PROJECT PROGRESS
Updated on: January 10, 2020
Week No. W2
Item PROJECT/ACTIVITY Start End Planned Actual 43840Current Status: -409mmmm d, yyyy
Duration Progress
B REPAIR OF DAMAGED PIPING 23-May-2018 ### (2039) 93%
B.1 Tendering & Contracting 23-May-2018 4-Feb-2019 257 100% * "Caution definitive" delivered on 04/02/2019
* long lead items arrived at Rades-Port on 11/05, cleared and
delivered in W28
* 3rd party SIS approved CMA work procedures
B.2 Procurement 14-Feb-2019 10-Jul-2019 146 100% * PQR (construction) was approved by "SIS" on 29/04
* CMA welders undergone Qualification Tests on 02/05 under
SIS witness
* PQR (repair) was approved by 3rd Party on 03/06
* Ezz#9 Works started on 15/07 (survey + stringing)
* Welding activity started on 17/07/2019
* The routing of Ezz#9 F/L at CPF changed to overcome
obstacles that stand in the way (Junk area + Ezz#4 reinforced-
B.3.1 Construction of Ezz#9 New Flow line 15-Jul-2019 6-Sep-2019 53 100% concrete pad), as agreed with F.Sup + CMA + 3rd party SIS
* HT @240psi PASS ---> OK on 31/08
* Ezz#9 FL commissioned on 06/09
* Well was shut-in during 4days
* Provisional acceptance carried out on 18/10
* HDPE line construction completed
B.3.2 Construction of 3" Fresh Water New Supply Line 1-Aug-2019 12-Oct-2019 72 100% * HT @14bar @30°C PASS ---> OK on 12/10
* Provisional acceptance carried out on 18/10
* Replacement of 09 leaking valves at 50M7 ended on 18/09
(General shutdown of 14 hrs)
* Completed the replacement of risers & connecting lines at
CPF & WH on 20/09
* HT @240psi failed on 21/09
* Replaced the 1st Leaking section (15m). 2nd HT failed on
23/09
B.4.1 Repair of Ezz#1 FL 13-Sep-2019 2-Oct-2019 19 100%
* HT @240psi of Ezz#7-to-Ezz#1 section failed on 25/09. HT
@240psi of Ezz#7-to-CPF section failed on 27/09
* Replaced the 2nd Leaking section (@Ezz#7) on 30/09.
Flushed Ezz#1 line during 8hr on 01/10
* HT of Ezz#1 FL @120psi failed on 02/10
* Well was shut-in during 6days
* Ezz#1 FL repair project aborted
* Ezz#17 riser @Ezz#1 area installed on 22/09
* Ezz#17 riser @CPF installed on 27/09
B.4.2 Repair of Ezz#17 FL 24-Sep-2019 3-Oct-2019 9 100% * HT @240psi PASS ---> OK on 29/09
* Ezz#17 FL connected to Ezz#1 wellhead on 03/10
(temporarily)
* New riser & connecting line @CPF side replaced on 12/10
* WH Riser replaced on 26/10
B.4.3 Repair of Ezz#2 FL 23-Sep-2019 27-Oct-2019 34 100% * HT @240psi PASS ---> OK on 27/10
NB: Ezz#2 line (700m) will be used as a section of Ezz#1 NEW
FL (1900m)
* Ezz#18 risers & WH connecting line replaced
* HT @120psi PASS ---> OK on 12/10
B.4.4 Repair of Ezz#18 FL 14-Sep-2019 14-Nov-2019 61 100% * FL connecting line @CPF constructed and installed
* HT of connecting line @240psi PASS ---> OK on 14/11
* New risers & connecting lines @CPF & WH replaced
B.4.5 Repair of Ezz#11 FL 15-Sep-2019 26-Oct-2019 41 100% * HT @120psi PASS ---> OK on 26/10
* FL commissioned on 26/10
* HT of connecting line @240psi PASS ---> OK on 14/11
B.5.1 Repair of Ezz#10 FL 31-Oct-2019 ### (152) 80% * Prefab of WH riser completed
* Ezz#10 Inj. line route survey done
* CMA Work procedure is under approval by MARETAP
* With the aim to minimize the well shut in period, risers replacement
will be executed at the same time as the tie-in of Ezz#10 New Inj. Line
"B.5.2"
* Well shut-in period is estimated 4 days
B.5.2 Construction Ezz#10 New Inj. Line ### ### (130) 38%
* Fabrication of process piping was completed on 24/08
*dismainting of this line is finished on 06/01/2020
B.6.1 Repair of Process Piping "50-117A1-6-PW"(total replacement) 14-Aug-2019 ### (153) 91% *stringing of pipe spools is ongoing(90%)
*installation works ongoing(40%)
* Painting work completed
* Installed and commissioned on 30/11
B.6.2 Repair of Process Piping "50-125A1-3-CR-IH-ET"(total replacement) 24-Aug-2019 30-Nov-2019 98 100% *Heat insulation lagging works were completed(100%)
*painting works are ongoing
* Fabrication of process piping was completed on 12/09
* Painting work completed
* the removal of the old line is completed
* Installation is finished
B.6.3 Repair of Process Piping "50-143A1-4-CR-IH-ET"(total replacement) 31-Aug-2019 10-Jan-2020 132 100% * welding works and ndt inspection are finished
* HT @240psi PASS ---> OK on 12/12
*line commisionned on 10/01/2020
*heat lagging works is finished
* Fabrication of process piping was completed on 16/09
*waiting for the shut down of EZZ 10 to complete the tie in
works with suction line of triplex pump
B.6.4 Repair of Process Piping "50-137A1-4-CR"(partial replacement) 13-Sep-2019 10-Jan-2020 119 100% *Hydraulic testing of all bolted spools @ 240psi for 2 hrs
-->ok27/12,
tie in works commisionning finished on 10/01/2020
* Painting work completed
* a leak was founded during flushing activity
*a wall thickness measurement was performed to check the
integrity the hole line==>a thinner area was detected with a
length of 1.3 m
* Repair is completed: elbow E12 as per SOW with additional
length (70cm of sch 40 A106 pipe) and the leaking area(1,3m of
sch 40 A106 pipe as per inspection report
* NDT is completed
B.6.5 Repair of Process Piping "50-185A1-4-CR"(partial replacement) 28-Nov-2019 13-Dec-2019 15 100% *1st hydraulic testing was performed on 07/12/2019==>test is
failed and two additional leaks were found and temporary
repaired by clamps
*second hydraulic testing was performed on 09/12/2019 for 5
hrs==>test was ok
repair works and ndt inspection are finished
* HT @240 for 2 hrs passed successfully
*line commisioned on 13/12
* Fabrication of process piping was completed on 17/08
*dismounting of the old line is finished
B.6.6 Repair of Process Piping "50-214A1-6-PW"(total replacement) 15-Aug-2019 ### (148) 97% *installation works are ongoing(90%=
* Painting work completed
* Fabrication of process piping was completed on 28/08
*dismounting of the old line is finished
B.6.7 Repair of Process Piping "50-126A1-8-PW"(total replacement) 17-Aug-2019 ### (149) 95% *fitting and welding works were finished
* Painting work completed
* Prefabrication completed
* Removal of old line is Finished on 15/12/2019 (100%)
* Installation is finished
*NDT inspection finished on 26/12
B.6.8 Repair of Process Piping "50-183A1-6-PW"(total replacement) 3-Sep-2019 10-Jan-2020 129 100% *hydrotest @240 Psi for 2h -->ok 27/12 for the 1st section and ok
28/12 for the second one
commisionning on 10/01/2020
* Painting work completed
* Fabrication of process piping was completed on 03/09
* painting works will be performed in fiew days
B.6.9 Repair of Process Piping "50-128A1-PW-IH-ET"(partial replacement) 28-Aug-2019 28-Dec-2019 122 100% *dismounting of this line is finished
*NDT inspection s finished and
HT@240 Psi for 2Hrs -->ok on 28/12
*commisionned on 28/12