TRANSMITTAL

TO :

FROM :

SUBJECT :

DATE :
________________________________________________________________________________________

Transmitting herewith for your endorsement and approval Variation Order (Extra Work/Change) No. 2
for Concreting of Purok Sansapan – Abtois – Purok 1 FMR, Barangay Upper Labay, General Santos City
and funded through the ___________________________ of the Department of Agriculture and
LGU General Santos City. The said project with a contract cost of PhP19,260,740.34 as per approved
variation order no. 1 is being undertaken by contract through MJ Tiongson Construction.

The said Variation Order (Extra Work/Change) No. 2 as evaluated and recommended for approval by the
Technical Review Team _______________ meeting in Isulan, Sultan Kudarat comprised the increase
and decrease in quantities of some item of the original program, including the introduction of a new
work item necessary for the improvement and protection of the project to wit:

Sample list:
1. Deduction of quantities for Items 102 (roadway excavation), 105 (subgrade preparation), 201
(aggregate base course) and SPL1 (backfill) from sta 1+685.70 – Sta 1+767.30 due to restationing
of the completed DPWH road project.
2. Introduction of new Item 101-1 (Removal of Existing Pavement) and Increase in quantity for Items
311 (PCCP) for works to be undertaken at Sta 1+282.661 to Sta 1+371.361
3. Increase in quantity for Item 505 (riprap & grouted riprap).

Included also in the conditions of the aforecited Variation Order No. 2 are the additional costing of
PhP346,088.62 and a time duration of _______________ calendar days to complete the said extra
works. The additional cost will be taken from the generated savings in the procurement of the original
program.

For your information and appropriate action.