkage cracks treated immediately with cement
26
sand mortar slurry .
27 Curing started as soon as deshuttering totally done. By water ponding/ Hassian cloth wraping .
28 Slab covered after concrete setting to avoid direct heat .
Curing date written on the member .[ Start and End date on the same place ].Column min 10days
29
and slab min 7 days.
Supports under the beam and slab being removed as per IS -456 2000. Deshuttering being done
30
props left under.
31 Finishing of slab found ok.No nails left after deshuttering .
32 Cube Compressive strength as per given grade.

SIGNATURE OF CONTRACTOR DATE

SIGNATURE OF EXECUTION ENGINEER DATE

SIGNATURE OF QC ENGINEER SIGN

You might also like