Subject: REVISION OF BILL OF QUANTITIES, PROJECT DESCRIPTION
PROJECT DURATION and APPROVED BUDGET FOR THE CONTRACT
This Supplemental Bulletin No. 067 is issued to amend provisions in the Bidding Documents (BDs) for the above stated
Contract, as follows:
Current Provision of BDs (including Previous Amended Provision of BDs under this Supplemental
Amendments) Bulletin
As posted in the Phil-GEPS and DPWH: Revision of bill of quantities, project description, project duration, and
approved budget for the contract (ABC)

Item No. Description Qty. Unit Item No. Description Qty. Unit
Part B – Other General Requirements Part B – Other General Requirements
B.4(1) Construction Survey and Staking 1.00 Km B.4(1) Construction Survey and Staking 2.88 Km
B.5 Project Billboard/ Signboard 1.00 Each B.5 Project Billboard/ Signboard 2.00 Each
Part G – Drainage and Slope Protection Structures Part G – Drainage and Slope Protection Structures
508(1) Handlaid Rock Embankment 1,035.00 Cu.m 508(1) Handlaid Rock Embankment 1,665.00 Cu.m
Part J – Flood Control and Drainage Part J – Flood Control and Drainage
1700(1) Clearing and Grubbing 13,007.00 Sq.m 1700(1) Clearing and Grubbing 19,619.85 Sq.m
1701(2) Surplus Common 13,918.00 Cu.m 1701(2) Surplus Common 30,134.00 Cu.m
1701(3) Surplus Rock Excavation 36,241.00 Cu.m 1701(3) Surplus Rock Excavation 14,780.00 Cu.m
1702(1)a Structure Excavation (Soft Rock) 2,861.00 Cu.m 1702(1)a Structure Excavation (Soft Rock) 4,991.00 Cu.m
1704(1)b Embankment (from Borrow) 17,858.00 Cu.m 1704(1)b Embankment (from Borrow) DELETED
1704(1)a Embankment from 23,190.00 Cu.m
Excavation (Common Soil)
1712(2) Concrete, Slope Protection 3,356.00 Cu.m 1712(2) Concrete, Slope Protection 5,423.00 Cu.m
Part C – Earthworks Part C – Earthworks
100(1) Clearing and Grubbing 0.70 Ha 100(1) Clearing and Grubbing DELETED
102(2) Surplus Common Excavation 11,604.14 Cu.m 102(2) Surplus Common Excavation 399.00 Cu.m
103(1)a Structure Excavation (Common 1,454.00 Cu.m 103(1)a Structure Excavation (Common 50.00 Cu.m
Soil) Soil)
104(1)a Embankment from Roadway 2,364.67 Cu.m 104(1)a Embankment from Roadway 5,902.00 Cu.m
Excavation (Common Soil) Excavation (Common Soil)
103(2)a Bridge Excavation (Common 115.90 Cu.m 103(2)a Bridge Excavation (Common DELETED
Soil) Soil)
104(2)a Embankment from Borrow 24.08 Cu.m 104(2)a Embankment from Borrow 231.24 Cu.m
(Common Soil) (Common Soil)
105(1)a Subgrade Preparation (Common 3,649.43 Sq.m 105(1)a Subgrade Preparation (Common 1,198.84 Sq.m
Material) Material)
Part D – Subbase and Base Course Part D – Subbase and Base Course
200(1) Aggregate Subbase Course 1,372.80 Cu.m 200(1) Aggregate Subbase Course 476.00 Cu.m
Part F – Bridge Construction Part F – Bridge Construction
404(1)a Reinforcing Steel, Grade 40 15,736.00 Kg 404(1)a Reinforcing Steel, Grade 40 17,675.00 Kg
404(1)b Reinforcing Steel, Grade 60 21,345.00 Kg 404(1)b Reinforcing Steel, Grade 60 17,944.00 Kg
405(1)b3 Structural Concrete, 27.58Mpa, 101.25 Cu.m 405(1)b3 Structural Concrete, 27.58Mpa, 234.150 Cu.m
Class A, 28 days Class A, 28 days
406(1)e8 Prestresses Structural Concrete 1.00 Each 406(1)e8 Prestresses Structural Concrete 4.00 Each
Members, 35.00m., type V, I- Members, 35.00m., type V, I-
Girders Girders
407(8) Lean Concrete, Class “B” (16.50 2.28 Cu.m 407(8) Lean Concrete, Class “B” (16.50 2.88 Cu.m
Mpa) Mpa)
411(2) Paint (Concrete Structures) 245.84 Sq.m 411(2) Paint (Concrete Structures) 412.18 Sq.m
412(1) Elastomeric Bearing Pads (Duro 1.00 Each 412(1) Elastomeric Bearing Pads (Duro 8.00 Each
60, 42mm x 500mm x 711mm) 60, 42mm x 500mm x 711mm)
418(1) Bridge Steel Deck 1.00 Sq.m 418(1) Bridge Steel Deck DELETED
Part G – Drainage and Slope Protection Structures Part G – Drainage and Slope Protection Structures
510(2) Concrete, Slope Protection 53.72 Cu.m 510(2) Concrete, Slope Protection DELETED
511(2)a1 Mattresses, Metallic Coated 108.00 Cu.m 511(2)a1 Mattresses, Metallic Coated 50.00 Cu.m
(0.3mx 2m x 6m) (0.3mx 2m x 6m)
511(3) Filter Cloth 360.00 Sq.m 511(3) Filter Cloth 168.00 Sq.m
517(1)a Drain Pipe, Galvanized (150mm 4.20 Lm 517(1)a Drain Pipe, Galvanized (150mm 6.24 Lm
Ø) Ø)

Page 1 of 2
.

SUPPLEMENTAL BULLETIN NO. 067

Project Description: Project Description:


35lm. RCDG Bridge; 875.141 lm. Reinf Conc’t Revetment @ LS; 780.35 Construction of 35lm. PCDG Bridge; Construction of Reinforced
lm. Reinf Conc’t Revetment @ LS Concrete Revetment at Left and right side; Gravelling of bridge
Approaches and Construction of Grouted Riprap Slope Protection
Project Duration: 200 Calendar Days Project Duration: 218 Calendar Days
ABC: Php96,499,965.84 ABC: Php96,499,998.75

All other scope of works not included in this revision remains the same. This Supplemental Bulletin shall form an integral
part of the said Bidding Documents.

For the guidance and information of all concerned.

RONALD B. CARIAGA
BAC Chairperson