0% found this document useful (0 votes)
64 views4 pages

PROJECT PROGRESS Sample

The document provides a progress update on various repair and construction projects related to damaged piping. It details the status of projects to repair flow lines for wells Ezz#1, Ezz#2, Ezz#10, Ezz#11, Ezz#17, and Ezz#18, as well as construction of new flow and injection lines. The progress ranges from 80% to 100% complete across the various sub-projects as of January 2020.

Uploaded by

Majdi Jerbi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
64 views4 pages

PROJECT PROGRESS Sample

The document provides a progress update on various repair and construction projects related to damaged piping. It details the status of projects to repair flow lines for wells Ezz#1, Ezz#2, Ezz#10, Ezz#11, Ezz#17, and Ezz#18, as well as construction of new flow and injection lines. The progress ranges from 80% to 100% complete across the various sub-projects as of January 2020.

Uploaded by

Majdi Jerbi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd

PROJECT PROGRESS

Updated on: January 10, 2020


Week No. W2

Item PROJECT/ACTIVITY Start End Planned Actual 43840Current Status: -409mmmm d, yyyy
Duration Progress
B REPAIR OF DAMAGED PIPING 23-May-2018 ### (2039) 93%

B.1 Tendering & Contracting 23-May-2018 4-Feb-2019 257 100% * "Caution definitive" delivered on 04/02/2019

* long lead items arrived at Rades-Port on 11/05, cleared and


delivered in W28
* 3rd party SIS approved CMA work procedures
B.2 Procurement 14-Feb-2019 10-Jul-2019 146 100% * PQR (construction) was approved by "SIS" on 29/04
* CMA welders undergone Qualification Tests on 02/05 under
SIS witness
* PQR (repair) was approved by 3rd Party on 03/06

* Ezz#9 Works started on 15/07 (survey + stringing)


* Welding activity started on 17/07/2019
* The routing of Ezz#9 F/L at CPF changed to overcome
obstacles that stand in the way (Junk area + Ezz#4 reinforced-
B.3.1 Construction of Ezz#9 New Flow line 15-Jul-2019 6-Sep-2019 53 100% concrete pad), as agreed with F.Sup + CMA + 3rd party SIS
* HT @240psi PASS ---> OK on 31/08
* Ezz#9 FL commissioned on 06/09
* Well was shut-in during 4days
* Provisional acceptance carried out on 18/10

* HDPE line construction completed


B.3.2 Construction of 3" Fresh Water New Supply Line 1-Aug-2019 12-Oct-2019 72 100% * HT @14bar @30°C PASS ---> OK on 12/10
* Provisional acceptance carried out on 18/10

* Replacement of 09 leaking valves at 50M7 ended on 18/09


(General shutdown of 14 hrs)
* Completed the replacement of risers & connecting lines at
CPF & WH on 20/09
* HT @240psi failed on 21/09
* Replaced the 1st Leaking section (15m). 2nd HT failed on
23/09
B.4.1 Repair of Ezz#1 FL 13-Sep-2019 2-Oct-2019 19 100%
* HT @240psi of Ezz#7-to-Ezz#1 section failed on 25/09. HT
@240psi of Ezz#7-to-CPF section failed on 27/09
* Replaced the 2nd Leaking section (@Ezz#7) on 30/09.
Flushed Ezz#1 line during 8hr on 01/10
* HT of Ezz#1 FL @120psi failed on 02/10
* Well was shut-in during 6days
* Ezz#1 FL repair project aborted
* Ezz#17 riser @Ezz#1 area installed on 22/09
* Ezz#17 riser @CPF installed on 27/09
B.4.2 Repair of Ezz#17 FL 24-Sep-2019 3-Oct-2019 9 100% * HT @240psi PASS ---> OK on 29/09
* Ezz#17 FL connected to Ezz#1 wellhead on 03/10
(temporarily)

* New riser & connecting line @CPF side replaced on 12/10


* WH Riser replaced on 26/10
B.4.3 Repair of Ezz#2 FL 23-Sep-2019 27-Oct-2019 34 100% * HT @240psi PASS ---> OK on 27/10
NB: Ezz#2 line (700m) will be used as a section of Ezz#1 NEW
FL (1900m)

* Ezz#18 risers & WH connecting line replaced


* HT @120psi PASS ---> OK on 12/10
B.4.4 Repair of Ezz#18 FL 14-Sep-2019 14-Nov-2019 61 100% * FL connecting line @CPF constructed and installed
* HT of connecting line @240psi PASS ---> OK on 14/11

* New risers & connecting lines @CPF & WH replaced


B.4.5 Repair of Ezz#11 FL 15-Sep-2019 26-Oct-2019 41 100% * HT @120psi PASS ---> OK on 26/10
* FL commissioned on 26/10

* HT of connecting line @240psi PASS ---> OK on 14/11


B.5.1 Repair of Ezz#10 FL 31-Oct-2019 ### (152) 80% * Prefab of WH riser completed
* Ezz#10 Inj. line route survey done
* CMA Work procedure is under approval by MARETAP
* With the aim to minimize the well shut in period, risers replacement
will be executed at the same time as the tie-in of Ezz#10 New Inj. Line
"B.5.2"
* Well shut-in period is estimated 4 days

B.5.2 Construction Ezz#10 New Inj. Line ### ### (130) 38%

* Fabrication of process piping was completed on 24/08


*dismainting of this line is finished on 06/01/2020
B.6.1 Repair of Process Piping "50-117A1-6-PW"(total replacement) 14-Aug-2019 ### (153) 91% *stringing of pipe spools is ongoing(90%)
*installation works ongoing(40%)
* Painting work completed

* Installed and commissioned on 30/11


B.6.2 Repair of Process Piping "50-125A1-3-CR-IH-ET"(total replacement) 24-Aug-2019 30-Nov-2019 98 100% *Heat insulation lagging works were completed(100%)
*painting works are ongoing
* Fabrication of process piping was completed on 12/09
* Painting work completed
* the removal of the old line is completed
* Installation is finished
B.6.3 Repair of Process Piping "50-143A1-4-CR-IH-ET"(total replacement) 31-Aug-2019 10-Jan-2020 132 100% * welding works and ndt inspection are finished
* HT @240psi PASS ---> OK on 12/12
*line commisionned on 10/01/2020
*heat lagging works is finished

* Fabrication of process piping was completed on 16/09


*waiting for the shut down of EZZ 10 to complete the tie in
works with suction line of triplex pump
B.6.4 Repair of Process Piping "50-137A1-4-CR"(partial replacement) 13-Sep-2019 10-Jan-2020 119 100% *Hydraulic testing of all bolted spools @ 240psi for 2 hrs
-->ok27/12,
tie in works commisionning finished on 10/01/2020
* Painting work completed

* a leak was founded during flushing activity


*a wall thickness measurement was performed to check the
integrity the hole line==>a thinner area was detected with a
length of 1.3 m
* Repair is completed: elbow E12 as per SOW with additional
length (70cm of sch 40 A106 pipe) and the leaking area(1,3m of
sch 40 A106 pipe as per inspection report
* NDT is completed
B.6.5 Repair of Process Piping "50-185A1-4-CR"(partial replacement) 28-Nov-2019 13-Dec-2019 15 100% *1st hydraulic testing was performed on 07/12/2019==>test is
failed and two additional leaks were found and temporary
repaired by clamps
*second hydraulic testing was performed on 09/12/2019 for 5
hrs==>test was ok
repair works and ndt inspection are finished
* HT @240 for 2 hrs passed successfully
*line commisioned on 13/12

* Fabrication of process piping was completed on 17/08


*dismounting of the old line is finished
B.6.6 Repair of Process Piping "50-214A1-6-PW"(total replacement) 15-Aug-2019 ### (148) 97% *installation works are ongoing(90%=
* Painting work completed

* Fabrication of process piping was completed on 28/08


*dismounting of the old line is finished
B.6.7 Repair of Process Piping "50-126A1-8-PW"(total replacement) 17-Aug-2019 ### (149) 95% *fitting and welding works were finished
* Painting work completed
* Prefabrication completed
* Removal of old line is Finished on 15/12/2019 (100%)
* Installation is finished
*NDT inspection finished on 26/12
B.6.8 Repair of Process Piping "50-183A1-6-PW"(total replacement) 3-Sep-2019 10-Jan-2020 129 100% *hydrotest @240 Psi for 2h -->ok 27/12 for the 1st section and ok
28/12 for the second one
commisionning on 10/01/2020
* Painting work completed

* Fabrication of process piping was completed on 03/09


* painting works will be performed in fiew days
B.6.9 Repair of Process Piping "50-128A1-PW-IH-ET"(partial replacement) 28-Aug-2019 28-Dec-2019 122 100% *dismounting of this line is finished
*NDT inspection s finished and
HT@240 Psi for 2Hrs -->ok on 28/12
*commisionned on 28/12

You might also like