You are on page 1of 15

ID Task Task Name Duration Start Finish Resource

17 Names
Nov '19 24 Nov '19 01 Dec '19
Mode W T F S S M T W T F S S M T W
1 SUPPLY, 54 days Fri 22/11/19 Wed NEXT
INSTALLATION AND 05/02/20 ,KCAA,KCAA
COMMISSIONING OF ADMINS,NEXT
INTEGRATED IP TECHNOLOGIES
BASED CCTV AND SECURITY
ACCESS CONTROL EXPERT
SYSTEMS AT JKIA
AND MIA AND
STATIONS.
2 Preparation 21 days Fri 22/11/19 Fri 20/12/19 NEXT ,KCAA N
3 Sign contract 1 day Mon Mon NEXT ,KCAA
between vendor 23/12/19 23/12/19
and client
4 Sign contract 1 day Tue Tue NEXT
between vendor 24/12/19 24/12/19
and OEM
5 Issue PO to OEM 1 day Wed 25/12/19Wed 25/12/19NEXT
6 Supply and 1 day Thu Thu NEXT ,KCAA
delivery of the 26/12/19 26/12/19
various structured
cabling and access
controlequipment

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project plan KCAA cctv
Summary Manual Summary Rollup Progress
Date: Wed 26/02/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1
ID Task Task Name Duration Start Finish Resource
17 Names
Nov '19 24 Nov '19 01 Dec '19
Mode W T F S S M T W T F S S M T W
7 Structured Cabling 29 days Fri 27/12/19 Wed KCAA,KCAA
and access control 05/02/20 ADMINS,NEXT
installation Works TECHNOLOGIES
SECURITY
EXPERT
8 Terminate all 3 days Fri 27/12/19 Tue KCAA
the Cables at the 31/12/19 ADMINS,NEXT
doors and entry TECHNOLOGIES
ways SECURITY
9 Terminate the 2 days Wed Thu EXPERT
NEXT
cables 01/01/20 02/01/20 TECHNOLOGIES
10 Installation of 1 day SECURITY
Fri 03/01/20 Fri 03/01/20 KCAA
the biometric ADMINS,NEXT
access control TECHNOLOGIES
module SECURITY
11 Configuration of 1 day Mon Mon EXPERT
KCAA
the access 06/01/20 06/01/20 ADMINS,NEXT
control TECHNOLOGIES
system-Hikcentral SECURITY
12 software of 1 day
Installation Tue Tue EXPERT
KCAA
the security 07/01/20 07/01/20 ADMINS,NEXT
doors ans locks TECHNOLOGIES
SECURITY
EXPERT

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project plan KCAA cctv
Summary Manual Summary Rollup Progress
Date: Wed 26/02/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 2
ID Task Task Name Duration Start Finish Resource
17 Names
Nov '19 24 Nov '19 01 Dec '19
Mode W T F S S M T W T F S S M T W
13 Labeling and 3 days Wed Fri 10/01/20 KCAA
Testing all the 08/01/20 ADMINS,NEXT
cables and TECHNOLOGIES
terminated SECURITY
points EXPERT
14 CCTV and 18 days Mon Wed KCAA
Network 13/01/20 05/02/20 ADMINS,NEXT
Installation TECHNOLOGIES
Works SECURITY
15 Pulling all CAT 5 days Mon EXPERT
Fri 17/01/20 NEXT
6 cables from 13/01/20 TECHNOLOGIES
camera SECURITY
stations to EXPERT
the racks
16 Terminating 3 days Mon Wed NEXT
all network 20/01/20 22/01/20 TECHNOLOGIES
cables SECURITY
17 Mounting all 3 days Thu Mon EXPERT,KCAA
NEXT
the cameras 23/01/20 27/01/20 TECHNOLOGIES
at designated SECURITY
locations EXPERT

18 Mounting the 2 days Tue Wed NEXT


active 28/01/20 29/01/20 TECHNOLOGIES
equipment(Switches, SECURITY
NVR) into EXPERT

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project plan KCAA cctv
Summary Manual Summary Rollup Progress
Date: Wed 26/02/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 3
ID Task Task Name Duration Start Finish Resource
17 Names
Nov '19 24 Nov '19 01 Dec '19
Mode W T F S S M T W T F S S M T W
19 Testing the 1 day Thu Thu KCAA
network 30/01/20 30/01/20 ADMINS,NEXT
connections TECHNOLOGIES
between SECURITY
cameras,active EXPERT
equipment
and the
access control
20 system
Configuring 1 day Fri 31/01/20 Fri 31/01/20 KCAA
the cameras ADMINS,NEXT
and the NVRs TECHNOLOGIES
and the SECURITY
monitoring EXPERT
system

21 Project 3 days Mon Wed KCAA


documentation 03/02/20 05/02/20 ADMINS,NEXT
handover and TECHNOLOGIES
sign off SECURITY
22 Knowledge 1 day Mon Mon EXPERT
KCAA
transfer 03/02/20 03/02/20 ADMINS,NEXT
23 Prensenting 1 day Tue Tue TECHNOLOGIES
KCAA
the project 04/02/20 04/02/20 ADMINS,NEXT
documentation TECHNOLOGIES
to KCAA SECURITY
EXPERT,KCAA,NEXT

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project plan KCAA cctv
Summary Manual Summary Rollup Progress
Date: Wed 26/02/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 4
ID Task Task Name Duration Start Finish Resource
17 Names
Nov '19 24 Nov '19 01 Dec '19
Mode W T F S S M T W T F S S M T W
24 KCAA 1 day Wed Wed NEXT ,KCAA
confirming 05/02/20 05/02/20
that all
equipment
is working
as required

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project plan KCAA cctv
Summary Manual Summary Rollup Progress
Date: Wed 26/02/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 5
'19 08 Dec '19 15 Dec '19 22 Dec '19 29 Dec '19 05 Jan '20 12 Jan '20
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M

NEXT ,KCAA
NEXT ,KCAA

NEXT

NEXT
NEXT ,KCAA

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project plan KCAA cctv
Summary Manual Summary Rollup Progress
Date: Wed 26/02/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 6
'19 08 Dec '19 15 Dec '19 22 Dec '19 29 Dec '19 05 Jan '20 12 Jan '20
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M

KCAA ADMINS,NEXT TECHNOLOGIES SECURITY EX

NEXT TECHNOLOGIES SECURITY EXPERT

KCAA ADMINS,NEXT TECHNOLOGIES S

KCAA ADMINS,NEXT TECHN

KCAA ADMINS,NEXT TE

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project plan KCAA cctv
Summary Manual Summary Rollup Progress
Date: Wed 26/02/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 7
'19 08 Dec '19 15 Dec '19 22 Dec '19 29 Dec '19 05 Jan '20 12 Jan '20
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M
KCAA ADMI

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project plan KCAA cctv
Summary Manual Summary Rollup Progress
Date: Wed 26/02/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 8
'19 08 Dec '19 15 Dec '19 22 Dec '19 29 Dec '19 05 Jan '20 12 Jan '20
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project plan KCAA cctv
Summary Manual Summary Rollup Progress
Date: Wed 26/02/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 9
'19 08 Dec '19 15 Dec '19 22 Dec '19 29 Dec '19 05 Jan '20 12 Jan '20
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project plan KCAA cctv
Summary Manual Summary Rollup Progress
Date: Wed 26/02/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 10
12 Jan '20 19 Jan '20 26 Jan '20 02 Feb '20 09 Feb '20 16 Feb '20
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project plan KCAA cctv
Summary Manual Summary Rollup Progress
Date: Wed 26/02/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 11
12 Jan '20 19 Jan '20 26 Jan '20 02 Feb '20 09 Feb '20 16 Feb '20
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S

SECURITY EXPERT

TY EXPERT

NOLOGIES SECURITY EXPERT

,NEXT TECHNOLOGIES SECURITY EXPERT

INS,NEXT TECHNOLOGIES SECURITY EXPERT

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project plan KCAA cctv
Summary Manual Summary Rollup Progress
Date: Wed 26/02/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 12
12 Jan '20 19 Jan '20 26 Jan '20 02 Feb '20 09 Feb '20 16 Feb '20
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
KCAA ADMINS,NEXT TECHNOLOGIES SECURITY EXPERT

NEXT TECHNOLOGIES SECURITY EXPERT

NEXT TECHNOLOGIES SECURITY EXPERT,KCAA ADMINS

NEXT TECHNOLOGIES SECURITY EXPERT

NEXT TECHNOLOGIES SECURITY EXPERT

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project plan KCAA cctv
Summary Manual Summary Rollup Progress
Date: Wed 26/02/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 13
12 Jan '20 19 Jan '20 26 Jan '20 02 Feb '20 09 Feb '20 16 Feb '20
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
KCAA ADMINS,NEXT TECHNOLOGIES SECURITY EXPERT

KCAA ADMINS,NEXT TECHNOLOGIES SECURITY EXPERT

KCAA ADMINS,NEXT TECHNOLOGIES SECURITY EXPERT

KCAA ADMINS,NEXT TECHNOLOGIES SECURITY EXPERT,KCAA,NEXT

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project plan KCAA cctv
Summary Manual Summary Rollup Progress
Date: Wed 26/02/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 14
12 Jan '20 19 Jan '20 26 Jan '20 02 Feb '20 09 Feb '20 16 Feb '20
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
NEXT ,KCAA

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project plan KCAA cctv
Summary Manual Summary Rollup Progress
Date: Wed 26/02/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 15

You might also like