STATUS OF 17 INTRA-

REGIONAL/ BY-PASS
ROAD NETWORKS
STATUS OF 17 INTRA-REGIONAL BY-PASS
ROAD NETWORKS
WITH FUNDING FROM DPWH 11
1. Datu Paglas-Columbio-Matanao road (13.07 Kms paved of 29.76 Kms)
2. Columbio-Lutayan-Koronadal City road (12.156 Kms paved of 31.653 Kms)

3. Banga-Tupi road ( 19.46 Kms paved of 37.8 Kms)


9
4. Tupi-Sarangani road (28 kms paved of 49.3 kms) 13
5. Surallah-T’boli-San Jose road (22.2 kms paved of 52.47 kms )

FOR FEASIBILITY STUDY 7

6. Koronadal By-pass road ( 21.2 km, 1.02 km paved)


7. Ninoy Aquino By-pass road, Kidapawan City (1.3 km)
8. NHW Jct Pob. Malungon -Boundary Sta. Maria Road, Davao 10
Occ. (17.65 km -initial survey) 1
9. Cotabato City By-Pass road (4.06 km)
2
10. Tacurong East By-pass road

6
OTHER ROAD NETWORKS PROPOSED FOR 3
4
DEVELOPMENT AND FUNDING 8

11. Malapag-Tinimbacan-Banisilan road ( 8 kms paved if 28.23 Kms) 12 15

12. Banga-T’boli-Koronadal Proper, Polomolok (18.75kms paved of 18.96kms paved) 5


14
13. Sadaan-Central Glad By-pass road, Midsayap, NC ( 3.77 km)
14. General Santos City middle ring Road (Alignment has yet to be finalized)
15. Silway 8-Mabuhay-Conel-Olympog-Upper Labay Road (Survey has yet to be conducted)

FOR ROAD CONVERSION


Balindog-Singao-San Vicente – Makilala Highway, Kidapawan City
Nikaan – Kitub – Banisilan Road (54km)
STATUS OF 17 INTRA-REGIONAL BY-
PASS ROAD NETWORKS

WITH FUNDING FROM DPWH


1. Datu Paglas-Columbio-Matanao road
( 15.734 Kms paved of 29.76 Kms)
2. Columbio-Lutayan-Koronadal City road
(12.156 Kms paved of 31.653 Kms)
1
3. Banga-Tupi road
2
( 19.46 Kms paved of 37.8 Kms)
4. Tupi-Sarangani road 3
4
(28 kms paved of 49.3 kms)
5. Surallah-T’boli-San Jose road 5

(22.2 kms paved of 52.47 kms )


STATUS OF 17 INTRA-REGIONAL BY-PASS ROAD
NETWORKS
WITH FUNDING FROM DPWH
1. Datu Paglas-Columbio-Matanao Road
Updates
Completed
1. Road opening of 2.66 km under
CY 2016 DPWH
2. Concreting of 4.77 km road under Datu Paglas
CY 2016 DPWH
5) 8.23 km concreting
On-going
7.74 road concreting at Brgy.
Sinapulan-Brgy. Colon Sabak Section 4) 3.87 km concreting

Proposed
2) 4.77 km concreting
3. Opening of 1.4 km road under CY
1) 2.66 km opening
2017 DPWH
4. Concreting of 3.87 km road under Columbio 3) 1.93 km opening
CY 2017 DPWH
5. Concreting of 8.23 km under CY Colonsabak
2018 DPWH
6. Concreting of 4.59 km road under 6) 4.59 km concreting
CY 2019 DPWH
Existing pavement Lutayan
(13.0715.734 Kms paved of 29.76 Kms)
8.304 km
STATUS OF 17 INTRA-REGIONAL BY-PASS ROAD
NETWORKS
WITH FUNDING FROM DPWH
2. Columbio-Lutayan-Koronadal City Road

Updates
(Sinapulan-Colonsabak section) Columbio

On-going
1. Concreting of 1.5 km under FSP CY 2016
2. Lutayan section - concreting of 3 km road
under CY 2016 DPWH
Proposed
3. Rotonda – Avanceña Section – 2.70 km. –
under DPWH CY 2017 Lutayan 6) 11.5 km concreting

4. concreting of 0.150 km bridge under CY 5) 2 km concreting


2017 DPWH 6) 9.06 km concreting
1) 1.5 km concreting
5. concreting of 2 km road under CY 2017
DPWH
2) 3 km concreting
6. concreting of 11.490 km road under CY
2018 DPWH 3) 2.7 km concreting

7. concreting of 9.063 km road under CY


4) 0.15km bridge
2019 DPWH
Existing road pavement
Koronadal to bndry Lutayan section- 6.058 km (12.156 Kms paved of 31.653 Kms)
Koroadal City
STATUS OF 17 INTRA-REGIONAL BY-PASS
ROAD NETWORKS
WITH FUNDING FROM DPWH
3. Banga – Tupi Bypass Road
Updates
- DPWH to conduct the Feasibility Study of the 1.) Existing
project amounting to PhP10 M (19.46 Kms paved of 37.8 Kms)
Existing 4.)SLRF 2015
1. BANGA Section – 4.29 km
Banga
2. TUPI Section – 3.74 km (FSP)
On-going
3. FSP 2015 – 2.38 km concreting; 6.10m
5.) Kalsada 2016
width; 0.20m thk – Banga
4. SLRF 2015 – 1.73 km concreting – Banga
5. KALSADA 2016 – 7.321 km conc.; 6.70m
width; 0.20m thk – Banga 2.) FSP - Existing
Proposed 6.) Kalsada 2017
6. KALSADA 2017 – 5.84 km
7.) FSP 2018 Tupi
(Lamba/Derilon/Lamian Section) –
Proposed Concreting
7. FSP 2018 – 3.00 km (Derilon/Lambingi
Section) – Proposed Concreting
8. FSP 2019 – 0.95 km (Lampari Proper to Lampari
Boundary) – Proposed Concreting
9. Const. of Access Road -Tablao - Upper
Village & Lampari - Upper Village – (for 9.) Road Opening
Funding)-8.34 km
3.) FSP 2015
10. (150 M Road; 26M Bridge 18 lm w/ slope 8.) FSP 2019
protection – DPWH 2018)
STATUS OF 17 INTRA-REGIONAL BY-PASS ROAD
NETWORKS
4. Tupi (South Cotabato) - Malungon (Sarangani) Road
Updates
Completed
1. Concreting of Jct.Nhwy to Crossing
Loleng (Cebuano) – 4.30 km Brgy Miasong
(DPWH)
On-going 5.) 7 km concreting
4.) 17 km concreting
2. Concreting of Cebuano – Linan FMR
– 3.70 km (MLGU, PLGU, PRDP)
6.) 14 km for funding
3. Concreting of Lote North to
3.) 3 km concreting
Landayao Area – 3.00 km
(DPWH/DOT) Tupi 2.) 3.7km concreting
Malandag
4. Concreting of 17 km road in 1.) 4.3km concreting
Malandag section under CY 2016
PRDP (28 Kms paved of 49.3 Kms)
Proposed
5. Concerting of 7 km road in Malandag
section proposed CY 2017 PRDP
6. Upgrading of Landayao Area to
Miasong – 14.00 km – For Funding
7. DPWH 2017 – 70M 2km in Miasong
Area
STATUS OF 17 INTRA-REGIONAL BY-PASS ROAD
NETWORKS
5. Surallah-T’boli-GSC Bypass Road

Updates
• 3.620 km road opening at Tboli –
Pobl.Surallah
Maan Section – P300M (CY 2016) -
DPWH
• 20 linear meter concrete bridge
proposed for construction
• DPWH to conduct the Feasibility
Study with PhP10 M budget
• 3.99 km road opening at Brgy. T'boli- Lake Sebu
Brgy. Maan Section-P144.75 M (CY
2017) DPWH T’boli

• 13.332 km road concreting at GSC


section-P193 M (CY 2017) DPWH Road Opening

Surface: GSC R/A


Asphalt – 21.30 kms.
Concrete – 0.925 km.
Gravel – 18.602 kms.
Earth (opening) – 11.60 kms.
Structures:
Bridge – 2 (Proposed)
Total Length ……… 52.427 km.
STATUS OF 17 INTRA-REGIONAL BY-PASS
ROAD NETWORKS

FOR FEASIBILITY STUDY


1. Koronadal By-pass road 4
(1.02 km paved of 21.2 km)
2. Ninoy Aquino By-pass road, 2

Kidapawan City (3.471 km)


3. NHW Jct Pob. Malungon - 5
Boundary Sta. Maria Road,
Davao Occ.
(17.65 km -initial survey) 1

4. Cotabato City By-Pass road 3

(4.06 km)
5. Tacurong East By-pass road
(15.179 km)
STATUS OF 17 INTRA-REGIONAL BY-PASS
ROAD NETWORKS FOR FEASIBILITY STUDY
1. KORONADAL BYPASS ROAD (indicate route)
Updates
• DPWH to conduct the Brgy. New Iloilo

Feasibility Study of the project


amounting to PhP10 M
• FSP 2014 – 1.029 km
concreting; 6.10m width; 0.20m
thk.
• FSP 2017 – 2.00 km proposed Koronadal City

concreting Proposed 2017


• DPWH 2018 – 169.2M; 6.77km Road Concreting

Proposed Opening

Concrete Surface... 4.146 km.


Gravel Surface…… 16.217 km.
Earth (opening)…. . 0.837 km.
Total Length …….. 21.20 km. Brgy. Saravia

Structures - Bridge – 4
- RCBC – 3
RROW - 10, 20 & 60 m
PCCP Width - 5–6.7m
STATUS OF 17 INTRA-REGIONAL BY-PASS
ROAD NETWORKS FOR FEASIBILITY STUDY
2. Ninoy Aquino By-pass road, Kidapawan City
Updates Enrolled as By-Pass Road to DPWH
For Opening
• Acquisition of road right-of-way Existing road (mostly graveled)
initially conducted
• LGU appropriated Php
2,101,462.48 under the 20%
LDF CY 2016 Supplemental
Budget No. 3 for the opening of
Magsaysay Section in
Kidapawan-Calunasan Road to
Sinsuat Extension

Gravel Surface…… 1.575 km.


Earth (opening)…. . 1.696km.
Bridge (for construction)…20 lm
Total Length …….. 3.471 km.
STATUS OF 17 INTRA-REGIONAL BY-PASS
ROAD NETWORKS FOR FEASIBILITY STUDY
3. NHW Jct Pob. Malungon -Boundary Sta. Maria Rd, Dvo Occ.
Updates
• Concreting of 4.8 km road is
on-going under CY 2016
KALSADA program
Under KALSADA
• Concreting of 5 km road CY 2016 & 2017
proposed CY 2017 KALSADA
program
Proposed projects under DPWH
- Concreting of 20 km CY 2018 Sta. Maria
- Concreting of 10 km CY 2019 Malungon
- Concreting of 25 km CY 2020
(For validation, DPWH funding)
Passed InfraCom res to include
MinDA

17.65 km- based on initial survey


of PLGU
STATUS OF 17 INTRA-REGIONAL BY-PASS
ROAD NETWORKS FOR FEASIBILITY STUDY
4. Cotabato City By-Pass road
Updates
• Total length of road is 4.060 km
which are all concreted
• Widening, rehab and Phase 1 – 2 km CY 2017
construction of drainage
facilities are required .
• DPWH to conduct the
Feasibility Study of the project
amounting to
PhP10,000,000.00 Phase 2 – 2.06 km CY 2018
• Concreting of 5.91 km under
CY 2017 DPWH

Cotabato City
STATUS OF 17 INTRA-REGIONAL BY-PASS
ROAD NETWORKS FOR FEASIBILITY STUDY
5. Tacurong East By-pass road
Updates
• Approximate length -15.179
kms, 10 meters width
• 3.22 kms -barangay road (not
passable)
• The rest is gravel road
Propos
• Concern: The by-pass road
is too close to the arterial
road Tacurong City
STATUS OF 17 INTRA-REGIONAL BY-PASS
ROAD NETWORKS
OTHER ROAD NETWORKS PROPOSED FOR 1

DEVELOPMENT AND FUNDING


3
1. Malapag-Tinimbacan-Banisilan road
( 8 kms paved of 28.23 Kms)
2. Banga-T’boli-Koronadal Proper,
Polomolok
(18.75kms paved of 18.96kms
paved)
3. Sadaan-Central Glad By-pass road,
Midsayap, NC
( 3.77 km)
4. General Santos City middle ring 2 5
Road (Alignment has yet to be finalized)
4
5. Silway 8-Mabuhay-Conel-Olympog-
Upper Labay Road
(Survey has yet to be conducted)
STATUS OF 17 INTRA-REGIONAL BY-PASS ROAD NETWORKS
OTHER ROAD NETWORKS PROPOSED FOR
DEVELOPMENT AND FUNDING
1. Malapag-Tinimbacan-
Banisilan road

Updates Banisilan

• DPWH to conduct the


Feasibility Study of the project
amounting to
PhP10,000,000.00
5 km - KALSADA CY 2017
• Concreting of 4 km road is on-
going under CY 2015 PRDP
• Concreting of 5 km road Corossing Tinimbacan
4km – PRDP
proposed CY 2017 KALSADA 1.395km - SOCSKSARGEN

(DPWH 2018 – P150M; 5km) 1.65km - SOCSKSARGEN

Concrete Surface... 8 km.


AFMA funded
Gravel Surface…… 20.23 km.
Total Length …….. 28.23 km. 2.78km PRDP Malapag
STATUS OF 17 INTRA-REGIONAL BY-PASS ROAD NETWORKS
OTHER ROAD NETWORKS PROPOSED FOR
DEVELOPMENT AND FUNDING
2. Banga-T’boli-Koronadal Proper, Polomolok
Updates
1. PAMANA – Lampari Bdry –
Lamsalome Concreting – 1.33 km
2. GAP – Lamsalome – 210 meters; Lampari
Proposed under FSP 2019 (tentative)
3. FSP 2014 – Lamsalome – 1- 1.33 km
Lambangan Concreting – 0.538 km 2- 0.21 km
Lamsalomi 3- 0.538 km
4. PAMANA – Lamsalome –
Lambangan – Simbo Concreting – Cr. Palkan
6.48 km
5. FSP 2011 – Simbo – Lambangan 4- 6.48 km 5- 0.843 km 8- 3.45 km
Concreting – 0.843 km 6- 2.40 km

6. FSP 2015 – Purok 4 – Purok 1 Lamabangan

Concreting – 2.40 km (On-going)


7. FSP 2016 – Kor. Proper – Talcon
Concreting – 3.719km (On-going) Surface:
8. KALSADA 2017 - Nhwy Cr. Palkan – Concrete (Existing/On-going) – 15.31 km
Asphalt – 3.446 km 7- 3.719 km
Kor. Proper – 3.446 km (Asphalt)
Gravel - 0.21 km
9. Const. of Simbo Concrete Bridge - Total Length – 18.966 km
suspended Structures: Bridge – 5, RCBC – 4
STATUS OF 17 INTRA-REGIONAL BY-PASS ROAD NETWORKS
OTHER ROAD NETWORKS PROPOSED FOR
DEVELOPMENT AND FUNDING
3. Sadaan-Central Glad By-pass road, Midsayap, NC
Updates
• DPWH to conduct the Feasibility
Study of the project amounting to
PhP10,000,000.00
Proposed projects under DPWH
- Opening of 3.77 km road CY 2018
- Concreting of 2 km road CY 2019
- Concreting of 1.77 km road CY 2020

Surface:
Asphalt/Gravel Surface…… 3.77 km.
Total Length …….. 3.77 km.

(Proposed 3.77 km)


STATUS OF 17 INTRA-REGIONAL BY-PASS ROAD NETWORKS
OTHER ROAD NETWORKS PROPOSED FOR
DEVELOPMENT AND FUNDING
4. General Santos City middle ring Road
Salvani St
Apopong
The road has two
possible alignment
• Bulaong terminal-Labangal (back of
Doña Solidad
Robinson land)-passing Makar
national H-way-going to Doña Bulaong
Soledad-Brgy. Fatima-MSU road- Terminal
39.2 FVR Village-Nat’l H-way Siguel
Makar road
• Salvani st.- Springville Subd.(Brgy.
Apopong)-Makar nat’l H-way-Brgy. Makar Port
Apopong (Prk Bagangga)-Doña
Soledad-Brgy. Fatima-MSU road-
Brgy. 39.2 FVR Village-nat’l H-way
Siguel Makar road

LGU-GSC to request DPWH for the


conduct of feasibility study of the said
road MSU
Proposed, joint GSC & DPWH survey

Siguil
STATUS OF 17 INTRA-REGIONAL BY-PASS ROAD NETWORKS
OTHER ROAD NETWORKS PROPOSED FOR
DEVELOPMENT AND FUNDING
5. Silway 8-Mabuhay-Conel-Olympog-Upper Labay Road
Update

Road survey has yet to be FSP 2016 Upper


FSP 2013
conducted by DPWH district Labay

office and LGU-GSC


FSP 2014
DPWH

LGU-GSC to request DPWH Olympog

for the conduct of feasibility


study of the said road Silway 8 Conel

Mabuhay
STATUS OF 17 INTRA-REGIONAL BY-PASS ROAD
NETWORKS
FOR ROAD CONVERSION
1. Balindog-Singao-San
Vicente – Makilala
Highway, Kidapawan City
( ? km); need to be improved first,
at least gravel road; there are
going PRDP projects along this
route, remaining to be proposed
under ROLL-IT

2. Nikaan – Kitub – Banisilan


Road (54km); need to be
improved first, at least
gravel road
STATUS OF 17 INTRA-REGIONAL BY-PASS ROAD
NETWORKS
FOR ROAD CONVERSION
1. Balindog-Singao-San Vicente
– Makilala Highway,
Kidapawan City
(alignment has yet to be finalized)
Updates
- Request for the conversion of road classification
was denied due to the following:
 Providing only an inter-barangay connections within
the Kidapawan City & Makilala and aids only as a
collector road of Jct. Davao-Cotabato Road and Allah
Valley Road
 Duplicates the function of the existing Matalam-M’lang-
Bagontapay Jct. Road

-On-going concreting of 1.3 km road along Balindog-


Singao-Libertad road under PRDP

- DPWH suggested to extend the alignment of the road


to Cotabato-Davao road
STATUS OF 17 INTRA-REGIONAL BY-PASS ROAD
NETWORKS
FOR ROAD CONVERSION
2. Nicaan – Kitub – Banisilan
Road (54km)
Update
Total Length: 54 km
Alignment : Brgy. Nikaan in Libungan to Brgy.
Kitub in Alamada to Poblacion Banisilan

• Concreting of 11 km road (Kiaring section)under CY


2017 KALSADA (P200 M)
• Concreting of 2.2 km (Pantar section)under CY 2017
FSP (P23.2M)
• Concreting of 2.5 km (Tinimbacan section) under CY
2018 FSP (P32 M)
• Concreting of 3.67 km under CY 2019 FSP (P47.5 M)
Salamat po!