ID Task Name day

Duration W1 W2 W3 W4 W5 W6 W7 W8
1 s
Medwe Irrigation 43
Network
2 Topographical Works 2 days Foreman,Site Engineer,Surveyor
3 Mobilization 1 day Bobcat,Asphalt Cutter,Compactor,Concrete Mixer,Concrete Vibrator,Drivers,Excavator,Foreman,Pickup,Labors,Roller,Site Engineer,Truck,Water tank,Welding Machine
4 Excavation 17 days Bobcat,Drivers,Excavator,Foreman,Pickup,Labors,Site Engineer
5 Bedding 17 days Bedding Materials,Bobcat,Compactor,Drivers,Foreman,Labors,Pickup,Site Engineer,Truck,Water tank
6 Pipe laying 17 days Electro Fusion Coupler,Foreman,Labors,Pipes,Pipes Fitter,Welding Machine,Site Engineer
7 Surround 17 days Bedding Materials,Bobcat,Compactor,Drivers,Foreman,Labors,Pickup,Site Engineer,Truck,Water tank
8 Backfilling 17 days Bobcat,Compactor,Drivers,Foreman,Labors,Pickup,Site Engineer,Truck,Water tank,Excavated Materials
9 Installation of 1 day Electro Fusion Coupler,Foreman,Labors,Pipes,Pipes Fitter,Welding Machine,Site Engineer
3 Washout
10 Installation of 4 Electro Fusion Coupler,Foreman,Labors,Pipes,Pipes Fitter,Welding Machine,Site Engineer
1 day
Air Release Valve
11 Installation of Foreman,Labors,Pipes,Pipes Fitter,Welding Machine,Site Engineer
1 day
2 Branches
12 Installation of 16 FTO 5 days Electro Fusion Coupler,Foreman,Labors,Pipes,Pipes Fitter,Welding Machine,Site Engineer,Protection Panel Box
13 Installation of 2 days Electro Fusion Coupler,Foreman,Labors,Pipes,Pipes Fitter,Welding Machine,Site Engineer
Main Filtration
Station 12 Concrete,Concrete Labors,Concrete Mixer,Concrete Vibrator,Foreman,Labors,Site Engineer,Steel,
14 Water Tank
Construction of 3 days
WO, 4 AV, and 2
Branches 2 days Bobcat,Compactor,Drivers,Excavated Materials,Foreman,Labors,Pickup,Site Engineer,
Water Tank
Chambers
15 Backfilling around
the Valve Chambers 1 day Base Course,Asphalt,Bobcat,Compactor,Drivers,Foreman,Labors,Pickup,Roller,Site Engineer, Truck, Water Tank
and FTOs 1 day
Bobcat,Drivers,Foreman,Site Engineer,Truck
16 Asphalt Works Foreman,Site Engineer,Surveyor
2 days
17 Cleaning the Site
18 As-Built Dwg

Task Project Summary Inactive Summary Manual Summary External Milestone


Project: Medwe Irrigation Split External Tasks Manual Task Start-only Progress
Network Date: Sun 19-07-20
Milestone External Milestone Duration-only Finish-only Deadline
Summary Inactive Milestone Manual Summary Rollup External Tasks