ID Task Name Duration Start Finish 2022.2 2022.3 2022.4 2022.5
14 16 18 20 22 24 26 28 2 4 6 8 10 12 14 16 18 20 22 24 26 28 31 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 2 4 6 8 10 12 14 16 18 20 22 24 26 28
1.2 Construction of Cofferdam for Upstream 30 2022-02-23 2022-03-24 Construction of Cofferdam for Upstream
1.3 Construction of Gabion Wall Reinforced 30 2022-03-25 2022-04-23 Construction of Gabion Wall & Reinforced concrete walls
concrete walls
1.5 Backfill and gutter construction 20 2022-05-09 2022-05-28 Backfill and gutter construction
2.2 Earth excavation and backfilling 15 2022-02-20 2022-03-06 Earth excavation and backfilling
Laying Raw water main from Intake to Balancing Laying Raw water main from Intake to Balancing tank
3 103 2022-02-15 2022-05-28
tank
3.1 Pipe trace marking,trial pits excavation 10 2022-02-15 2022-02-24 Pipe trace marking,trial pits excavation
3.4 Chamber culvert / bridge crossing etc. 30 2022-04-01 2022-04-30 Chamber & culvert / bridge crossing etc.
3.7 Disinfection Commissioning handing over 7 2022-05-22 2022-05-28 Disinfection & Commissioning & handing over