ID Task Task Name Duration Start Finish Predecessors Resource Names 3 Apr '17 10 Apr '17 17 Apr '17

Mode S S M T W T F S S M T W T F S S M T W T F
1 Eccentrics 51 days Mon 3/04/17 Mon 5/06/17
2 Machining bore, spline and 5 days Mon 3/04/17 Fri 7/04/17
circlet groove
3 Build up 15 days 2
4 PWHT 4 days Tue 25/04/17 Fri 28/04/17 3
5 Finish machining circlet groove 5 days Sat 29/04/17 Thu 4/05/17 4
and bore, turning spline for
NDT
6 NDT 1 day Fri 5/05/17 Fri 5/05/17 5
7 Programing Inno to cut spline 1 day 2
8 Finish Machine spline 10 days Mon 8/05/17 Fri 19/05/17 6
9 Hand dress 4 days Thu 25/05/17 8
10 Inspection 1 day Fri 26/05/17 Fri 26/05/17 9
11 Paint 2 days Tue 30/05/17 10
12 Package 1 day 11
13 Send Reports 1 day Thu 1/06/17 Thu 1/06/17 12
14 Send Eccentric 3 days Thu 1/06/17 Mon 5/06/17 12

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: Project1 Split External Tasks Inactive Summary Manual Summary Progress
Date: Tue 4/04/17 Milestone External Milestone Manual Task Start­only
Summary Inactive Task Duration­only Finish­only

Page 1
24 Apr '17 1 May '17 8 May '17 15 May '17 22 May '17 29 May '17 5 Jun '17
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: Project1 Split External Tasks Inactive Summary Manual Summary Progress
Date: Tue 4/04/17 Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 2

You might also like