Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
MAJOR INFRASTRUCTURE PROJECTS
Status as of September 25, 2018
CONCRETING OF BRGY. NANCAPIAN FMR, BRGY. NANCAPIAN, MALASIQUI,
Name of Project : PANGASINAN
Station Limits :
PROJECT DESCRIPTION:
Reconstruction/ rehabilitation/ widening of damaged paved Farm-to-Market road.
PROJECT IMPACT:
The project will provide ease and comfort, lessen transport cost of farm products, and shorten travel time from farms to
markets thereby contributing to greater income for farmers and their families.
CONTRACTUAL DATA : FINANCIAL STATUS :
Project Component : Roads
Province : Pangasinan
Region :I Amount (P'000)
Location : Allocation Releases Obligation Disbursement
Department of Agriculture CY 2018
Source of Funds :
Farm-to-Market Road Project FY2017
Mode of Contract : Competitive Bidding FY2018
Implementing Office : Total: -
Date of Bidding :
Contractor :
Total Project Cost :
Revised Contract Amount : N/A
Start Date :
Contract Duration :
Revised Contract Duration :
Completion Date :
Revised Completion Date :
PHYSICAL ACCOMPLISHMENT : REMARKS:
Previous To Date
Planned Accomplishment : 0.00%
Actual Accomplishment : 0.00%
Slippage : 0.00%
PROJECT UPDATE: EQUIPMENT ON SITE:
1 - Backhoe 1- Dump Truck
1- Pay Loader 1- Vibratory Roller
MANPOWER ON SITE:
1 - Project Engineer
1 - Construction Foreman
10 - Laborer
ACTIVITIES UNDERTAKEN:
PROBLEMS/ISSUES: ACTIONS UNDERTAKEN:
Prepared by: Submitted by: Approved by:
______________________ _____________________________ ____________________________
Project Engineer I Chief, Construction Section District Engineer
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
MAJOR INFRASTRUCTURE PROJECTS
Status as of September 25, 2018
Name of Project : CONCRETING OF BRGY. NANCAPIAN FMR, BRGY. NANCAPIAN, MALASIQUI,
PANGASINAN
Station Limits :0
BENEFITS:
SOCIAL ECONOMIC ENVIRONMENTAL OTHER BENEFITS
1. Concreting of the Farm- 1. Concreting of the Farm-to- 1. Concreting of the Farm-to- 1. Concreting of the Farm-to-
to-Market Road will Market Road will provide Market Road results in less Market Road will result in
provide the public with fast and easy transport of noise and air pollution due cost of fuel savings due to
transport convenience goods, commodities and to continuous flow of fast and improved travel of
due to improved and services to their intended traffic. vehicles.
continuous flow of traffic. points of destination,
thereby, improving the
economic viability of
businesses.
PROGRESS PHOTOGRAPHS:
BEFORE: DURING: AFTER:
LOCATION MAP:
THIS SITE
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
MAJOR INFRASTRUCTURE PROJECTS
Status as of October 31, 2017
Name of Project : Construction of Small Water Impounding Project, San Carlos City, Pangasinan
Station Limits :
PROJECT DESCRIPTION:
Construction of two (2) Small Water Impounding Project - Reinforced Concrete Structure with Rubble Concrete Slope
Protection on approaches at Downstream = 50.00 l.m. and Upstream = 200.00 l.m. (Brgy. Libas) and Downstream =
50.00 l.m. and Upstream = 100.00 l.m. (Brgy. Lilimasan); and Gabion Revetment of 60.00 l.m. at Brgy Libas.
PROJECT IMPACT:
Small Water Impounding Project provides supplemental irrigation water for intensified crop production which may
substantially increase farmer's income. In addition, it also contributes to the water requirements of livestock production,
aquaculture, power generation, and recreation.
CONTRACTUAL DATA : FINANCIAL STATUS :
Project Component : Small Water Impounding Construction
Province : Pangasinan
Region : I Amount (P'000)
Location : San Carlos City, Pangasinan Allocation Releases Obligation Disbursement
Source of Funds : GAA 2017 (LIP) FY2016
Mode of Contract : Competitive Bidding FY2017 25,000 25,000
Implementing Office : DPWH - Pangasinan IV District Total: 25,000 25,000 -
Engineering Office
Date of Bidding : April 25, 2017
Contractor : JASA BUILDERS
Total Project Cost : 23,636,319.32
Revised Contract Amount : N/A
Start Date : June 8, 2017
Contract Duration : 168 C.D.
Revised Contract Duration : 198 C.D.
Completion Date : November 22, 2017
Revised Completion Date : December 22, 2017
PHYSICAL ACCOMPLISHMENT : REMARKS:
Previous To Date
Planned Accomplishment : 23.40% 23.40%
Project is totally suspended due to unworkable
Actual Accomplishment : 15.00% 15.00%
site condition/ high water level.
Slippage : -8.40% -8.40%
PROJECT UPDATE: EQUIPMENT ON SITE:
NONE
Project is totally suspended due to unworkable site condition/ high
water level (August 1, 2017 up to Present). MANPOWER ON SITE:
NONE
ACTIVITIES UNDERTAKEN:
NONE
PROBLEMS/ISSUES: ACTIONS UNDERTAKEN:
Project is totally suspended due to unworkable site condition/ high Contract Time Suspension and Extension were
Project is totally suspended due to unworkable site condition/ high Contract Time Suspension and Extension were
water level caused by previous heavy rains. introduced to the project.
Prepared by: Submitted by: Approved by:
ELDRED M. MISLANG VIRGILIO B. ZAMUDIO SIMPLICIO D. GONZALES
Project Engineer Chief, Construction Section District Engineer