Professional Documents
Culture Documents
I. INTRODUCTION
This Health Safety & Environmental (HSE) Plans to discribe the HSE related program and
activities that will be execute on all work, may be internal or external works of “Kota
Kasablanka” (hereinafter, the Project) which is to be carried out by “Lotte Engineering &
Construction –Totalindo Joint Operation” (hereinafter referred as Contractor). The HSE plan
provides the approach, methods and practices that will be implemented to perform the work in a
safe and secure manner in order to protect and preserve the well-being of personel, property and
equipment. The Site HSE Plan is prepared, based on the Contractor’s HSE management system
and the related standards to pursue Contractor’s HSE Policy. The ultimate goal is to provide the
safe working environment by identifying, eliminating and mitigating the risk encounter while
performing the work and thefore protecting the physical integrity of all person, equipment,
property and environment.
All personnel, including subcontractor’s employees, engaged in the project construction
work is responsible for his own safety and the people around him. This is therefore of paramount
importance that each employee understand all safety rules and standards and particularly those
safety rules and standards specifically concerned with the work the perform.
This HSE plan is intended to be complimentary to the general code of practice and to
the existing atatutory regulation of :
Government Laws and Regulations.
Local Municipal Laws and Regulations.
Labour legislation with regard to medical, first aid, safety and training requirement
Employer’s rules, regulations and requirements.
Contractor’s HSE program, procedures, standards and practices.
All contractors / sub-contractor shall adhere to this HSE plan and appoint their HSE Officer
or so acting that must be approved prior to commencement of the work. They are contacted
to perform for LTJO. The HSE plan will be reviewed & revised by the HSE Manager
periodically as and when required /6 monthly review meeting.
II. DEFINITION
For the purposes of this Procedure, the following words shall have the meanings listed Below :
Employer : PT. Elite Prima Hutama
Project : Kota Kasablanka Phase 2
KOTA KASABLANKA 3
PT. ELITE PRIMA HUTAMA ( Member of Pakuwon Group )
Location : Contract No Document No
KOTA KASABLANKA 3 PROJECT A020 KK3-PR-00-00001D
Title : Page 0 1 2 3 4
Construction Site Health, Safety & Environment 2 of 32 X
III. PURPOSE
The following document is designed to provide a detailed action plan.The items are
contained safety manual. This safety plan identifies steps that should be taken by LTJO to
achieve the standard of safety requirement based on safety policy statement.
V. ORGANIZATION
KOTA KASABLANKA 3
PT. ELITE PRIMA HUTAMA ( Member of Pakuwon Group )
Location : Contract No Document No
KOTA KASABLANKA 3 PROJECT A020 KK3-PR-00-00001D
Title : Page 0 1 2 3 4
Construction Site Health, Safety & Environment 4 of 32 X
HSE MANAGER
PARAMEDIC ADMIN
SAFETY PROTECTION
CLEANING SERVICE
Responsible for all over safety in work of the entire project for ensuring LTJO
supervision and management, comply with LTJO Safety Policy.
B. FIELD SUPERVISORS
LTJO will endeavor to ensure every person who perform work under their reins who can
be affected by OHS Impact are competent persons based on proper education, training or
experience and maintain related work evidence. LTJO also must determine, implement and
maintain procedure to make persons who work under reins aware to HSE impact
responsibility and procedure
Supervisors supervise workers in work directly regarding work procedures, including
safety procedures, at anytime or any where, necessary. Supervisor also check any violations
KOTA KASABLANKA 3
PT. ELITE PRIMA HUTAMA ( Member of Pakuwon Group )
Location : Contract No Document No
KOTA KASABLANKA 3 PROJECT A020 KK3-PR-00-00001D
Title : Page 0 1 2 3 4
Construction Site Health, Safety & Environment 5 of 32 X
of safety procedures or unsafe work conditions, and if find the case,foreman will stop work
immediately and take necessary action to correct worker and or facilites before start working
more. Supervisor conduct a daily tool-box meeting for about five minutes regarding work
procedures to be carried out.
C. HSE MANAGER
D. HSE OFFICER
Here are job description of HSE Officer :
2) Check persons and vehicles that entering and leaving through the gates.
3) Check and confirm materials, equipment and tools that be brought in / out the site.
4) Record material passes
5) Interrogate individuals entering or leaving the site.
6) Take over and compile information and report from the previous guards, and submit it
to the security coordinator.
“ No Workers Can Going Inside To The Working Area Without ID Badge and wearing
vest ”.
15. Gate entrance.Based on this project the Entrance Gate are been split to:
a. Gate 1, location LTJO construction area, this gate are proposed especially for visitor.
b. Gate2, location LTJO construction area, this gate are proposed for in/out material
vehicle and Heavy Equipment of owner.
c. Gate General, This gate are proposed LTJO employees/subcontractor and visitor as
accessway to entrance construction area.
16. Use of subcontractors. Pricipal subcontractor :
a. Principal subcontractor are those who are engaged on sections of the contract
providing their own plant and equipment and who may also be responsible for
supplying some materials.
All subcontractors will be vetted prior to starting of the project. Subcontractor
agreement will be completed ang signed by each subcontractor to ensure that they are
fully aware of KOKAS 3 PROJECT quality and safety requirements. Principal
subcontractor will generally provide their own site management and site supervision.
However, all their activies will be closely monitored by the dedicated LTJO site
supervisory team.
b. Minor Subcontractors, Labour-Only Subcontractor
These are normally smaller companies or labour-supply agents where safety
awareness will not have been assessed and any acknowledgement of obligation would
be minimal. These include :
Carpenters
Steel fixers
Labour agents
In general employees of these companies will be treated as if they were direct
employees and will be closely supervised by LTJO staff on site.
2. SAFETY TALKS
Safety Talks, on subjects of site safety in particular and occupational health in
general will be conducted on the LTJO Project and will be held on friday. In
Saturday after safety talk all employee and staff will do general cleaning. To inform
all employee of developments in Safe practices and to convey at an understandable
level, the requirements of the project.
4. SAFETY CAMPAIGN
Monthly program, this program puspose to increase employee’s knowledge
about accupational safety and health with exiting media.
5. TRAINING
Purpose of the training program to increase the knowledge and awareness of all
workers to safe working processes and safely.
The training program must be tailored to the needs of work in the field so that the
training must be right on target and objectives.
Among the training that needs to be held as follow:
5.1 Lifting dan rigging
5.2 Working at height
5.3 Fire prevention
5.4 Electrical tool handling “ Bar cutting, Bar banding “
5.5 Confined space work
5.6 Hot work job
KOTA KASABLANKA 3
PT. ELITE PRIMA HUTAMA ( Member of Pakuwon Group )
Location : Contract No Document No
KOTA KASABLANKA 3 PROJECT A020 KK3-PR-00-00001D
Title : Page 0 1 2 3 4
Construction Site Health, Safety & Environment 10 of 32 X
7. SAFETY INDUCTION
For all new employee in the new project, before they start to work they must
follow induction training by Safety Department then they will be given ID Card
( unless the owner and visitors ) when they have passed induction. The content of
induction area:
a) LTJO Safety policy Statement
b) Basic Safety Knowledge
c) Basic Rules of Safety Permit System
d) HSE Guidelines LTJO
e) Hazard Indentification
f) Personnal Protective Equipment
8. VIOLATION
To motivate workers who have worked without accidents or any significant
violation of safety. Prior to the commencement of work on any worksite, LTJO
agree on a safety objective with respect to personnel and equipment, lost time
accident or pollution will be used as the reference for the evaluation of LTJO safety
performance. LTJO employee and sub-contractor will be get punishment as a
violation letter if they do not follow safety regulation.
B. SAFETY INSPECTION
1. General Safety Inspection
As part of daily activities and when assigning personnel to work stations. All
supervisors examine area facilities, equipment tools and materials that used by the
employee systematically as: bored machine, circle saw, bar cutting, bar banding,
cutting wheel, welding machine, cable power, lighting lamp etc. Safety department
monitor those same areas as within their normal job scope continually.
Material Safety Data Sheets (MSDS) of all chemicals and orther harmful
subtances used by LTJO on the site will be made available to the work force and
LTJO safety and related disciplines
1. Safety helmet
2. Body vest
3. Safety shoes and boot
4. Hand gloves ( if, necessary )
5. Safety belt for work at height above 2 meters
6. Ear protection ( if, necessary )
7. Safety Glasses (if, necessary )
KOTA KASABLANKA 3
PT. ELITE PRIMA HUTAMA ( Member of Pakuwon Group )
Location : Contract No Document No
KOTA KASABLANKA 3 PROJECT A020 KK3-PR-00-00001D
Title : Page 0 1 2 3 4
Construction Site Health, Safety & Environment 13 of 32 X
B. Working At Height
All activities and moving will perform at elevated above 2 meter, worker must use
safety belt and safety harness or be provided scaffolding, working platform, handrail and
ladder for access. Safety sign board and barricade area must be provided under the work
area when the working are perform at height. Dropping or throwing anything from an
elevated height are prohibited.
1. High of upright frame willnot exceed two(2) meters and spacing will not exceed 1.8
meters. Uprightframe must be tied to cross braces and ledger frames.
2. Spacing of ties or stays will not exceed five(5) meters verticaly and 5.5. meters
horizontaly.
3. For erecting and dismantling of scaffolds will be prepared by qualified personnel.
4. Inspection will be conducted by Safety Department for working platform or
scaffoldsand a tag system will be estlabished, and made known to all personnel
concerned.
5. Competent and authorized scaffold inspector will be given assign.
6. At the external Scaffolding LTJO will be covered with Safety Net.
D. Grinding Welding and Cutting
All grinding, welding and cutting equipments will be inspected daily. Defective
apparatus and equipment will be replace or repaired. Combustible material and
equipment such as gas cylinders, rubber hoses and debris will be removed or shielded
from heat, spark and slag from grinding, welding and cutting. Flash back arestor (safety
valve) will be provided at each cylinder bottle of cutting equipment.
3. Rigger must be check and ensure the binding has been conducted good and right
4. When lowering or lifting material from/to the ground, suitable devices, such as a
chute, bag or container with a rope, will be used.
5. During such work, a watchman will carefully monitor, and “No Entry” and “Danger
Overhead” signs, and rope off around the work area will be provided.
6. When lifting a load, nobody will enter under the load..
7. During erecting unstable steel structures, or before the structures become stable using
proper permanent framing and fittings, false work such as guy wires or stays or
temporary supports will be provided to prevent their collapse.
8. Temporary access ladders for climbing columns, hanging personnel cage for
fastening bolts and nuts or welding, and pieces for installing life lines will be studied
and provided before installation of steel structures.
F. ELECTRICAL AND INSTRUMENT WORK ON CONTRUCTION AREA
1. Temporary Electrical Supply Plan
Before the commencement of Fabrication work on the site, an overall electricity
supply plan for fabrication including, electricity demand forecast, transformer banks,
allocation of distribution.Boards, distribution cable routing and rating, etc. will be
prepared and reviewed by qualified electrical engineers and fabrication planning
personnel.
2. Electrical workers
Electrical work including installation, testing, inspection and maintenance will only
be executed by competent electrician/workers and supervised by qualified
supervisors. The designated supervisor will directly in
struct foreman and workers, and before starting the work, he will explain the scope of
the work, work location, work procedure, time, schedule, proper personal protective
equipment (PPE), proper equipment and tools to be used, allocation of workers, etc.
Throughly to all workers concern.
3. Insulation
During routine inspections and tests, the insulation of electrical equipment and the
associated items will be checked. Where it is found to be damaged or incomplete the
item will be removed from the service.
All wiring will be insulated throughly and where there is the possibility of physical
KOTA KASABLANKA 3
PT. ELITE PRIMA HUTAMA ( Member of Pakuwon Group )
Location : Contract No Document No
KOTA KASABLANKA 3 PROJECT A020 KK3-PR-00-00001D
Title : Page 0 1 2 3 4
Construction Site Health, Safety & Environment 15 of 32 X
damage, the wiring must be further protected either by metal conduits or armoring.
Insulation shall be provided at all locations where it is possible for workers to come
into contact with live equipment.
4. Earthing
Earth cables will be tested for continuity and resistance to ensure they are effective
forthat particular application. Remedial action will be taken where they are found
inadequate or ineffective. Until such remedial action is taken the item of equipment
will be taken out of service.
5. Isolation Procedure
Detailed as part of the Permit-To-Work system, isolations are intended to prevent
accidental contact with live electrical equipment.
Work shall officially be carried out on electrical systems until a competent or
authorized person has indicated, in writing, on a work permit that he has isolated the
system by means of locks using the lock out/tag out procedure. The person issuing the
work permit must witness the isolation.
6. Work in the Vicinity of Live Equipment
All electrical systems shall be signed with appropriate warning signs. Work adjacent
to electrical systems shall be subject to work permit procedures even where
surrounding areas do not come under such procedures.
3. House Keeping
Platforms and walkways at elevated locations will be kept clear of any obstacles,
material, tools, etc. which might fall and injure personnel below. These articles will
be bundled or put in cases or bags so as to prevent their falling and injuring persons
or objects underneath their location. Any debris and scraps will be immediately
removed from elevated location.
I. CLEAN UP
LTJO will keep its work area in a neat, clean and safe condition all times and remove
from LTJO premises and vicinity and properly dispose of all debris and rubbish caused
by LTJO Upon completion of work, LTJO will promptly remove all scrape and waste
from companys premises leaving vicinity clean, safe and ready for use.
the particular type of equipment. Operators’ qualification for cranes and heavy
equipment are subject to review by the competent equipment supervisor and safety
manager.
B. Scheduled Inspection and Maintenance
All Subcontractors' construction equipment and vehicles are to be periodically
inspected and maintained according to pre-determined schedule. Complete record of all
inspection and maintenance are to be maintained for Contractor's review and approval.
Construction equipment and vehicles found to be unsafe for operational use shall be
tagged “Out of Service, Do not use” at the operator’s position. Their use shall be
strictly prohibited until they are repaired and certified as fit for use.
C. Equipment Operator Qualification and Training
Contractor and subcontractors shall review the qualifications of all crane
operators, crane maintenance personnel and other mobile equipment operators in
accordance with the following procedure :
(1) Possession of valid driving a license from the government and job site
authorization card signed by Contractor’s HSE Manager.
(2) Successful completion of a practical operating examination administered by
competent and authorized personnel.
(3) Training - Operator responsibilities, familiarity and comprehension concerning all
crane safety and O&M requirements, load capacity charts, rigging methods and
practices, hand signals and other requirements will be examined by competent and
authorized personnel.
D. Guarding and Safety Devices
Contractor’s Site management and supervision shall ensure that all equipment
and vehicles are equipped with guards and that all safety devices required by law and
site regulations are fitted and effective.
E. Construction Equipment and Vehicles Identification
All construction equipment and vehicles will be clearly identified with the
appropriate names and equipment serial numbers.
must be equipped with the required safety equipment in good working order, e.g.
reversing arms, flashing lights, etc.
1) Preventive maintenance will be performed on all vehicles on a monthly schedule.
All safety features will be checked and repaired as necessary to ensure proper
operation.
2) Drivers and operators will perform a pre-operational check of their assigned
vehicles and equipment at the start of each working day.
3) Each driver shall keep a record of the daily and monthly pre-operational vehicle
and equipment checks.
D. Motor Vehicle Accident Investigations
Contractor’s site management and supervision shall give appropriate instructions
and ensure full compliance of the following requirements: All motor vehicle and
equipment accidents shall be reported and investigated. Investigation and causation
analysis is necessary to implement corrective actions to prevent recurrence.
E. Traffic Controls & Signs
Contractor’s site management and supervision will ensure that traffic control and
signs are displayed as required for the site.
The following traffic signs are mandatory as required by the conditions of site :
1) Stop and yield signs
2) Speed limit signs as follows :
Maximum speed limit on site is 10 km/h
3) Pedestrian crossings
4) No parking or standing
5) No vehicle entry
6) No passing or overtaking
7) Low clearance - overhead obstruction or utilities
8) Temporary Traffic Diversions
plans will include an emergency evacuation plan. Fire drills and emergency
evacuation exercises will be conducted regularly.
Contractor and subcontractors will implement fire prevention by house
keeping, no smoking in any place, training, meetings, safety patrol, site inspection,
daily work instructions, etc. Contractor and subcontractor supervision will make
workers fully aware of fire prevention policy and strategy through these activities.
1) Fire Fighting Equipment
Contractor’s site management will ensure that adequate and well-maintained
fire extinguishers are provided for each construction site. Contractor’s site
management will also ensure that subcontractors provide an adequate quantity of
well-maintained extinguisher for their premises, equipment and vehicles.
Contractor’s site management will ensure that workmen are trained in the use of
fire extinguishers, and the basic skills of safe fire fighting.
2) Fire Wardens
As part of the overall fire prevention effort, the fire wardens will be appointed
from within the subcontractor work force. Contractor and subcontractors will
jointly implement fire fighting and prevention training and certification of the fire
wardens.
3) Fire and Emergency Simulations
Contractor will arrange simulation opportunities for fire extinguisher training
and site evacuations every six months.
4) Reporting a Fire
Fires will be reported to Contractor’s Site Manager and the Site HSE
Manager. Then, corrective actions can be determined and taken to prevent
recurrence.
the site fully understand the procedures, and the actions to be taken during
emergency situations. The following will be considered to establish emergency
procedures:
1) Coordinate with the Employer’s representative in establishing emergency
procedures.
2) Make a list of available emergency services and confirm their communication
channels.
3) Ensure that subcontractors clearly understand their responsibility and role in the
site emergency procedures.
4) Designate first aid/medical supplies, and other material and equipment that may
be required for emergency use.
5) Set up emergency response teams.
6) Determine emergency evacuation routes for work areas and the construction
site.
7) Establish a personnel staging area or assembly points for evacuees.
8) Make sure that all personnel clearly understand emergency warning siren
signals or other warning signals used by the Employer, Contractor and/or other
authorities.
9) Provide summarized communication diagrams and necessary maps, and display
them at proper places in the site.
10) Designate a supervisor to conduct a head count and give instructions to
evacuees as necessary.
11) Post emergency information for each work area on the site.
12) Conduct emergency procedure drill periodically.
Excavation
Demolition
Working at height
Temporary/site electrics
Movement of Plant and Vehicle
KOTA KASABLANKA 3
PT. ELITE PRIMA HUTAMA ( Member of Pakuwon Group )
Location : Contract No Document No
KOTA KASABLANKA 3 PROJECT A020 KK3-PR-00-00001D
Title : Page 0 1 2 3 4
Construction Site Health, Safety & Environment 26 of 32 X
Lifting operations
Dust/debris and noise control
Interfacing with the existing Buildings or other facilities .
Kecil Padamkan
Karyawan Fire levels Sendiri
Setiap safety subcont memimpin penyelamatan
manusia dan asset. Karyawan menggunakan
masker dan helm.
HRD Investigasi
Di bantu team security
1. Working at height
3. Hot works/welding
8. Deep excavation
And other work requested by EPH. This permit will cover the safe system of
work for operations on existing services. Recommendations are included for a
Permit-to-Work system which can be used as a benchmark for any system
promoted by the client. Prior to the commencement, during work and other
check list/inspection form are also provided.
If the system is already available from EPH, then this will be used in
KOTA KASABLANKA 3
PT. ELITE PRIMA HUTAMA ( Member of Pakuwon Group )
Location : Contract No Document No
KOTA KASABLANKA 3 PROJECT A020 KK3-PR-00-00001D
Title : Page 0 1 2 3 4
Construction Site Health, Safety & Environment 28 of 32 X
The HSE Officer will ensure that all lost time accident, accident
involving third parties and dangerous occurrences are investigated to
determine the basic causes and, what corrective action need to be taken
to prevent re occurrences. All such investigation report when completed
will again be forwarded to the KOKAS 3 Project Manager or Project
Director for review.
b. Immediate Reports
The HSE Manager will also prepare a brief report for immediate
distribution to Project manager
intoxicated will be immediately refused to access to the site or removed from its
normal duties.