1 Earthfilling material approval Excavated earth as per specification Before filling Visual Each shift Checklist I W W
2 Foreign materials/ Lumps Quality of filling material as per specification Before filling Visual While spreading I W W
Checklist
3 Layer of filling 300mm layer as per specification During filling Visual While filling I W W
Checklist
as per specification/
4 Compaction Plate compactor/Roller well compaction After each layer filling Sand replacement test instruction from IS2720:1983 Part 7 I W W
engineer in charge
as per specification/
as per IS2720:1983
5 Test Results 95% compaction, MDD After each layer/test Sampling instruction from Test Result QR R R
Part 7
engineer in charge
I Inspection
T Test
W Witness (Optional)