Timeline Pemasangan New Rotor Wheel Nadrowsky PT.

MAG
Estimasi Lead Time (Hari)
No Planning Pekerjaan Ket
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
1 Travel To Site PT. MAG 2 Hari
2 Proses Pembongkaran 1 Hari
3 Travel to Medan 2 Hari
4 Proses Pekerjaan Workshop 7 Hari
5 Travel to Site PT. MAG 2 Hari
6 Proses Pemasangan & Comissioning 2 Hari