ID Task Task Name Duration Start Jul 23, '23 Jul 30, '23 Aug 6, '23 Aug 13,

Duration Start Jul 23, '23 Jul 30, '23 Aug 6, '23 Aug 13, '23
Mode S SMTWT F S SMTWT F S SMTWT F
0 Phase 1 - Evaluate the current situation 13 days Mon 7/31/23
1 Need Assessment- All Systems 8 days Mon 7/31/23
2 Identify stakeholders 1 day Mon 7/31/23 Manager
3 Interview owners of similar businesses 2 days Wed 8/2/23 Business Advisor,Manager
4 Investigate problem or opportunity 2 days Sun 8/6/23
5 Identify gaps in organizational capabilities- 2 days Tue 8/8/23
6 Document delivery 1 day Tue 8/8/23
7 Evaluate Business Approach 11 days Mon 7/31/23
8 Define new entity requirements 2 days Mon 7/31/23 Business Advisor
9 Summarize business approach 2 days Wed 8/2/23 Business Advisor
10 Document delivery 1 day Mon 8/14/23
11 Evaluate Potential Risks 9 days Sun 8/6/23
12 Assess System stability 2 days Sun 8/6/23 Business Advisor
13 Review and modify the strategic plan 1 day Tue 8/8/23 Business Advisor
14 Document delivery 1 day Wed 8/16/23

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Phase 1 - Evaluate the current situation
Summary Manual Summary Rollup Progress
Date: Mon 7/24/23
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1

You might also like