Effective to date, you are directed to resume construction operations in the project site
in view of the new project site location is approved.
Hereunder is the historical data of your approved Work Suspension Order and Contract
Time Extension.
Original Contract Approved Work Approved Contract
Time: (cd) _150_ Suspension Order: Time Extension: _150_ Days Used to date:
Contract Time (cd) (cd) _____150_____(cd)
including
Extension: W.S.O. No. 1 _150_ C.T.E. No. 1 _150_ Days remaining:
(cd). ___190____ _____40______(cd)
Please acknowledge receipt of this order by signing (with date) and returning the three
(3) of the attached copies. The fourth copy is your file.
MABEL E. JAVIER
Municipal Engineer