You are on page 1of 9

Construction of new retail units, flats and resurfacing of

parking areas at John Street Car Park Site, Tunbridge Wells


Project Brief (RIBA Stage 2, Concept Design)

Introduction

 In 2012 TWBC Property Services undertook a programme of work to review the


potential to release value from various land assets. The existing Car park at John
Street was reviewed and a number of schemes considered. After this feasibility
work, a scheme for resurfacing the car park and obtaining outline planning
consent for a development of retail and flats was developed and submitted.

 In January 2014 Outline Planning was approved by the Planning Committee.


Formal consent has yet to be issued subject to final approval of Section 106
agreement requirements.

Aims

 To provide an up to date, safe public parking facility and improve the general
appearance of the site for the benefit of the community.

 To develop the building element of the scheme on a commercial basis to provide


a long-term income producing asset.

Scope:

 The project includes works to the area within the ‘red line’ as shown on drawing
number 1641 015, including design and construction of the units and resurfacing
of the car park.

 The project includes providing the electrical and mechanical services necessary
for the development.

 The project may include resurfacing to pavements and works to incoming


services outside the red line area.

 The scope of the project excludes the operation/management of the new


development and parking areas.

 The project includes the relocation of the bus stop and works on street parking
bays which are required to facilitate the scheme, but will be carried out by others.
Accommodation

 Provide the following accommodation:

o 3 number separate retail units fronting St Johns Road. Units are to be


finished to a shell standard with the exception of glazed shop fronts which
will be provided as part of the base build provision. See drawing 1641 020

o 4 number 2 bed flats (2 on the first floor and 2 on the second floor) See
drawing 1641 021

o 1 number 3 bed flat/apartment on the third floor. See drawing 1641 023

 Provide a minimum of 63 parking spaces (as per the outline planning consent)

 Provide servicing and emergency access to the rear of the units and additional
locations for recycling bin storage.

Key Assumptions

 The scheme will receive outline planning consent based on the January 2014
Planning Committee decision.

 The site is in the ownership of TWBC and no legal reasons exist to prevent the
Council developing the site.

 No underground services, ground conditions or contamination exist on the site


that cannot be dealt with as part of the proposed works.

Constraints

 The site is known to have areas of Japanese Knotweed which will need to be
removed. The treatment of this will be included as part of the proposed site
redevelopment.

 The car park will need to remain operational in some form during the works.

 Some neighbouring buildings may need party wall agreements and agreements
regarding rights of light.

Key Milestone Dates:

 The Stage 2 (Concept Design) information to be submitted to Cabinet on the 18


September 2014.

 Subject to this approval, work on Stage 3 (Developed Design) is anticipated to


begin in September 2014 for a submission of full planning at the end of
November 2014 and appointment of a contractor in June 2015.
 A completion date of the end of July 2016 has been set by TWBC, although this
is subject to review during Stage 3 and Stage 4 (Technical Design & Tender).

Key Risks:

 A separate risk review has been carried out at Appendix F.

Key Issues:

 The business case appraisal for the project has been carried out at Appendix E.

 Following approval to proceed, party wall agreements and any rights of light
agreements would be needed and the Council would appropriate the site to
enable the development to proceed.

 An outline project sequencing and logistics plan will be needed for parking and
access.

 Work to remove the Japanese Knotweed will need to be fully scoped and put into
place.

 A programme of further consultations may be needed prior to a full planning


application or submission for approval of reserved matters being submitted.

 Resolution on how Section 106 agreements are dealt with is needed and a formal
consent for Outline Planning should then be issued.

Stakeholders

 The project is being promoted by TWBC Property Services.

 The project delivery team is currently being led by Faithful and Gould under the
SCAPE framework.

Current Status of Project and Plans:

 The Project has reached completion of RIBA Stage 2 (Concept Design).


Site Plan Drawing 1641 015
Ground Floor Plan Drawing 1641 020
First & Second Floor Plan Drawing 1641 021
Third Floor Plan Drawing 1641 023
Section A-A Drawing 1641 025
North Elevation Drawing 1641 031

You might also like