ID Task Name Duration Start Finish Predecessors Total Slack Free Slack December 2016

29 02 05 08 11 14 17 20 23
1 PROYEK X 78 days Mon 05/12/16 Tue 07/03/17 0 days 0 days
2 A 18 days Mon 05/12/16 Mon 26/12/16 0 days 0 days
3 B 20 days Tue 27/12/16 Wed 18/01/17 2 0 days 0 days
4 C 22 days Wed 21/12/16 Sat 14/01/17 2FS-5 days 8 days 5 days C
5 D 16 days Thu 19/01/17 Tue 07/02/17 3;4FS-9 days 0 days 0 days
6 E 17 days Sat 17/12/16 Thu 05/01/17 2FS-8 days 3 days 0 days E
7 F 16 days Wed 28/12/16 Sat 14/01/17 6FS-8 days 3 days 0 days
8 G 20 days Tue 31/01/17 Wed 22/02/17 5FS-7 days;7FS+8 days 0 days 0 days
9 H 24 days Mon 16/01/17 Mon 13/02/17 4FS-5 days;7 3 days 3 days
10 I 21 days Sat 11/02/17 Tue 07/03/17 8FS-10 days;9FS-5 days 0 days 0 days

Task Rolled Up Task External Tasks


Critical Task Rolled Up Critical Task Project Summary
Project: Tugas No.A.mpp
Progress Rolled Up Milestone Group By Summary
Date: Thu 08/12/16
Milestone Rolled Up Progress Deadline
Summary Split

Page 1
January 2017 February 2017 March 2017
26 29 01 04 07 10 13 16 19 22 25 28 31 03 06 09 12 15 18 21 24 27 02 05 08

Task Rolled Up Task External Tasks


Critical Task Rolled Up Critical Task Project Summary
Project: Tugas No.A.mpp
Progress Rolled Up Milestone Group By Summary
Date: Thu 08/12/16
Milestone Rolled Up Progress Deadline
Summary Split