Daily Report for Overhaul Activity UNiT-9

Date: 28.09.2017
Sr. No. Location/Aux Period Work Carried out Remark
1 CRH NRV RHS 27.09.2017 CRH NRV RHS cover retainer removed, WIP Work in progress
to
03.10.2017
2 TDBFP #A IP Extraction 25.09.2017 Valve spindle having scouring marks; ; Internal Work in progress
MOV to inspection and servicing is in progress
03.10.2017
3 Deaerator 25.09.2017 Internal inspection completed; Manhole box Work in progress
to up work in progress
29.09.2017
4 DMCW(TG) PHE #1 22.09.2017 Box up WIP Work in progress
To
28.09.2017
5 CRH NRV LHS 25.09.2017 CRH NRV LHS cover retainer removed; one of Work in progress
to the gasket retainer found stuck causing
01.10.2017 bonnet not going down; Arrangement for
lowering bonnet is in progress;
6 CPP Pit Drain pumps 23.09.2017 CPP Drain pump B pump shaft run out Work in progress
to checked and found bend, WIP; Pump A
05.10.2017 assembled
7 TDBFP Drain Pit 23.09.2017 TDBFP drain pit pump A & B box up done Work completed
to
28.09.2017
8 HPH 6B STEAM EXT 26.09.2017 Valve spindle having scouring marks; Internal Work in progress
MOV to inspection and servicing is in progress
02.10.2017
9 TDBFP B 26.09.2017 HPV dismantling done; Rear side top bearing Work in progress
to removed; LPV servo oil unit and valve
01.10.2017 dismantling done; Oil draining from tank is
completed; Oil tank cleaning done; Work is
being carried out by M/s EM Services
10 Condenser 28.09.2017 Condenser inlet line 1 tube cleaning work Work in progress
to started by M/S BIMCON
05.09.2017
11 WDC A 28.09.2017 Actuator removal WIP Work in progress
to
05.10.2017
12 Service Air Compressor 22.09.2017 LP Element replacement work Work in progress
No.3 to
29.09.2017
13 ACW 25.09.2017 ACW Pump No.1 lifting arrangement WIP Work in progress
to
02.10.2017
14 NDCT 25.09.2017 Dewatering is in progress Work in progress
to
01.10.2017
Section: TM-660MW