Document Title: Method Statement for road work Page : 13 Revision : 0 Date : 9/11/2010

INSPECTION & TEST PLAN (ITP) : Road work


Sr. Inspection / Test Acceptance Criteria Method Frequency Reference Involved Parties Remarks

No Activity Doc. / Format

1 Material approval as per specification visual Initial -- I W W

2 Sub-base/base complete as per specification/dwg visual Initial -- I W W

3 Number of roller passes as per approval visual initial -- I W W

4 Finished level as per drawing visual after laying checklist I W W

5 Surface regularity as per specification / dwg visual after laying checklist I W W

6 Aggregate impact value as per IRC 19:1977 asper IS 2386 part IV as per std. checklist I W W

7 Gradation as per IRC 19:1977 asper IS 2386 part IV as per IS2720 partIV checklist I W W

one per 500 sqm of


8 field density as per IS 2720 Part 28 as per IS 2720 part 28 checklist I W W
compacted area

Inspection Legend Description


I Inspection
T Test
R Review & Approval
W Witness
H Hold (Mandatory Witness Inspection)
QR Quality Record (Report Required)