Professional Documents
Culture Documents
Implementing Agency
Noted By:
3.0 Annexes
Annex “A” Project Bar Chart & S-Curve page 7-8
Extension of Time
: 0 Calendar Days
Revised Contract
Completion Date
PROJECT UPDATE
The following contract requirements are all submitted at BCDA Field Office located at
Capas, Tarlac:
- Construction Schedule and S-Curve;
- Manpower Schedule;
- Construction Schedule;
- Equipment Utilization Schedule;
- Construction Safety and Health, Sanitation and Security Program;
- PERT/CPM;
- Contractor’s All-Risk Insurance;
- Personal Accident Insurance; and
- Shop drawings
Pre-Construction Activity:
- Joint as stake survey.
- Establishment of centerline.
- Establishment of RROW limit.
- Establishment of drainage structures.
- Application of tree cutting permit.
- Joint Tree Inventory with CENRO.
General:
- Construction of Field Office
- Facilities for the engineer were provided.
Earthworks
N/A
N/A
Construction
of Bridge
N/A
Drainage and
Slope Protection
N/A
N/A
Street
Landscape
The activity for this this period is as follows:
N/A
Most of the documentary requirements for the project like as-stake plans
schedules and other pertinent documents are already transmitted at BCDA
Site Office located at Capas, Tarlac.
As of March 02, 2021, the project is at 0.3797% versus the scheduled percent
accomplishment of 0.2805% which makes it advance by 0.0992%. Most of the
activities were for the facilities of engineers and other pre-construction activity
such as above-mentioned activity.
C EARTHWORKS 10.52%
Clearing and Grubbing 14.01 ha. 0.73% 0.060% 0.060% 0.060% 0.060% 0.060% 0.060%
P r o g r e s s A c c o m p l i s h m e n t R e p o r t P a g e 1 5 | 83
F e b r u a r y 2 0 2 1
Annex “E1”
Mobilized Equipment and
Tools Schedule
-O (OPERATIONAL)
- I (IDLE)
- B (BREAKDOWN)
P r o g r e s s A c c o m p l i s h m e n t R e p o r t P a g e 1 9 | 83
F e b r u a r y 2 0 2 1
Annex “E3”
List of Delivered Materials
02 / 02 / 2021 18:01
02 / 03 / 2021 17:32 PM
02 / 04 / 2021 15:14 PM
02 / 03 / 2021 17:32 PM
02 / 04 / 2021 17:32 PM
CONSTRUCTION OF WAREHOUSE
02 / 05 / 2021 13:45 PM
02 / 05 / 2021 13:45 PM
02 / 08 / 2021 06:36 AM
02 / 05 / 2021 13:45 PM
02 / 05 / 2021 13:45 PM
02 / 05 / 2021 13:46 PM
02 / 05 / 2021 13:47 PM
02 / 09 / 2021 07:01 AM
CONSTRUCTION OF WAREHOUSE
02 / 22 / 2021 10:12 AM
02 / 22 / 2021 10:12 AM
02 / 22 / 2021 10:14 AM
02 / 22 / 2021 10:14 AM
02 / 25 / 2021 09:51 AM
02 / 25 / 2021 09:51 AM