FALSEWORK
17 December 2020
Document Number
TGA-00-CN-0000-SPC-0819
REVISION RECORDING
TABLE OF CONTENTS
Contents
GENERAL ................................................................................................. 5
819.01 SCOPE ........................................................................................5
819.02 REFERENCES .................................................................................5
819.03 DEFINITIONS .................................................................................5
819.04 – 819.05 NOT USED .........................................................................5
PRODUCTS AND MATERIALS .......................................................................... 6
819.06 GENERAL .....................................................................................6
819.07 PROPRIETARY FALSEWORK ................................................................6
819.08 – 819.25 NOT USED .........................................................................6
OPERATIONS ............................................................................................ 6
819.26 GENERAL .....................................................................................6
819.27 SAFETY .......................................................................................6
819.28 DESIGN .......................................................................................7
819.29 LOAD TESTING (PROVISIONAL ITEM) .....................................................7
819.30 REMOVAL ....................................................................................8
819.31 – 819.70 NOT USED .........................................................................8
AS BUILT AND HANDOVER REQUIREMENTS ........................................................ 8
819.71 – 819.90 NOT USED .........................................................................8
CONTRACT SPECIFIC REQUIREMENTS ............................................................... 9
819.91 – 819.94 NOT USED .........................................................................9
819.95 PRECAST BEAM BRIDGES ...................................................................9
819.96 – 819.99 NOT USED .........................................................................9
SPECIFICATION 819
FALSEWORK
GENERAL
819.01 SCOPE
1. The work under this specification consists of the design and erection of
falsework required for the proper construction of the permanent Works and
after completion of these Works the dismantling and removal of falsework.
819.02 REFERENCES
Australian Standards
AS 3610 Formwork for Concrete
AS 5100 Bridge Design
819.03 DEFINITIONS
1. Footings shall comprise concrete bases or timber bed logs or other types Footings
of suitable materials and shall be of a size that will satisfactorily distribute
the bearing pressures under each footing.
2. All standards shall be securely fastened to sole plates and shall be Bracing
adequately braced in every direction necessary to provide rigid and stable Standards
support to the permanent Work. Where standards are used with extending
ends, the length of unbraced extensions shall be limited in accordance with
the manufacturer's published recommendations.
OPERATIONS
819.26 GENERAL
2. In the event that falsework settles under load to such an extent that the
allowable tolerances on the finished concrete work are exceeded then the
concrete shall be removed and the falsework modified so that the finished
work is in accordance with the Drawings. The cost of such remedial works
shall be at no cost to the Alliance.
819.27 SAFETY
1. All falsework shall comply with the requirements of the Occupational Worksafe
Safety and Health Regulations 1996.
819.28 DESIGN
1. The design of all falsework shall be in accordance with AS 3610, and shall Design by
be adequate in every way for the loads it is required to support and to Contractor
meet the requirements specified in Clause 819.26.
3. Falsework shall be designed and erected in such a manner that the loads
are accepted in accordance with the loading assumptions made. All
permanent structures such as piers and abutments which are adjacent to
or surrounded by falsework shall be adequately protected to ensure that
they are not damaged during the Contract.
5. At least two weeks prior to commencing falsework (including sheet HOLD POINT
piling) erection the Contractor shall supply to the Alliance Director or
Delegated Authority design details and drawings checked and
certified by a qualified structural engineer in accordance with the
Specification.
6. At least two weeks prior to the installation of sheet piling the HOLD POINT
Contractor shall supply to the Alliance Director or Delegated
Authority the proposed process description for installation and
removal.
819.29.01 GENERAL
1. When directed by the Alliance Director or Delegated Authority the Testing When
Contractor shall carry out load tests on representative areas of the Directed
completed soffit formwork.
3. The purpose of the tests will be to prove the structural adequacy of the
falsework/formwork system under overload.
1. The load shall be applied using kentledge. The load shall be equivalent to Kentledge
1.25 times the actual weight of the concrete plus a construction live load of
0.75kN per square metre.
2. The full test load shall be applied for at least twenty four hours during Tolerances
which time the Alliance will determine the displacement of the falsework
resulting from the application of the test load. The acceptance of the
system shall be subject to it sustaining no structural damage under the test
load and it being adequate such that the profile of the soffit surface after
pouring the concrete shall be in accordance with the Drawings and the
Formwork Tolerances.
819.29.04 NON-CONFORMANCE
1. If any section of the falsework under the test load displaces such that the Retesting a
profile of the cast concrete soffit will not be within the tolerances specified non-
or if the falsework under the test load shows signs of structural distress conformance
then the Contractor shall make the necessary modifications to the
falsework tested and to all other areas which would be similarly defective.
The Contractor shall then carry out a further test load on an area of the
modified falsework in accordance with this Specification. The costs of all
modifications and retesting shall be at no cost to the Alliance.
819.30 REMOVAL
1. After completion of the permanent works the Contractor shall dismantle all
falsework and remove it from the site. Where falsework is approved to
remain in position in the permanent works, this must be included in the as-
built documentation
1. The Contractor shall provide adequate temporary bracing for the beams to
prevent rotation and lateral movement due to superimposed loads.