You are on page 1of 6

Section 3

TEMPORARY WORKS

3.1 GENERAL drawings shall be submitted sufficiently in advance of


proposed use to allow for their review, revision, if needed,
3.1.1 Description and approval without delay to the work.
The Contractor shall not start the construction of any
This work shall consist of the construction and re- temporary work for which working drawings are required
moval of temporary facilities which are generally de- until the drawings have been approved by the Engineer.
signed by the Contractor and employed by the Contractor Such approval will not relieve the Contractor of responsi-
in the execution of the work and whose failure to perform bility for results obtained by use of these drawings or any
properly could adversely affect the character of the of his other responsibilities under the contract.
contract work or endanger the safety of adjacent facil-
3.1.3 Design
ities, property, or the public. Appropriate reductions in
allowable stresses or loads shall be used for design
The design of temporary works shall conform to the
when other than new or undamaged materials are to be
AASHTO Standard Specifications for Highway Bridges
used. Such facilities include, but are not limited to, false- or the Guide Design Specifications for Bridge Temporary
work, forms and form travelers, cofferdams, shoring, Works; or to other established and generally accepted de-
water control systems, and temporary bridges. sign code or specification for such work.
The following publications are useful reference docu- When manufactured devices are to be employed, the
ments in the preparation of specifications for the design, design shall not result in loads on such devices in excess
review and inspection of temporary works: of the load ratings recommended by their manufacturer.
For equipment where the rated capacity is determined by
Synthesis of Falsework, Formwork, and Scaffolding load testing, the design load shall be as stated in the Guide
for Highway Bridge Structures, November 1991, Design Specifications for Bridge Temporary Works.
(FHWA-RD-91-062) The load rating used for special equipment, such as ac-
Guide Standard Specifications for Bridge Temporary cess scaffolding, may be under the jurisdiction of OSHA
Works, November 1993, (FHWA-RD-93-031) and/or other State/local regulations. However, in no case
Guide Design Specification for Bridge Temporary shall the rating exceed 80% of the maximum load sus-
Works, November 1993, (FHWA-RD-93-032) tained during load testing of the equipment.
Certification Program for Bridge Temporary Works, When required by statute or specified in the contract
November 1993, (FHWA-RD-93-033) documents, the design shall be prepared and the drawings
Construction Handbook for Bridge Temporary signed by a Registered Professional Engineer.
Works, November 1993, (FHWA-RD-93-034)
3.1.4 Construction

3.1.2 Working Drawings Temporary works shall be constructed in conformance


with the approved working drawings. The Contractor shall
Whenever specified or requested by the Engineer, the verify that the quality of the materials and workmanship
Contractor shall provide working drawings with design employed are consistent with that assumed in the design.
calculations and supporting data in sufficient detail to per-
mit a structural review of the proposed design of a tem- 3.1.5 Removal
porary work. When concrete is involved, such data shall
include the sequence and rate of placement. Sufficient Unless otherwise permitted, all temporary works shall
copies shall be furnished to meet the needs of the Engi- be removed and shall remain the property of the Contrac-
neer and other entities with review authority. The working tor upon completion of their use. The area shall be re-
483
484 HIGHWAY BRIDGES 3.1.5

stored to its original or planned condition and cleaned of for wind. However, in no case shall the horizontal load to
all debris. be resisted in any direction be less than 2% of the total
dead load.
For post-tensioned structures, the falsework shall also
3.2 FALSEWORK AND FORMS
be designed to support any increased or redistribution of
loads caused by prestressing of the structure.
3.2.1 General
Loads imposed by falsework onto existing, new or par-
tially completed structures shall not exceed those permit-
Falsework is considered to be any temporary structure
which supports structural elements of concrete, steel, ma- ted in Article 8.15, “Application of Loads.”
sonry, or other materials during their construction or erec-
tion. Forms are considered to be the enclosures or panels 3.2.2.2 Foundations
which contain the fluid concrete and withstand the forces
due to its placement and consolidation. Forms may in turn Falsework shall be founded on a solid footing safe
be supported on falsework. Form travelers, as used in seg- against undermining, protected from softening, and capa-
mental cantilever construction, are considered to be a ble of supporting the loads imposed on it. When requested
combination of falsework and forms. by the Engineer, the Contractor shall demonstrate by suit-
Whenever the height of falsework exceeds 14 feet or able load tests that the soil bearing values assumed for the
whenever traffic, other than workmen involved in con- design of the falsework footings do not exceed the sup-
structing the bridge, will travel under the bridge, the porting capacity of the soil.
working drawings for the falsework shall be prepared and Falsework which cannot be founded on a satisfactory
sealed by a Registered Engineer. footing shall be supported on piling which shall be
Falsework and forms shall be of sufficient rigidity and spaced, driven, and removed in an approved manner.
strength to safely support all loads imposed, and produce
in the finished structure the lines and grades indicated on 3.2.2.3 Deflections
the plans. Forms shall also impart the required surface
texture and rustication, and shall not detract from the uni- For cast-in-place concrete structures, the calculated de-
formity of color of formed surfaces. flection of falsework flexural members shall not exceed
1/240 of their span irrespective of the fact that the deflec-
3.2.2 Falsework Design and Construction tion may be compensated for by camber strips.

3.2.2.1 Loads 3.2.2.4 Clearances

The design load for falsework shall consist of the Unless otherwise provided, the minimum dimensions
sum of dead and live vertical loads, and any horizontal of clear openings to be provided through falsework for
loads. roadways which are to remain open to traffic during con-
As a minimum, dead loads shall include the weight of struction shall be at least 5 feet greater than the width of
the falsework and all construction material to be sup- the approach traveled way, measured between barriers
ported. The combined weight of concrete, reinforcing and when used, and 14 feet high, except that the minimum
prestressing steel and forms shall be assumed to be not vertical clearance over interstate routes and freeways shall
less than 160 pounds per cubic foot of normal weight con- be 14.5 feet.
crete or 130 pounds per cubic foot of lightweight concrete
that is supported. 3.2.2.5 Construction
Live loads shall consist of the actual weight of any
equipment to be supported applied as concentrated loads Falsework shall be constructed and set to grades which
at the points of contact and a uniform load of not less than allow for its anticipated settlement and deflection, and for
20 pounds per square foot applied over the area supported, the vertical alignment and camber indicated on the plans
plus 75 pounds per linear foot applied at the outside edge or ordered by the Engineer for the permanent structure.
of deck overhangs. Variable depth camber strips shall be used between false-
The horizontal load used for the design of the work beams and soffit forms to accomplish this when di-
falsework bracing system shall be the sum of the horizon- rected by the Engineer.
tal loads due to equipment, construction sequence, in- Suitable screw jacks, pairs of wedges or other devices
cluding unbalanced hydrostatic forces from fluid shall be used at each post to adjust falsework to grade, to
concrete, stream flow when applicable, and an allowance permit minor adjustments during the placement of con-
3.2.2.5 DIVISION II—CONSTRUCTION 485

crete or structural steel should observed settlements de- standard. In selecting the hydrostatic pressure to be used
viate from those anticipated, and to allow for the gradual in the design of forms, consideration shall be given to the
release of the falsework. Telltales attached to the forms maximum rate of concrete placement to be used, the ef-
and extending to the ground, or other means, shall be fects of vibration, the temperature of the concrete and any
provided by the Contractor for accurate measurement of expected use of set-retarding admixtures or pozzolanic
falsework settlement during the placing and curing of the materials in the concrete mix.
concrete.
Falsework or formwork for deck slabs on girder 3.2.3.3 Construction
bridges shall be supported directly on the girders so that
there will be no appreciable differential settlement during Forms shall be set and held true to the dimensions,
placing of the concrete. Girders shall be braced and tied lines and grades of the structure prior to and during the
to resist any forces that would cause rotation or torsion in placement of concrete. Forms may be given a bevel or
the girders caused by the placing of concrete for di- draft at projections, such as copings, to ensure easy re-
aphragms or deck. Welding of falsework support brackets moval. Prior to reuse, forms shall be cleaned, inspected
or braces to structural steel members or reinforcing steel for damage and, if necessary, repaired. When forms ap-
will not be allowed unless specifically permitted. pear to be defective in any manner, either before or dur-
ing the placement of concrete, the Engineer may order the
3.2.3 Formwork Design and Construction work stopped until defects have been corrected.
Forms shall be treated with form oil or other approved
3.2.3.1 General release agent before the reinforcing steel is placed. Mate-
rial which will adhere to or discolor the concrete shall not
Forms shall be of wood, steel, or other approved mate- be used.
rial and shall be mortar tight and of sufficient rigidity to Except as provided herein, metal ties or anchorages
prevent objectional distortion of the formed concrete sur- within the forms shall be so constructed as to permit their
face due to pressure of the concrete and other loads inci- removal to a depth of at least 1 inch from the face without
dental to the construction operations. injury to the concrete. Ordinary wire ties may be used
Forms for concrete surfaces exposed to view shall pro- only when the concrete will not be exposed to view and
duce a smooth surface of uniform texture and color sub- where the concrete will not come in contact with salts or
stantially equal to that which would be obtained with the sulfates. Such wire ties, upon removal of the forms, shall
use of plywood conforming to the National Institute of be cut back at least 1 ⁄ 4 inch from the face of the concrete
Standards and Technology Product Standard PSI for Ex- with chisels or nippers; for green concrete, nippers shall
terior B-B Class I Plywood. Panels lining such forms shall be used. Fittings for metal ties shall be of such design that,
be arranged so that the joint lines form a symmetrical pat- upon their removal, the cavities that are left will be of the
tern conforming to the general lines of the structure. The smallest possible size. The cavities shall be filled with ce-
same type of form lining material shall be used through- ment mortar and the surface left sound, smooth, even, and
out each element of a structure. Such forms shall be suf- uniform in color.
ficiently rigid so that the undulation of the concrete sur- When epoxy-coated reinforcing steel is required, all
face shall not exceed 1 ⁄ 8 inch when checked with a metal ties, anchorages or spreaders which will remain in
5-foot-long straightedge or template. All sharp corners the concrete shall be of corrosion resistant material or
shall be filleted with approximately 3 ⁄ 4-inch chamfer coated with a dielectric material.
strips. For narrow walls and columns, where the bottom of the
Concrete shall not be deposited in the forms until all form is inaccessible, an access opening shall be provided
work connected with constructing the forms has been in the forms for cleaning out extraneous material imme-
completed, all debris has been removed, all materials to diately before placing the concrete.
be embedded in the concrete have been placed for the unit
to be cast, and the Engineer has inspected the forms and 3.2.3.4 Tube Forms
materials.
Tubes used as forms to produce voids in concrete slabs
3.2.3.2 Design shall be properly designed and fabricated or otherwise
treated to make the outside surface waterproof. Prior to
The structural design of formwork shall conform to concrete placement such tubes shall be protected from the
ACI Standard, “Recommended Practice for Concrete weather and stored and installed by methods that prevent
Formwork,” (ACI 347) or some other generally accepted distortion or damage. The ends of tube forms shall be cov-
486 HIGHWAY BRIDGES 3.2.3.4

ered with caps that shall be made mortar tight and water- Falsework for:
proof. If wood or other material that expands when moist Spans over 14 feet 14 days
is used for capping tubes, a premolded rubber joint filler Spans of 14 feet or less 10 days
1 ⁄ 4 inch in thickness shall be used around the perimeter of Bent caps not yet supporting girders 10 days
the caps to permit expansion. A PVC vent tube shall be
provided near each end of each tube. These vents shall be Forms:
constructed to provide positive venting of the voids. After Not supporting the dead 24 hours
exterior form removal, the vent tube shall be trimmed to weight of the concrete
within 1 ⁄ 2 inch of the bottom surface of the finished con- For interior cells of box 12 hours
crete. girders and for railings
Anchors and ties for tube forms shall be adequate to
prevent displacement of the tubes during concrete place- If high early strength is obtained with Type III cement
ment. or by the use of additional cement, these periods may be
reduced as directed.
3.2.3.5 Stay-in-Place Forms When field operations are controlled by cylinder tests,
the removal of supporting forms or falsework shall not
Stay-in-place deck soffit forms, such as corrugated begin until the concrete is found to have the specified
metal or precast concrete panels, may be used if compressive strength, provided further that in no case
shown on the plans or approved by the Engineer. Prior to shall supports be removed in less than 7 days after plac-
the use of such forms the Contractor shall provide a com- ing the concrete.
plete set of details to the Engineer for review and In addition to the above time requirements:
approval. The detailed plans for structures, unless other-
wise noted, are dimensioned for the use of removable Forms shall not be removed until the concrete has
forms and any changes necessary to accommodate sufficient strength to prevent damage to the surface.
stay-in-place forms, if approved, shall be at the expense Falsework for post-tensioned portions of structures
of the Contractor. shall not be released until the prestressing steel has
been tensioned.
Falsework supporting any span of a continuous or
3.2.4 Removal of Falsework and Forms
rigid frame bridge shall not be released until the
aforementioned requirements have been satisfied
3.2.4.1 General
for all of the structural concrete in that span and in
the adjacent portions of each adjoining span for a
Falsework or forms shall not be removed without ap-
length equal to at least one-half the length of the
proval of the Engineer. In the determination of the time for
span where falsework is to be released.
the removal of falsework and forms, consideration shall
be given to the location and character of the structure, the Unless otherwise specified or approved, falsework
weather, the materials used in the mix, and other condi- shall be released before the railings, copings or barriers
tions influencing the early strength of the concrete. are placed for all types of bridges. For arch bridges, the
Methods of removal likely to cause overstressing of the time of falsework release relative to the construction of el-
concrete or damage to its surface shall not be used. Sup- ements of the bridge above the arch shall be as shown on
ports shall be removed in such a manner as to permit the the plans or directed by the Engineer.
structure to uniformly and gradually take the stresses due
to its own weight. For arch structures of two or more
spans, the sequence of falsework release shall be as spec- 3.2.4.3 Extent of Removal
ified or approved.
All falsework and forms shall be removed except:
3.2.4.2 Time of Removal Portions of driven falsework piles more than 1 foot
below subgrade within roadbeds, or 2 feet below
If field operations are not controlled by beam or cylin- the original ground or finished grade outside of
der tests, the following minimum periods of time, exclu- roadbeds, or 2 feet below the established limits of
sive of days when the temperature is below 40F, shall any navigation channel.
have elapsed after placement of concrete before falsework Footing forms where their removal would endanger
is released or forms are removed: the safety of cofferdams or other work.
3.2.4.3 DIVISION II—CONSTRUCTION 487

Forms from enclosed cells where access is not 3.3.2 Protection of Concrete
provided.
Deck forms in the cells of box girder bridges that do Cofferdams shall be constructed so as to protect green
not interfere with the future installation of utilities concrete against damage from a sudden rising of the
shown on the plans. stream and to prevent damage to the foundation by ero-
sion. No struts or braces shall be used in cofferdams or
3.3 COFFERDAMS AND SHORING shoring systems in such a way as to extend into or through
the permanent work, without written permission from the
3.3.1 General Engineer.

Cofferdams and shoring consist of those structures 3.3.3 Removal


used to temporarily hold the surrounding earth and water
out of excavations and to protect adjacent property and fa- Unless otherwise provided or approved, cofferdams,
cilities during construction of the permanent work. and shoring with all sheeting and bracing shall be removed
Cofferdams shall be constructed to adequate depths, after the completion of the substructure, with care being
generally well below the bottom of the excavation, and to taken not to disturb or otherwise injure the finished work.
adequate heights to seal off all water. They shall be safely
designed and constructed, and be made as watertight as is
necessary for the proper performance of the work which 3.4 TEMPORARY WATER CONTROL SYSTEMS
must be done inside them. In general, the interior dimen-
sions of cofferdams shall be such as to give sufficient 3.4.1 General
clearance for the construction of forms and the inspection
of their exteriors, and to permit pumping from outside the Temporary water control systems consist of dikes, by-
forms. Cofferdams which are tilted or moved laterally pass channels, flumes and other surface water diversion
during the process of sinking shall be righted, reset, or en- works, cut-off walls and pumping systems, including
larged so as to provide the necessary clearance. This shall wellpoint and deep well systems, used to prevent water
be solely at the expense of the Contractor. from entering excavations for structures.
When water cannot be controlled so that footing con-
crete can be placed in the dry, a cofferdam shall be em- 3.4.2 Drawings
ployed, and a concrete seal conforming to the require-
ments of Section 8, “Concrete Structures” placed Working drawings for temporary water control sys-
underwater below the elevation of the footing. When such tems, when required, shall include details of the design
a seal is shown on the plans, the Engineer will determine and the equipment, operating procedures to be employed,
if a cofferdam and seal is required, the depth of the seal to and location of point or points of discharge. The design
be used, and the required cure time. Such determination and operation shall conform to all applicable water pollu-
will be based on conditions existing at the time of con- tion control requirements.
struction. When a concrete seal is not shown on the plans,
the Contractor shall make these determinations, and shall 3.4.3 Operations
be fully responsible for the performance of the seal. After
the seal has cured, the cofferdam shall then be pumped out Pumping from the interior of any foundation enclosure
and the balance of the masonry placed in the dry. When shall be done in such manner as to preclude the possibil-
weighted cofferdams are employed and the weight is uti- ity of the movement of water through any fresh concrete.
lized to partially overcome the hydrostatic pressure acting No pumping will be permitted during the placing of con-
against the bottom of the foundation seal, special anchor- crete or for a period of at least 24 hours thereafter, unless
age such as dowels or keys shall be provided to transfer it be done from a suitable sump separated from the con-
the entire weight of the cofferdam into the foundation crete work by a watertight wall or other effective means
seal. During the placing and curing of a foundation seal, subject to approval of the Engineer.
the elevation of the water inside the cofferdam shall be Pumping to unwater a sealed cofferdam shall not com-
controlled to prevent any flow through the seal, and if the mence until the seal has set sufficiently to withstand the
cofferdam is to remain in place, it shall be vented or hydrostatic pressure.
ported at or below low water level. Pumping from wellpoints or deep wells shall be regu-
Shoring shall be adequate to support all loads imposed lated so as to avoid damage by subsidence to adjacent
and shall comply with any applicable safety regulations. property.
488 HIGHWAY BRIDGES 3.5

3.5 TEMPORARY BRIDGES tails, including the maximum loads to be carried, shall be
submitted to the Engineer for approval. Such drawings
3.5.1 General shall be signed by a Registered Professional Engineer.
The design shall conform to AASHTO design standards
Temporary bridges include detour bridges for use by when applicable or to other appropriate standards.
the public, haul road bridges and other structures, such as
conveyor bridges, used by the Contractor. Temporary 3.5.4 Maintenance
bridges shall be constructed, maintained and removed in
The maintenance of temporary bridges for which
a manner that will not endanger the work or the public.
working drawings are required shall include their re-
placement in case of partial or complete failure. The De-
3.5.2 Detour Bridges
partment reserves the right, in case of the Contractor’s
delay or inadequate progress in making repairs and re-
When a design is furnished by the Department, detour
placement, to furnish such labor, materials, and supervi-
bridges shall be constructed and maintained to conform to
sion of the work as may be necessary to restore the struc-
such design or an approved alternative design. When per-
ture for proper movement of traffic. The entire expense of
mitted by the specifications, the Contractor may submit a
such restoration and repairs shall be considered a part of
proposed alternative design. Any alternative design must
the cost of the temporary structure and where such ex-
be equivalent in all respects to the design and details fur-
penditures are incurred by the Department, they shall be
nished by the Department and is subject to approval by the
charged to the Contractor.
Engineer. The working drawings and design calculations
for any alternative design must be signed by a Registered
3.6 MEASUREMENT AND PAYMENT
Professional Engineer.
When a design is not furnished by the Department, the
Unless otherwise provided, payment for temporary
Contractor shall prepare the design and furnish working
works shall be considered to be included in the payment
drawings to the Engineer for approval. The design shall
for the various items of work for which they are used and
provide the clearances, alignment, load capacity and other
no separate payment will be made therefore.
design parameters specified or approved. The design shall
When an item for concrete seals for cofferdams is in-
conform to the Standard Specifications for Highway
cluded in the bid schedule, such concrete will be mea-
Bridges adopted by AASHTO. If design live loads are not
sured and paid for as provided in Section 8, “Concrete
otherwise specified, an HS II 15-44 loading shall be used.
Structures.”
The working drawings and design calculations shall be
When an item or items for temporary bridges, coffer-
signed by a Registered Professional Engineer.
dams, shoring systems or water control systems is in-
cluded in the bid schedule, payment will be the lump sum
3.5.3 Haul Bridges bid for each such structure or system which is listed on the
bid schedule and which is constructed and removed in ac-
When haul road bridges or other bridges which are not cordance with the contract requirements. Such payment
for public use are proposed for construction over any includes full compensation for all costs involved with the
right-of-way which is open to the public or over any rail- furnishing of all materials and the construction, mainte-
road, working drawings showing complete design and de- nance, and removal of such temporary works.

You might also like