Republic of the Philippines

Department of Public Works and Highways


SAMAR FIRST DISTRICT ENGINEERING OFFICE
Calbayog City

PROJECT : 18IJ-0081(Re- Advertise)


Widening of Permanent Bridges: Pisong Br.( B00338 SM) along Daang
Maharlika (SM) ( San Isidro - San Juanico Bridge) Including ROW
Calbayog City, Samar

CONTRACTOR : B. VICENCIO BUILDERS (BVB)INC.

STATEMENT OF TIME ELAPSED AND WORK ACCOMPLISHED


As of November 13, 2018 (80.90 %)

1. Original Contract Time ------------------ 145 Calendar Days

2. Date of Effective of Contract ------------------ June 21, 2018

3. Original Contract Amount ------------------ P 28,376,433.00

4. Revised Contract Amount due to Approved ------------------


Change Order/ Extra Work Order

5. Original Expiry Date ------------------ November 12, 2018

6. Approved Time Suspension ------------------ 30 Calendar Days

7. Revised Duration due to Change Order ------------------

8. Approved Time Extension ------------------

9. Total/Calendar Days Elapsed to Date ------------------ 116 Calendar Days

10. Contract Time Elapsed (After Extension & Suspension) ------------------ -

11. Revised Expiry Date Due to Suspension & Extension ------------------ December 12, 2018

12. Percentage of Time Elapsed ------------------ 80.00 %

13. Percentage of Work Accomplished ------------------ 80.90 %

14. Slippage ------------------ (+) 0.90 %

Submitted by:

RAUL C. NABOR, JR
Project Engineer
Noted:

ALVIN A. IGNACIO
District Engineer
CONTRACTOR : JFR CONSTRUCTION

STATEMENT OF TIME ELAPSED AND WORK ACCOMPLISHED


As of April 21, 2015 (80.44 %)

PROJECT : Local Infrastructure Program - Construction of One(1) Storey -


Two(2) Classroom School Bldg. Pilar Agricultural National
High School, Brgy. Pilar, Calbayog, Samar 1st LD

CONTRACTOR : JFR CONSTRUCTION

STATEMENT OF TIME ELAPSED AND WORK ACCOMPLISHED


As of April 21, 2015 (80.44 %)

1. Original Contract Time ------------------ 105 Calendar Days

2. Date of Effective of Contract ------------------ January 30, 2015

3. Original Contract Amount ------------------ P 1,836,803.08

4. Revised Contract Amount due to Approved ------------------


Change Order/ Extra Work Order

5. Original Expiry Date ------------------ May 14, 2015

6. Approved Time Extension ------------------

7. Revised Duration due to Change Order ------------------

8. Total Time Extension and Shutdown ------------------ -

9. Total/Calendar Days Elapsed to Date ------------------ 82 Calendar Days

10. Contract Time Elapsed (After Extension & Suspension) ------------------ -

11. Revised Expiry Date Due to Extension ------------------

12. Percentage of Time Elapsed ------------------ 78.10 %

13. Percentage of Work Accomplished ------------------ 80.44 %

14. Slippage ------------------ (+) 2.34 %

Submitted by:

ALBERTO F. DOROJA
Project Engineer
Noted:
VIRGILIO C. EDUARTE
District Engineer

CONTRACTOR : JFR CONSTRUCTION

STATEMENT OF TIME ELAPSED AND WORK ACCOMPLISHED


As of May 28, 2015 (100.00 %)

PROJECT : Local Infrastructure Program - Construction of One(1) Storey -


Two(2) Classroom School Bldg. Pilar Agricultural National
High School, Brgy. Pilar, Calbayog, Samar 1st LD

CONTRACTOR : JFR CONSTRUCTION

STATEMENT OF TIME ELAPSED AND WORK ACCOMPLISHED


As of May 28, 2015 (100.00 %)

1. Original Contract Time ------------------ 105 Calendar Days

2. Date of Effective of Contract ------------------ January 30, 2015

3. Original Contract Amount ------------------ P 1,836,803.08

4. Revised Contract Amount due to Approved ------------------ P 1,927,304.20


Change Order/ Extra Work Order

5. Original Expiry Date ------------------ May 14, 2015

6. Approved Time Extension ------------------ 15 Calendar Days

7. Revised Duration due to Change Order ------------------ 120 Calendar Days

8. Total Time Extension and Shutdown ------------------ -

9. Total/Calendar Days Elapsed to Date ------------------ 119 Calendar Days

10. Contract Time Elapsed (After Extension & Suspension) ------------------ -

11. Revised Expiry Date Due to Extension ------------------ May 29, 2015

12. Percentage of Time Elapsed ------------------ 99.17 %

13. Percentage of Work Accomplished ------------------ 100.00 %

14. Slippage ------------------ (+) 0.83 %

Submitted by:

ALBERTO F. DOROJA
Project Engineer
Noted:

VIRGILIO C. EDUARTE
District Engineer
44,010,720.90 10 june 125
31,203,590.70 31 july
12,807,130.20 31 aug
30 sep
31 oct
13 nov.
146 145
0

29
170
17.05882
Republic of the Philippines
Department of Public Works and Highways
SAMAR FIRST DISTRICT ENGINEERING OFFICE
Calbayog City

PROJECT : 18IJ-0081(Re- Advertise)


Widening of Permanent Bridges: Pisong Br.( B00338 SM) along Daang
Maharlika (SM) ( San Isidro - San Juanico Bridge) Including ROW
Calbayog City, Samar

CONTRACTOR : B. VICENCIO BUILDERS (BVB)INC.

STATEMENT OF TIME ELAPSED AND WORK ACCOMPLISHED


As of March 1, 2019 (91.10 %)

1. Original Contract Time ------------------ 145 Calendar Days

2. Date of Effective of Contract ------------------ June 21, 2018

3. Original Contract Amount ------------------ P 28,376,433.00

4. Revised Contract Amount due to Approved ------------------


Change Order/ Extra Work Order

5. Original Expiry Date ------------------ November 12, 2018

6. Approved Time Suspension ------------------ 60 Calendar Days

7. Revised Duration due to Change Order ------------------

8. Approved Time Extension ------------------

9. Total/Calendar Days Elapsed to Date ------------------ 55 Calendar Days

10. Contract Time Elapsed (After Extension & Suspension) ------------------ -

11. Revised Expiry Date Due to Suspension & Extension ------------------ January 11, 2019

12. Percentage of Time Elapsed ------------------ 100.00 %

13. Percentage of Work Accomplished ------------------ 91.10 %

14. Slippage ------------------ (-) 8.90 %

Submitted by:

RAUL C. NABOR, JR
Project Engineer
Noted:

ALVIN A. IGNACIO
District Engineer
CONTRACTOR : JFR CONSTRUCTION

STATEMENT OF TIME ELAPSED AND WORK ACCOMPLISHED


As of April 21, 2015 (80.44 %)

PROJECT : Local Infrastructure Program - Construction of One(1) Storey -


Two(2) Classroom School Bldg. Pilar Agricultural National
High School, Brgy. Pilar, Calbayog, Samar 1st LD

CONTRACTOR : JFR CONSTRUCTION

STATEMENT OF TIME ELAPSED AND WORK ACCOMPLISHED


As of April 21, 2015 (80.44 %)

1. Original Contract Time ------------------ 105 Calendar Days

2. Date of Effective of Contract ------------------ January 30, 2015

3. Original Contract Amount ------------------ P 1,836,803.08

4. Revised Contract Amount due to Approved ------------------


Change Order/ Extra Work Order

5. Original Expiry Date ------------------ May 14, 2015

6. Approved Time Extension ------------------

7. Revised Duration due to Change Order ------------------

8. Total Time Extension and Shutdown ------------------ -

9. Total/Calendar Days Elapsed to Date ------------------ 82 Calendar Days

10. Contract Time Elapsed (After Extension & Suspension) ------------------ -

11. Revised Expiry Date Due to Extension ------------------

12. Percentage of Time Elapsed ------------------ 78.10 %

13. Percentage of Work Accomplished ------------------ 80.44 %

14. Slippage ------------------ (+) 2.34 %

Submitted by:

ALBERTO F. DOROJA
Project Engineer
Noted:
VIRGILIO C. EDUARTE
District Engineer

CONTRACTOR : JFR CONSTRUCTION

STATEMENT OF TIME ELAPSED AND WORK ACCOMPLISHED


As of May 28, 2015 (100.00 %)

PROJECT : Local Infrastructure Program - Construction of One(1) Storey -


Two(2) Classroom School Bldg. Pilar Agricultural National
High School, Brgy. Pilar, Calbayog, Samar 1st LD

CONTRACTOR : JFR CONSTRUCTION

STATEMENT OF TIME ELAPSED AND WORK ACCOMPLISHED


As of May 28, 2015 (100.00 %)

1. Original Contract Time ------------------ 105 Calendar Days

2. Date of Effective of Contract ------------------ January 30, 2015

3. Original Contract Amount ------------------ P 1,836,803.08

4. Revised Contract Amount due to Approved ------------------ P 1,927,304.20


Change Order/ Extra Work Order

5. Original Expiry Date ------------------ May 14, 2015

6. Approved Time Extension ------------------ 15 Calendar Days

7. Revised Duration due to Change Order ------------------ 120 Calendar Days

8. Total Time Extension and Shutdown ------------------ -

9. Total/Calendar Days Elapsed to Date ------------------ 119 Calendar Days

10. Contract Time Elapsed (After Extension & Suspension) ------------------ -

11. Revised Expiry Date Due to Extension ------------------ May 29, 2015

12. Percentage of Time Elapsed ------------------ 99.17 %

13. Percentage of Work Accomplished ------------------ 100.00 %

14. Slippage ------------------ (+) 0.83 %

Submitted by:

ALBERTO F. DOROJA
Project Engineer
Noted:

VIRGILIO C. EDUARTE
District Engineer