CLIENT: SAR CONSULTANT: SAUDI CONSULTANT SERVICES MAIN CONTRACTOR: AL MOBTY COMPANY SUBCONTRACTOR: CHINA RAILWAY ENGINEERING GROUP.

2
TWO WEEK PLAN (From 11-Sep-22 to 24-sep-22)
Project Diversion pf existing railway line near Hofuf
OWNER SAUDI RAILWAYS ORGANIZATION
CONSULTANT SAUDI CONSULTING SERVICES
MAIN CONTRACTOR AL MOBTY COMPANY
SUB CONTRACTOR CHINA RAILWAY ENGINEERING GROUP NO.2

Activities: Manpower Equipment/ Machinery

Skilled Labor

Dam truck
Steel fixer
Carpenter

Excavator
UnSkilled

Trailler

Loader
Crane
Planned

Labor
S.No Activity Name Activity Duration Unit Qty
%

A Mobilization
1 Mobilization 14 100%
B      Bridge NO.1
1 Re-excavation of temporary backfilling at abutment 2, backwall area 2 CUM 175 100%
32 7
2 Surface preparation (Cleaning), abutment 2, backwall area 1 Sq.M 64 100%
3 Water proofing with two coal tar, abutment 2, backwall area 2 Sq.M 64 100%
4 Supply and installation of water proof membrane,abutment 2, backwall area 5 Sq.M 64 100%
5 Abutment wall backfilling 6 CUM 319.64 20%
B ·     Bridge NO.2
1 Subcontractor Agreement signing (Jeddah Foundation) 2 100%
2 Purchasing steel for bored piling & delivery to site 14 ton 280 100%
B ·     Bridge NO.3
1 Dilivery of material for gridder 100%
1.1.B Trumpet for three gridder 1 pic 21 100%
1.2.B Saddle (Duct Grout pipe connection), for three gridder 1 pic 15 100%
2 Repainting of steel rebair (small portion), all three gridder 1 100%

27 5
3 Fixing of Trumpit & Saddle, only one gridder 3 100%
27 5
Consultant inspection, for steel, only one gridder 1 100%
4 Form work installation, one girdder 5 100%
Consultant inspection for formwork, one girdder 1 100%
6 Concrete pouring, only one girdder 1 cum 65 100%
7 Removal of form work, one girdder 1 100%
8 Curring of girdder, one girdder 14 10%
D      Bridge NO.4
To arrange with consultant and all other stakeholders to prepare all technical documents and
1 14
drawing as per SAR requirement to get the permit
E Utility crossing
To sign an agreement, with the subcontractor and arrange with STC to get all required 14
technical documents and drawing for transferring cables
F     Earth work ( Cutting) at 28 KM
20 22
1 Cutting at KM 28 14 cum 108,386 5%
Comments: Bridge No.3, three girder remaining. Casting of one grider in two week.
near Hofuf
N
CES

ROUP NO.2

quipment/ Machinery
Water tanker

Compactor
Vibrator

5
5

22