You are on page 1of 1

CLIENT : M/s.

ONGC
Contractor : M/s. LTHE
Sub‐Contractor : M/s DOEPL
PROJECT : Balance work for Pipeline Replacement Project ‐ 4

CA : M/S. ABSIV (India) Pvt.Ltd. PRODUCTION DATE: 30.03.2018

TPI : M/S. DNV‐GL REPORTING DATE : 31.03.2018


Location : NLM10 Platform
Barge: Ocean303
Achieved Cumulative Balance Achieved % Cumulative
Sr. no Description UOM Scope Alloted % Balance % Remarks
Qty.Today Qty. Qty. Today %
Over all Progress ( A+B+C) 100.00% 0.50% 100.00% 0.00%

A) Piping

1 Erection of piping spools Nos 14 20.00% 0 14 0 0.00% 20.00% 0.00%

Fit up of (Field Joints) Nos 27 13.00% 0 27 0 0.00% 13.00% 0.00%


2
Fit up of (Modification joints) Nos 7 0.00% 0 7 0 0.00% 0.00% 0.00%

3 Fit up Adiitional work Nos N/A N/A N/A N/A N/A NA N/A N/A

Welding (Field Joints) Inch Dia 83.5 29.00% 0 83.5 0 0.00% 29.00% 0.00%
4
Welding (Modification joints) Inch Dia 42 0.00% 0 42 0 0.00% 0.00% 0.00%

5 Welding of Additional work Inch Dia N/A N/A N/A N/A N/A NA N/A N/A

6 Installation of Piping Supports Nos. 6 7.00% 0 6 0 0.00% 7.00% 0.00%


NDT of (Field Joints)
Nos 27 12.00% 0 27 0 0.00% 12.00% 0.00%
7
NDT of (Modification Joints) Nos 7 0.00% 0 7 0 0.00% 0.00% 0.00%

8 Hydrotesting of Piping Loops Nos. 2 4.00% 0 2 0 0.00% 4.00% 0.00%

9 Hook up/Tie in points Nos. 2 4.00% 0 2 0 0.00% 4.00% 0.00%

10 Painting Touch-up work lot 1 1.00% 0.5 1 0 0.50% 1.00% 0.00%

11 Insulation lot N/A N/A N/A N/A N/A NA N/A N/A

TOTAL-A 90.00% 0.50% 90.00% 0.00%

B) DEMOLITION

1 NIL lot 0 0.00% 0 0 0 0.00% 0.00% 0.00%

TOTAL-B 0 0.00% 0.00% 0.00% 0.00%

C) ELECTRICAL & INSTRUMENTATION

1 Instrument Installation No 4 3.50% 0 4 0 0.00% 3.50% 0.00%

2 Impulse Tubing mtr 20 1.00% 0 20 0 0.00% 1.00% 0.00%

3 Cable Tray mtr 50 1.00% 0 50 0 0.00% 1.00% 0.00%

4 Cable laying mtr 300 1.50% 0 300 0 0.00% 1.50% 0.00%

5 Cable termination and glanding No 8 1.00% 0 8 0 0.00% 1.00% 0.00%

6 Calibration No 4 1.00% 0 4 0 0.00% 1.00% 0.00%

7 Loop checking No 4 1.00% 0 4 0 0.00% 1.00% 0.00%

TOTAL-C 10.00% 0 0 0.00% 10.00% 0.00%

Distribution and Contact List


ABSIV sekumaran@eagle.org, pramanathan@absconsulting.com, dbhujbal@absconsulting.com
ONGC pandey_ak5@ongc.co.in, khanra_Rajat@ongc.co.in, Thakur_Ashish@ongc.co.in
DNV‐GL birju.jaiswal@dnvgl.com, mani.choudhary@dnvgl.com, merlyn.menezes@dnvgl.com

Activities performed
1 MPT & UT of Golden joints completed

2 Pipe Support welding completed

3 Touch‐up painting completed

4 Removal of scaffolding on cellar deck completed

5 Gangway is removed

6 De‐anchoring is done

Planned activities(Next Day) :‐

1 Towing from NLM10 platform to North Field

Area of Concern if any :

According to ONGC Specification 2009F Rev.7 Clause No. 1.3 " Gamma rays can be used with permission from Company". LTHE yet to be submit the ONGC Approval for using Gamma rays at Barge Ocean303

Bhabesh Porel Vipin James EL.Krishnan


DNV ‐Mech. ( ONGC‐TPI) DNV‐E&I (ONGC‐TPI) ABSIV‐Mech. (ONGC‐CA) ABSIV‐E & I (ONGC‐CA) (ONGC REP.)