Professional Documents
Culture Documents
ONGC
Contractor : M/s. LTHE
Sub‐Contractor : M/s DOEPL
PROJECT : Balance work for Pipeline Replacement Project ‐ 4
A) Piping
3 Fit up Adiitional work Nos N/A N/A N/A N/A N/A NA N/A N/A
Welding (Field Joints) Inch Dia 83.5 29.00% 0 83.5 0 0.00% 29.00% 0.00%
4
Welding (Modification joints) Inch Dia 42 0.00% 0 42 0 0.00% 0.00% 0.00%
5 Welding of Additional work Inch Dia N/A N/A N/A N/A N/A NA N/A N/A
B) DEMOLITION
Activities performed
1 MPT & UT of Golden joints completed
5 Gangway is removed
6 De‐anchoring is done
According to ONGC Specification 2009F Rev.7 Clause No. 1.3 " Gamma rays can be used with permission from Company". LTHE yet to be submit the ONGC Approval for using Gamma rays at Barge Ocean303