ID Task WBS Task Name Predecessors Duration Start

Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 20


Mode M J J A S O N D J F M A M J J
1 1 School Safety Threat Management 2335 days? Mon 11/27/23
2 1.1 Initiation Phase 1386.1 days Mon 11/27/23
3 1.1.1 Vendor Selection 0 days Mon 11/27/23 11/27
4 1.1.2 Internal Team Prep 267 days Fri 12/1/23
5 1.1.3 Documentation Review 31 days Mon Kelly,Prathamesh,Divy
(RFQ, statutes, etc.) 12/11/23
6 1.1.4 Project Management 450 days Mon 12/11/23
7 1.1.4.1 Conduct Status Meetings 442 days Thu 12/21/23
8 1.1.4.2 Status Reports 7 442 days Thu 12/21/23 K
9 1.1.4.3 Manage Project (CRAIDL) 8 441 days Fri 12/22/23 K
10 1.1.4.4 Project Management Complete
7,8,9 0 days Tue 3/20/29
11 1.1.5 Project Risk Complexity 72 days Fri 12/15/23
Assessment
12 1.1.5.1 Create Project Risk 5,10 6 days Fri 12/15/23 Keisha
Complexity Assessment
13 1.1.5.2 Review Project Risk 12 27 days Fri 12/22/23 Erica (EPMO)
Complexity Assessment
14 1.1.5.3 Incorporate changes into 13 19 days Mon 1/29/24 Keisha
Project Risk Complexity
Assessment
15 1.1.5.4 Submit Updated Risk 14 0 days Thu 2/22/24 2/22
Complexity Assessment
16 1.1.5.5 Review Project Risk 15 5 days Fri 2/23/24 Erica (EPMO)
Complexity Assessment

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project File
Summary Manual Summary Rollup Progress
Date: Mon 3/18/24
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1
ID Task WBS Task Name Predecessors Duration Start
Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 20
Mode M J J A S O N D J F M A M J J
17 1.1.5.6 Incorporate changes into 6 days Mon
Project Risk Complexity 11/23/26
Assessment
18 1.1.5.7 Submit Updated Risk 2 days Thu
Complexity Assessment 12/31/26
19 1.1.5.8 Review Project Risk 5 days Fri 3/8/24 Erica (EPMO)
Complexity Assessment
20 1.1.5.9 Incorporate changes into 19 5 days Mon 3/18/24 Keisha
Project Risk Complexity
Assessment Into
21 1.1.5.10 documents
Submit Updated Risk 20 2 days Mon 3/25/24 Keisha
Complexity Assessment
22 1.1.5.11 Project Risk Complexity 21 0 days Mon 2/15/27
Assessment Complete
23 1.1.6 Project Charter 45 days Thu 2/29/24
24 1.1.6.1 Create Project Charter 16 days Mon 2/26/24 K
25 1.1.6.2 Internal Review Project Charter
24 6 days Tue 11/17/26
26 1.1.6.3 Incorporate feedback to 25 4 days Wed
Project Charter 12/16/26
27 1.1.6.4 Submit Project Charter 26 0 days Tue
for Review 12/22/26
28 1.1.6.5 Internal Review Project Charter
27 6 days Tue 12/22/26
29 1.1.6.6 Incorporate feedback to 28 4 days Wed 2/17/27
Project Charter

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project File
Summary Manual Summary Rollup Progress
Date: Mon 3/18/24
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 2
ID Task WBS Task Name Predecessors Duration Start
Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 20
Mode M J J A S O N D J F M A M J J
30 1.1.6.7 Submit Project Charter 29 0 days Tue 2/23/27
for Review
31 1.1.6.8 External Review of the 27,28 0 days Wed 2/17/27
Project Charter
32 1.1.6.9 Incorporate Changes to 30,31 4 days Tue 2/23/27
the Project Charter
33 1.1.6.10 Review and Approve 32 4 days Mon 3/1/27
Project Management
34 1.1.6.11 Plan
Project Management Complete 0 days Wed 5/15/24 5/15
35 1.1.7 Project Management Plan (PMP) 51 days Tue 2/20/24
36 1.1.7.1 Create Project 24,32 16 days Mon 2/26/24 K
Management Plan
37 1.1.7.2 Internal Review Project 36 6 days Fri 3/5/27
Management Plan
38 1.1.7.3 Incorporate Feedback to 37 4 days Mon 3/15/27
Project Management
39 1.1.7.4 Plan
Submit Project 38 0 days Fri 3/19/27
Management Plan for
40 1.1.7.5 Review
Internal Review Project 39 6 days Fri 3/19/27
Management Plan
41 1.1.7.6 Incorporate Feedback to 40 4 days Mon 3/29/27
Project Management
42 1.1.7.7 Plan
Submit Project 41 0 days Fri 4/2/27
Management Plan for
43 1.1.7.8 Review
External Review for the 42 21 days Fri 4/2/27
Project Management
Plan
Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project File
Summary Manual Summary Rollup Progress
Date: Mon 3/18/24
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 3
ID Task WBS Task Name Predecessors Duration Start
Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 20
Mode M J J A S O N D J F M A M J J
44 1.1.7.9 Incorporate Feedback to 43 4 days Fri 5/7/27
Project Management
45 1.1.7.10 Plan and Approve
Review 44,43 4 days Thu 5/13/27
Project Management
46 1.1.7.11 Plan Management
Project 45 0 days Wed 5/19/27
Plan Complete
47 1.1.8 Project Schedule 62 days Tue 2/20/24
48 1.1.8.1 Create Project Schedule 16 days Tue 2/20/24 K
49 1.1.8.2 Internal Review Project 48 11 days Wed
Schedule 11/11/26
50 1.1.8.3 Incorporate feedback 49 6 days Wed 12/9/26
into Project Schedule
51 1.1.8.4 Submit Project Schedule 50 2 days Thu
for Review 12/17/26
52 1.1.8.5 Internal Review Project 51 6 days Mon
Schedule 12/21/26
53 1.1.8.6 Revise or Update Project 52 3 days Wed 2/24/27
Schedule
54 1.1.8.7 Submit Project Schedule 53,52 2 days Mon 3/1/27
for Review
55 1.1.8.8 External Review Project 54 11 days Wed 3/3/27
Schedule
56 1.1.8.9 Incorporate feedback 55 2 days Wed 4/14/27
into Project Schedule
57 1.1.8.10 Review and Approve 56 6 days Fri 4/16/27
updated Project Schedule
Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project File
Summary Manual Summary Rollup Progress
Date: Mon 3/18/24
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 4
ID Task WBS Task Name Predecessors Duration Start
Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 20
Mode M J J A S O N D J F M A M J J
58 1.1.8.11 Project Management 57 0 days Mon 6/7/27
Plan Complete
59 1.1.9 Initiation Phase Complete 10,34,46 0 days Tue 3/20/29
60 1.2 Planning Phase 0 days? Fri 8/29/25
61 1.2.1 Requirements Analysis 0 days Fri 8/29/25
62 1.2.2 JAD Sessions 0 days Fri 8/29/25
63 1.2.3 JADs 0 days Mon 1/22/24 1/22
64 1.2.3.1 SESIR Reporting 0 days Mon 1/22/24 1/22
65 1.2.3.1.1 Conduct SESIR 61 0 days Mon 1/22/24 1/22
Reporting
66 1.2.3.1.2 Requirements
Incorporate Session
Changes 65 3 days Mon 1/22/24 Divya,Kelly,Prathames
67 1.2.3.1.3 Schedule Follow-up Session
66 0 days Wed 1/24/24 1/24
68 1.2.3.1.4 Conduct SESIR 67 0 days Mon 2/19/24 2/19
Reporting
Requirements Session
69 1.2.3.1.5 Iteration 2 Changes 68
Incorporate 0 days Mon 2/19/24 2/19
70 1.2.3.1.6 Schedule Follow-up Session
69 0 days Mon 2/19/24 2/19
71 1.2.3.1.7 Conduct SESIR 70 0 days Tue 2/20/24 2/20
Reporting
Requirements Session
72 1.2.3.1.8 Iteration 3 Changes 71
Incorporate 0 days Tue 2/20/24 2/20
73 1.2.3.1.9 Schedule Follow-up 72 0 days Mon 2/26/24 2/26
Session with
Stakeholders

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project File
Summary Manual Summary Rollup Progress
Date: Mon 3/18/24
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 5
ID Task WBS Task Name Predecessors Duration Start
Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 20
Mode M J J A S O N D J F M A M J J
74 1.2.3.1.10 Review Vision 73 2 days Mon 2/26/24 Divya,Kelly,Pratha
Statement doc from
75 1.2.3.1.11 Stakeholder(new)
Incorporate Changes 74 0 days Wed 2/28/24 2/28
76 1.2.3.1.12 Submit Updated SESIR 75 0 days Wed 2/28/24 2/28
Reporting
Requirements for
77 1.2.3.1.13 Review by
Conduct Final SESIR 76 0 days Thu 2/29/24 2/29
Reporting
Requirements Session
78 1.2.3.1.14 Iteration Final
Conduct 4 SESIR 77 0 days Thu 2/29/24 2/29
Reporting
Requirements Session
79 1.2.3.1.15 Iteration 4 ptChanges
Incorporate II 78 8 days Thu 2/29/24 Divya,Kelly,Prath
80 1.2.3.1.16 Submit Document for 79 5 days Mon 3/18/24 Keisha
Review by
81 1.2.3.1.17 Stakeholders
Review and Approve 80 4 days Mon 3/25/24 OSS
SESIR Reporting
Requirements by
82 1.2.3.1.18 Stakeholders
Submit SESIR 81 10 days Wed 4/3/24 K
Reporting
Requirements to
83 1.2.3.1.19 EPMO for Review
Incorporate 82 2 days Thu
changes/updates from 11/26/26
84 1.2.3.1.20 EPMO SESIR
Submit 83 0 days Mon
Reporting 11/30/26
Requirements to
EPMO for Final Review
Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project File
Summary Manual Summary Rollup Progress
Date: Mon 3/18/24
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 6
ID Task WBS Task Name Predecessors Duration Start
Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 20
Mode M J J A S O N D J F M A M J J
85 1.2.3.1.21 Review and Approve 84 5 days Mon
SESIR Reporting 11/30/26
Requirements by
86 1.2.3.1.22 EPMO SESIR
Submit 85 5 days Fri 1/22/27
Reporting
Requirements to
87 1.2.3.1.23 Vendor for Review
Incorporate 86 3 days Fri 1/29/27
changes/updates from
88 1.2.3.1.24 Vendor SESIR
Submit 87 4 days Fri 3/12/27
Reporting
Requirements to
89 1.2.3.1.25 Vendor and
Review for Final
Approve 88 6 days Wed
SESIR Reporting 11/14/29
Requirements by
90 1.2.3.1.26 Vendor SESIR
Submit 89 10 days Fri 11/23/29
Reporting
Requirements to
91 1.2.3.1.27 Leadership for Review
Incorporate 90 3 days Tue 6/22/32
changes/updates from
92 1.2.3.1.28 Leadership
Submit SESIR 91 2 days Tue 7/20/32
Reporting
Requirements to
93 1.2.3.1.29 Leadershp
Review andfor Final
Approve 92 2 days Thu 7/22/32
SESIR Reporting
Requirements by
Leadership

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project File
Summary Manual Summary Rollup Progress
Date: Mon 3/18/24
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 7
ID Task WBS Task Name Predecessors Duration Start
Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 20
Mode M J J A S O N D J F M A M J J
94 1.2.3.1.30 Conduct SESIR 93 2 days Mon 7/26/32
Reporting
95 1.2.3.1.31 Requirements Session
Remediate 94 2 days Wed 7/28/32
RTM/Incorporate
96 1.2.3.1.32 Changes Session with
Schedule 95 2 days Fri 7/30/32
Stakeholders
97 1.2.3.1.33 Conduct SESIR 96 2 days Tue 8/3/32
Reporting
98 1.2.3.1.34 Requirements
Remediate Session 97 2 days Thu 8/5/32
RTM/Incorporate
99 1.2.3.1.35 Changes
Conduct SESIR 98 2 days Mon 8/9/32
Reporting
100 1.2.3.1.36 Requirements
Remediate Session 99 2 days Wed 8/11/32
RTM/Incorporate
101 1.2.3.1.37 Changes
Submit Document for 100 2 days Fri 8/13/32
Review by
102 1.2.3.1.38 Stakeholders
Review and Approve 101 2 days Tue 8/17/32
SESIR Reporting
Requirements by
103 1.2.3.1.39 Stakeholders
Submit SESIR 102 2 days Thu 8/19/32
Reporting
Requirements to
104 1.2.3.1.40 EPMO for Review
Incorporate 103 2 days Mon 8/23/32
changes/updates from
EPMO

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project File
Summary Manual Summary Rollup Progress
Date: Mon 3/18/24
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 8
ID Task WBS Task Name Predecessors Duration Start
Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 20
Mode M J J A S O N D J F M A M J J
105 1.2.3.1.41 Submit SESIR 104 2 days Wed 8/25/32
Reporting
Requirements to
106 1.2.3.1.42 EPMO for
Review andFinal Review
Approve 105 2 days Fri 8/27/32
SESIR Reporting
Requirements by
107 1.2.3.1.43 EPMO
Submit SESIR 106 2 days Tue 8/31/32
Reporting
Requirements to
108 1.2.3.1.44 Vendor for Review
Incorporate 107 2 days Thu 9/2/32
changes/updates from
109 1.2.3.1.45 Vendor SESIR
Submit 108 2 days Mon 9/6/32
Reporting
Requirements
110 1.2.3.1.46 toVendor
Review andforApprove
Final 109 2 days Wed 9/8/32
SESIR Reporting
Requirements by
111 1.2.3.1.47 Vendor SESIR
Submit 110 2 days Fri 9/10/32
Reporting
Requirements to
112 1.2.3.1.48 Leadership for Review
Incorporate 111 2 days Tue 9/14/32
changes/updates from
113 1.2.3.1.49 Leadership
Submit SESIR 112 2 days Thu 9/16/32
Reporting
Requirements to
Leadershp for Final

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project File
Summary Manual Summary Rollup Progress
Date: Mon 3/18/24
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 9
ID Task WBS Task Name Predecessors Duration Start
Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 20
Mode M J J A S O N D J F M A M J J
114 1.2.3.1.50 Review and Approve 113 8 days Mon 9/20/32
SESIR Reporting
Requirements by
115 1.2.4 Leadership
Threat Management & 71 days Mon
Threat Assessment 1/29/24
116 1.2.4.1 Conduct Threat Mgmt & 3 days Mon 1/29/24 Keisha
Threat Assessment
117 1.2.4.2 Session
Incorporate Changes 116 2 days Tue 1/30/24 Divya,Kelly,Prathame
118 1.2.4.3 Schedule Follow-up Session
117 4 days Wed 1/31/24 Keisha
119 1.2.4.4 Conduct Threat Mgmt & 118 3 days Mon 2/5/24 Keisha
Threat Assessment
120 1.2.4.5 Iteration 2 Changes
Incorporate 119 0 days Tue 2/6/24 2/6
121 1.2.4.6 Submit Updated Threat 120 0 days Wed 2/28/24 2/28
Mgmt & Threat
Assessment
Requirements for Review
122 1.2.4.7 by Stakeholders
Conduct Final Threat 121 6 days Fri 3/1/24 K
Mgmt & Threat
Assessment
Requirements Session
123 1.2.4.8 Iteration 3/4Changes
Incorporate 122 6 days Fri 12/4/26
124 1.2.4.9 Review/Approve Threat 123 5 days Wed
Mgmt & Threat Assessmt 12/23/26
Requirements by
Stakeholder

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project File
Summary Manual Summary Rollup Progress
Date: Mon 3/18/24
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 10
ID Task WBS Task Name Predecessors Duration Start
Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 20
Mode M J J A S O N D J F M A M J J
125 1.2.4.10 Confirm Workgroup for 124 8 days Thu
Notifications and Alerts 12/31/26
Requirements
126 1.2.4.11 Schedule Session 125 8 days Tue 1/12/27
127 1.2.4.12 Submit Notifications and 126 8 days Fri 1/22/27
Alerts Document for
Review by Stakeholder
128 1.2.4.13 Conduct Notifications 127 9 days Wed 2/3/27
and Alerts Requirements
129 1.2.4.14 Session
Remediate 128 10 days Tue 2/16/27
RTM/Incorporate
130 1.2.4.15 ChangesDocument for
Submit 129 11 days Tue 3/2/27
Review by Stakeholders
131 1.2.4.16 Conduct Notifications 130 12 days Wed 3/17/27
and Alerts Requirements
132 1.2.4.17 Session
Remediate 131 13 days Fri 4/2/27
RTM/Incorporate
133 1.2.4.18 Changesand Approve
Review 132 13 days Wed 4/21/27
Notifications and Alerts
Requirements by
134 1.2.4.19 Stakeholders
Submit Threat Mgmt & 133 5 days Mon 5/10/27
Threat Assessment
Requirements to EPMO
135 1.2.4.20 for Review
Incorporate 134 3 days Mon 5/17/27
changes/updates from
EPMO

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project File
Summary Manual Summary Rollup Progress
Date: Mon 3/18/24
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 11
ID Task WBS Task Name Predecessors Duration Start
Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 20
Mode M J J A S O N D J F M A M J J
136 1.2.4.21 Submit Threat Mgmt & 135 0 days Tue 6/15/27
Threat Assessment
Requirements to EPMO
137 1.2.4.22 for Finaland
Review Review
Approve 136 6 days Tue 6/15/27
Threat Mgmt & Threat
Assessment
138 1.2.4.23 Requirements
Submit Threat by EPMO
Mgmt & 137 3 days Wed 7/7/27
Threat Assessment
Requirements to Vendor
139 1.2.4.24 for Review
Incorporate 138 0 days Thu 8/5/27
changes/updates from
140 1.2.4.25 Vendor Threat Mgmt &
Submit 139 6 days Thu 8/5/27
Threat Assessment
Requirements toVendor
141 1.2.4.26 for Finaland
Review Review
Approve 140 2 days Fri 8/13/27
Threat Mgmt & Threat
Assessment
142 1.2.4.27 Requirements
Submit Threat by Vendor
Mgmt & 141 2 days Tue 8/17/27
Threat Assessment
Requirements to
143 1.2.4.28 Leadership for Review
Incorporate 142 0 days Thu 8/19/27
changes/updates from
144 1.2.4.29 Leadership
Submit Threat Mgmt & 143 0 days Thu 8/19/27
Threat Assessment
Requirements to
Leadershp for Final

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project File
Summary Manual Summary Rollup Progress
Date: Mon 3/18/24
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 12
ID Task WBS Task Name Predecessors Duration Start
Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 20
Mode M J J A S O N D J F M A M J J
145 1.2.4.30 Review and Approve 144 5 days Thu 8/19/27
Threat Mgmt & Threat
Assessment
146 1.2.4.31 Requirements
Attend Threat by 145 0 days Fri 2/23/24 2/23
Assessment Training
147 1.2.4.32 User Stories 146 0 days Fri 2/23/24 2/23
148 1.2.4.33 Create User Stories for 147 7 days Mon 3/4/24 Prathamesh
Approved Requirements
(SESIR Reporting and
Threat Assess & Mgmt)
149 1.2.4.34 Review and Approve by 148 5 days Tue 3/12/24 Keisha
Stakeholder
150 1.2.4.35 Incorporate 149 3 days Tue 3/19/24 Prathamesh
changes/updates from
151 1.2.4.36 Leadership
Submit Document for 150 5 days Fri 3/22/24 Keisha
Review by Stakeholder
152 1.2.4.37 Review/Approve User 151 3 days Fri 3/29/24 Angie
Stories by Stakeholder
153 1.2.4.38 Submit Approved User 152 5 days Wed 4/3/24 Keisha
Stories to EPMO for
154 1.2.4.39 Review
Incorporate 153 5 days Wed 4/10/24 Prathame
changes/updates from
155 1.2.4.40 EPMO
Submit Approved User 154 5 days Thu 5/30/24 Keisha
Stories to EPMO for Final
156 1.2.4.41 Review and Approve 155 5 days Thu 6/6/24 Eric
User Stories by EPMO

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project File
Summary Manual Summary Rollup Progress
Date: Mon 3/18/24
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 13
ID Task WBS Task Name Predecessors Duration Start
Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 20
Mode M J J A S O N D J F M A M J J
157 1.2.4.42 Submit Approved User 156 5 days Fri 7/26/24 Ke
Stories to Vendor for
158 1.2.4.43 Review
Incorporate 157 5 days Fri 8/2/24
changes/updates from
159 1.2.4.44 Vendor Approved User 158
Submit 5 days Tue 8/27/24
Stories toVendor for
160 1.2.4.45 Final Review
Review Approved User 159 5 days Tue 9/3/24
Stories Requirements by
161 1.2.4.46 Vendor
Submit Approved User 160 5 days Tue 9/10/24
Stories to Leadership for
162 1.2.4.47 Review
Incorporate 161 5 days Tue 9/17/24
changes/updates from
163 1.2.4.48 Leadership
Submit Approve User 162 5 days Tue 9/24/24
Stories to Leadershp for
164 1.2.4.49 Final
ReviewReview
and Approve 163 5 days Tue 10/1/24
User Stories by
165 1.2.4.50 Leadership
Business Process Flow Diagram
164 5 days Mon 10/14/24
166 1.2.4.51 Develop Business Process 165 5 days Mon
Flow Diagram 10/21/24
167 1.2.4.52 Team review of Business 166 0 days Mon
Process Flow Diagram 10/28/24
168 1.2.4.53 Incorporate feedback 167 4 days Mon
from Team for Business 10/28/24
Process Flow Diagram

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project File
Summary Manual Summary Rollup Progress
Date: Mon 3/18/24
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 14
ID Task WBS Task Name Predecessors Duration Start
Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 20
Mode M J J A S O N D J F M A M J J
169 1.2.4.54 Submit Internal Business 168 6 days Fri 11/8/24
Process Flow Diagram for
Review to EMPO
170 1.2.4.55 Incorporate 169 3 days Mon
changes/updates for 11/18/24
Business Process Flow
171 1.2.4.56 Diagram from EPMO
Submit Process Business 170 0 days Fri 11/29/24
Flow Diagram to EMPO
for Final Review
172 1.2.4.57 Review and Approve 171 10 days Fri 11/29/24
Process Flow Diagram by
173 1.2.4.58 EMPO Approved Process 172
Submit 2 days Wed 1/15/25
Flow Diagram to Vendor
174 1.2.4.59 for Review
Incorporate 173 3 days Fri 1/17/25
changes/updates from
175 1.2.4.60 Vendor
Submit Approved Process 174 0 days Fri 1/24/25
Flow Diagram toVendor
for Final Review
176 1.2.4.61 Review Approved 175 0 days Fri 1/24/25
Process Flow Diagram by
177 1.2.4.62 Vendor Approved Process 176
Submit 0 days Fri 1/24/25
Flow Diagram to
Leadership for Review
178 1.2.4.63 Incorporate 177 0 days Fri 1/24/25
changes/updates from
Leadership

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project File
Summary Manual Summary Rollup Progress
Date: Mon 3/18/24
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 15
ID Task WBS Task Name Predecessors Duration Start
Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 20
Mode M J J A S O N D J F M A M J J
179 1.2.4.64 Submit Approve Process 178 0 days Fri 1/24/25
Flow Diagram to
Leadershp for Final
180 1.2.4.65 Review and Approve 179 0 days Fri 1/24/25
Business Process Flow
Diagram by Leadership
181 1.2.4.66 Notifications and Alerts 180 0 days Fri 1/24/25
182 1.2.4.67 Confirm Workgroup for 181 4 days Fri 1/24/25 A
Notifications and Alerts
Requirements
183 1.2.4.68 Conduct Notifications 182 0 days Wed
and Alerts Session 10/27/27
184 1.2.4.69 Incorporate Changes 183 5 days Wed 10/27/27
185 1.2.4.70 Schedule follow-up session184 0 days Wed 11/24/27
186 1.2.4.71 Conduct Notifications 185 0 days Wed
and Alerts Session 11/24/27
187 1.2.4.72 Iteration 2 Changes
Incorporate 186 5 days Wed 11/24/27
188 1.2.4.73 Submit Updated 187 0 days Fri 12/10/27
Notifications and Alerts
Review by Stakeholders
189 1.2.4.74 Conduct Final 188 0 days Fri 12/10/27
Notifications and Alerts
Review by Stakeholders
190 1.2.4.75 Iteration 3 Changes
Incorporate 189 2 days Fri 12/10/27

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project File
Summary Manual Summary Rollup Progress
Date: Mon 3/18/24
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 16
ID Task WBS Task Name Predecessors Duration Start
Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 20
Mode M J J A S O N D J F M A M J J
191 1.2.4.76 Submit Document for 190 0 days Tue
Review by Stakeholder 12/14/27
192 1.2.4.77 Review/Approve 191 3 days Tue
Notifications and Alerts 12/14/27
Requirements by
193 1.2.4.78 Stakeholder
Submit Threat Mgmt & 192 6 days Fri 12/17/27
Threat Assessment
Requirements to EPMO
194 1.2.4.79 for Review
Incorporate 193 3 days Mon
changes/updates from 12/27/27
195 1.2.4.80 EPMO Threat Mgmt &
Submit 194 2 days Thu
Threat Assessment 12/30/27
Requirements to EPMO
196 1.2.4.81 for Finaland
Review Review
Approve 195 6 days Mon 1/3/28
Threat Mgmt & Threat
Assessment
197 1.2.4.82 Requirements
Submit Threat by EPMO
Mgmt & 196 3 days Tue 1/11/28
Threat Assessment
Requirements to Vendor
198 1.2.4.83 for Review
Incorporate 197 3 days Fri 1/14/28
changes/updates from
199 1.2.4.84 Vendor Threat Mgmt &
Submit 198 6 days Wed 1/19/28
Threat Assessment
Requirements toVendor
for Final Review

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project File
Summary Manual Summary Rollup Progress
Date: Mon 3/18/24
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 17
ID Task WBS Task Name Predecessors Duration Start
Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 20
Mode M J J A S O N D J F M A M J J
200 1.2.4.85 Review and Approve 199 0 days Thu 1/27/28
Threat Mgmt & Threat
Assessment
201 1.2.4.86 Requirements
Submit Threat by Vendor
Mgmt & 200 3 days Thu 1/27/28
Threat Assessment
Requirements to
202 1.2.4.87 Leadership
Incorporatefor Review 201 0 days Tue 2/1/28
changes/updates from
203 1.2.4.88 Leadership
Submit Threat Mgmt & 202 0 days Tue 2/1/28
Threat Assessment
Requirements to
204 1.2.4.89 Leadershp
Review andfor Final
Approve 203 6 days Tue 2/1/28
Threat Mgmt & Threat
Assessment
205 1.2.5 Requirements
Requirements by
Traceability 6 days? Wed 5/1/24
Matrix (RTM)
206 1.2.5.1 Develop RTM 5 days Fri 1/26/24 Divya,Kelly,Prathame
207 1.2.5.2 Internal Review RTM 206 6 days Thu 2/1/24 EPMO
208 1.2.5.3 Incorporate feedback to RTM
207 5 days Thu 2/8/24 Divya,Kelly,Pratham
209 1.2.5.4 Develop RTM 208 7 days Wed 2/14/24 Divya,Kelly,Pratham
210 1.2.5.5 Internal Review RTM 209 7 days Thu 2/22/24 EPMO
211 1.2.5.6 Incorporate feedback to RTM
210 6 days Fri 3/1/24 Divya,Kelly,Prath
212 1.2.5.7 Internal Review RTM 211 4 days Fri 3/15/24 EPMO
213 1.2.5.8 Incorporate feedback to RTM
212 3 days Thu 3/21/24 Kelly
214 1.2.5.9 Submit RTM for Review 213 2 days Wed 3/27/24 Keisha

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project File
Summary Manual Summary Rollup Progress
Date: Mon 3/18/24
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 18
ID Task WBS Task Name Predecessors Duration Start
Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 20
Mode M J J A S O N D J F M A M J J
215 1.2.5.10 External Review of RTM 214 4 days Fri 3/29/24 EPMO
216 1.2.5.11 Incorporate feedback to RTM
215 2 days Thu 4/4/24 Kelly
217 1.2.5.12 Requirements 216 0 days Tue 4/9/24 4/9
Traceability Matrix
218 1.2.6 Complete and
Operational 0 days? Tue 4/9/24 4/9
Maintenance Plan
219 1.2.6.1 Complete
Develop Operational and 0 days Tue 4/9/24 4/9
Maintenance Plan
220 1.2.6.2 Review the Operational 219 0 days Tue 4/9/24 4/9
and Maintenance Plan
221 1.2.6.3 Incorporate feedback to 220 0 days Tue 4/9/24 4/9
the Operational and
Maintenance Plan
222 1.2.6.4 Submit Operational and 221 0 days Tue 4/9/24 4/9
Maintenance Plan
223 1.2.6.5 External Review the 222 0 days Tue 4/9/24 4/9
Operational and
Maintenance Plan
224 1.2.6.6 Incorporate feedback to 223 0 days Tue 4/9/24 4/9
the Operational and
Maintenance Plan
225 1.2.6.7 Review and Approve the 224 0 days Tue 4/9/24 4/9
Operational and
Maintenance Plan
226 1.2.7 System Design 0 days? Tue 3/19/24 3/19

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project File
Summary Manual Summary Rollup Progress
Date: Mon 3/18/24
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 19
ID Task WBS Task Name Predecessors Duration Start
Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 20
Mode M J J A S O N D J F M A M J J
227 1.2.7.1 Business Requirements 0 days? Tue 3/19/24 3/19
Management Plan
228 1.2.7.1.1 Develop Requirements 0 days Tue 3/19/24 3/19
Document
229 1.2.7.1.2 Intermal Review 228 0 days Tue 3/19/24 3/19
Requirements
Document
230 1.2.7.1.3 Incorporate feedback 229 0 days Tue 3/19/24 3/19
to Requirements
Document
231 1.2.7.1.4 Submit Requirements 230 0 days Tue 3/19/24 3/19
Document for Review
to EMPO
232 1.2.7.1.5 Develop Requirements 231 0 days Tue 3/19/24 3/19
Document
233 1.2.7.1.6 Internal Review 232 0 days Tue 3/19/24 3/19
Requirements
Document
234 1.2.7.1.7 Incorporate feedback 233 0 days Tue 3/19/24 3/19
to Requirements
Document
235 1.2.7.1.8 Submit Requirements 234 0 days Tue 3/19/24 3/19
Document for Review
to EMPO

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project File
Summary Manual Summary Rollup Progress
Date: Mon 3/18/24
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 20
ID Task WBS Task Name Predecessors Duration Start
Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 20
Mode M J J A S O N D J F M A M J J
236 1.2.7.1.9 External Review of 235 0 days Tue 3/19/24 3/19
Requirements
Document
237 1.2.7.1.10 Incorporate feedback 236 0 days Tue 3/19/24 3/19
to Requirements
Document
238 1.2.7.1.11 Review and Approve 237 0 days Tue 3/19/24 3/19
Requirements
Document
239 1.2.7.1.12 Requirements 238 0 days Tue 3/19/24 3/19
Document Complete

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project File
Summary Manual Summary Rollup Progress
Date: Mon 3/18/24
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 21
Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028
J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A

Keisha
athamesh,Divya

Keisha
Keisha

PMO)

ha

a (EPMO)

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project File
Summary Manual Summary Rollup Progress
Date: Mon 3/18/24
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 22
Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028
J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
Keisha

Keisha

ica (EPMO)

eisha

eisha

2/15

Keisha
Erica (EPMO)
Keisha

12/22

Erica (EPMO)
Keisha

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project File
Summary Manual Summary Rollup Progress
Date: Mon 3/18/24
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 23
Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028
J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
2/23

2/17

Keisha

Shawna (Sponsor)

5/15

Keisha

Erica (EPMO)

Keisha

3/19

Erica (EPMO)

Keisha

4/2

Shawna (Sponsor)

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project File
Summary Manual Summary Rollup Progress
Date: Mon 3/18/24
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 24
Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028
J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
Keisha

Shawna (Sponsor)

5/19

Keisha
Erica (EPMO)

Keisha

Keisha

Erica (EPMO)

Keisha

Keisha

Shawna (Sponsor)

Keisha

Shawna (Sponsor)

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project File
Summary Manual Summary Rollup Progress
Date: Mon 3/18/24
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 25
Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028
J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
6/7

8/29
8/29
8/29

elly,Prathamesh

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project File
Summary Manual Summary Rollup Progress
Date: Mon 3/18/24
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 26
Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028
J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
a,Kelly,Prathamesh

8
8

vya,Kelly,Prathamesh
eisha

OSS

Keisha,Erica (EPMO)

Prathamesh

11/30

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project File
Summary Manual Summary Rollup Progress
Date: Mon 3/18/24
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 27
Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028
J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
Erica (EPMO)

Vendor

Prathamesh

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project File
Summary Manual Summary Rollup Progress
Date: Mon 3/18/24
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 28
Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028
J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project File
Summary Manual Summary Rollup Progress
Date: Mon 3/18/24
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 29
Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028
J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project File
Summary Manual Summary Rollup Progress
Date: Mon 3/18/24
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 30
Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028
J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A

Kelly,Prathamesh

Keisha

Divya,Kelly,Prathamesh
OSS

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project File
Summary Manual Summary Rollup Progress
Date: Mon 3/18/24
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 31
Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028
J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A

Keisha

Prathamesh

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project File
Summary Manual Summary Rollup Progress
Date: Mon 3/18/24
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 32
Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028
J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
6/15

Prathamesh

Prathamesh

8/5

8/19

8/19

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project File
Summary Manual Summary Rollup Progress
Date: Mon 3/18/24
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 33
Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028
J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A

athamesh

eisha

rathamesh

Keisha

Angie

Keisha

Prathamesh

Keisha

Erica (EPMO)

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project File
Summary Manual Summary Rollup Progress
Date: Mon 3/18/24
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 34
Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028
J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
Keisha

Prathamesh

Keisha

Vendor

Keisha

Prathamesh

Keisha

Shawna (Sponsor)

Kelly/Diviya

10/28

Divya,Kelly

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project File
Summary Manual Summary Rollup Progress
Date: Mon 3/18/24
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 35
Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028
J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
Keisha

Divya,Kelly

11/29

Amanda,Erica (EPMO),Shawna (Sponsor)

Keisha

Kelly

1/24

1/24

1/24

1/24

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project File
Summary Manual Summary Rollup Progress
Date: Mon 3/18/24
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 36
Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028
J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
1/24

1/24

1/24
Angie,Keisha

10/27

Divya,Kelly,Prathamesh
11/24
11/24

Divya,Kelly,Prathamesh
12/10

12/10

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project File
Summary Manual Summary Rollup Progress
Date: Mon 3/18/24
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 37
Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028
J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
12/14

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project File
Summary Manual Summary Rollup Progress
Date: Mon 3/18/24
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 38
Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028
J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
1/27

2/1

2/1

Kelly,Prathamesh

,Kelly,Prathamesh
a,Kelly,Prathamesh
MO
vya,Kelly,Prathamesh
PMO
elly
Keisha

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project File
Summary Manual Summary Rollup Progress
Date: Mon 3/18/24
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 39
Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028
J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
EPMO
Kelly
4/9

4/9

4/9

4/9

4/9

4/9

4/9

4/9

4/9

19

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project File
Summary Manual Summary Rollup Progress
Date: Mon 3/18/24
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 40
Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028
J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
19

19

19

19

19

19

19

19

19

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project File
Summary Manual Summary Rollup Progress
Date: Mon 3/18/24
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 41
Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028
J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
19

19

19

19

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project File
Summary Manual Summary Rollup Progress
Date: Mon 3/18/24
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only