Madurai, RR
Name of the Execution Division

Madurai, C&M
Name of Q.C division:

6
6
No.of Works inspected at site

No of CMP / Ready mix site

5
5
inspected
Madurai

15
15
Gradation

6
6
Binder content
-

40
40

Thickness, Width
-

9
9

Density
-

6
6

Temperature
-

Viscosity
No of tests conducted

Compressive strength /
-

Rebound hammer test/ Slump


-

76
76

Total
-

12
12

Gradation
-

6
6

Binder content
ABSTRACT
AGENDA No.2

40
40

Thickness, Width
-

8
8

Density
-

6
6

Temperature
-

Viscosity
No. of test satisfied

Compressive strength /
-

Rebound hammer test


-

72
72

Total
-

3
3

Gradation
-

Binder content
INSPECTION REPORT OF ADE(H) QC Madurai FOR THE MONTH OF JUNE - 2017.

Thickness
-

1
1

Density
-

Temperature
-

0
0

Viscosity
No.of test Not satisfied

Compressive strength /
-

0
0

Rebound hammer test


-

4
4

Total
--
Remarks

then Rectified
4 Not satisfied
FORM-1

FOR NON BITUMINOUS / BITUMINOUS WORKS (FIELD INSPECTION REPORT OFADE) FOR THE MONTH OF JUNE- 2017.

Name of Q.C division: Madurai

value Remarks
Name of Exe.Dn Item of work with
S Date of As per
Exe.sub. Name of work Test location Name of As per test Satisfied / Not
No inspection Estimate /
dn Test (*) at site satisfied
JMF
NAME OF THE QC SUB DIVISION:MADURAI

BM

Km 1/ 330 Thickness 50 mm 51 mm Satisfied


R/S 1.20m from
edge Width 3.75 m 3.75 m Satisfied

17.06.2017 Field Density > 100 % 100.30% Satisfied

BM
Km. 0/080
R/S 0.80m from Thickness 50 mm 50 mm Satisfied
edge
Strengthening to Muruganeri road Width 3.75m 3.76m Satisfied
Madurai C&M/
1 brg.from Km.3/0 of Subbulapuram-
Peraiyur C&M BC
Sengulam road Km 0/0-1/6
Km 1/ 330 Thickness 30 mm 32 mm Satisfied
R/S 1.20m from
edge Width 3.75 m 3.75 m Satisfied
18.06.2017 Field Density > 100 % 100.20% Satisfied

BC
Km. 0/080
R/S 0.80m from Thickness 30 mm 31 mm Satisfied
edge
Width 3.75m 3.80m Satisfied
FORM-1

FOR NON BITUMINOUS / BITUMINOUS WORKS (FIELD INSPECTION REPORT OFADE) FOR THE MONTH OF JUNE- 2017.

Name of Q.C division: Madurai

value Remarks
Name of Exe.Dn Item of work with
S Date of As per
Exe.sub. Name of work Test location Name of As per test Satisfied / Not
No inspection Estimate /
dn Test (*) at site satisfied
JMF
BM
Km. 2/303
R/S 0.80m from Thickness 50 mm 51 mm Satisfied
edge
Width 3.75 m 3.78 m Satisfied
19.06.2017
BM
Km. 1/412
L/S 0.80m from Thickness 50 mm 52 mm Satisfied
edge
Madurai C&M/ Strengthening to Keeranoor road Width 3.75m 3.75m Satisfied
2
Melur C&M Km 0/0-2/4 BC
Km. 2/303
R/S 0.80m from Thickness 30 mm 32 mm Satisfied
edge
Width 3.75 m 3.78 m Satisfied
21.06.2017
BC
Km. 1/412
L/S 0.80m from Thickness 30 mm 31 mm Satisfied
edge
Width 3.75m 3.75m Satisfied
FORM-1

FOR NON BITUMINOUS / BITUMINOUS WORKS (FIELD INSPECTION REPORT OFADE) FOR THE MONTH OF JUNE- 2017.

Name of Q.C division: Madurai

value Remarks
Name of Exe.Dn Item of work with
S Date of As per
Exe.sub. Name of work Test location Name of As per test Satisfied / Not
No inspection Estimate /
dn Test (*) at site satisfied
JMF
BM
Km 2/030
Thickness 50 mm 51 mm Satisfied
R/S 1m from edge
Width 3.75 m 3.75 m Satisfied

BM
Km. 1/ 876.50
15.06.2017 R/S 0.90m from Thickness 50 mm 51 mm Satisfied
edge
Width 3.75m 3.75m Satisfied

BM
Km 0/ 732.50
L/S 0.9m from Thickness 50 mm 50 mm Satisfied
edge
Madurai C&M/ Strengthening of Buskkaranpatti- Width 3.75m 3.75m Satisfied
3
Usilampatti C&M Kakkiveeranpatti road km 0/0-4/2 BC
Km 2/030
Thickness 30 mm 30 mm Satisfied
R/S 1m from edge
Width 3.75m 3.75m Satisfied

BC
Km. 1/ 876.50
26.06.2017 R/S 0.90m from Thickness 30 mm 30 mm Satisfied
edge
Width 3.75m 3.75m Satisfied

BC
Km 0/ 732.50
L/S 0.9m from Thickness 30 mm 32 mm Satisfied
edge
Width 3.75m 3.75m Satisfied
FORM-1

FOR NON BITUMINOUS / BITUMINOUS WORKS (FIELD INSPECTION REPORT OFADE) FOR THE MONTH OF JUNE- 2017.

Name of Q.C division: Madurai

value Remarks
Name of Exe.Dn Item of work with
S Date of As per
Exe.sub. Name of work Test location Name of As per test Satisfied / Not
No inspection Estimate /
dn Test (*) at site satisfied
JMF
WMM

Thickness 100mm 102mm Satisfied


Madurai C&M/ Strengthening to NH 7 km 34/10 of
Km 0/360 L/S Width 3.75m 3.75m Satisfied
4 18.06.2017 Thirumangalam Mythanpatti Road at km. 0/0 - 1/0
0.9m from edge
C&M (O4174) Not Satisfied and
Field Density > 100 % 97.60%
then rectified
Not Satisfied and
Gradation - -
then rectified
WMM

Thickness 250 mm 250 mm Satisfied


Km 0/098 R/S
Width 3.75m 3.75m Satisfied
1.00m from edge
Field Density > 100 % 100.20% Satisfied
Strengthening to Thirumangalam -
Madurai C&M/ Pallapatti road 13/0 of Gradation - - Satisfied
5 25.06.2017 Thirumangalam Kangeyanatham Road at km. 0/0 -
C&M 1/300 Including Providing Paver WMM
block at km. 1/3 - 1/6 (O1982)
Thickness 250 mm 260 mm Satisfied
Km 1/ 412 R/S
Width 3.75m 3.75m Satisfied
0.70 m from edge
Field Density > 100 % 100.30% Satisfied

Gradation - - Satisfied
FORM-1

FOR NON BITUMINOUS / BITUMINOUS WORKS (FIELD INSPECTION REPORT OFADE) FOR THE MONTH OF JUNE- 2017.

Name of Q.C division: Madurai

value Remarks
Name of Exe.Dn Item of work with
S Date of As per
Exe.sub. Name of work Test location Name of As per test Satisfied / Not
No inspection Estimate /
dn Test (*) at site satisfied
JMF

WMM

Thickness 100 mm 102 mm Satisfied


Km 2/210 R/S
Width 3.75m 3.75m Satisfied
0.70 m from edge
Field Density > 100 % 100.20% Satisfied

27.06.2017 Gradation - - Satisfied

WMM

Thickness 100 mm 103 mm Satisfied


Km 1/370 R/S
0.90m from edge
Field Density > 100 % 100.30% Satisfied

Madurai C&M/ Strengthening to Veeraperumal Gradation - - Satisfied


S (FIELD INSPECTION REPORT OFADE) FOR THE MONTH
Thirumangalam puram - OF JUNE- 2017.
Krishnapuram road km 0/0
C&M - 3/6 (Using Plastic Waste) WMM

Thickness 100 mm 102 mm Satisfied


Km 0/716 R/S
0.80m from edge
Field Density > 100 % 100.20% Satisfied

Gradation - - Satisfied

WMM

Thickness 100 mm 103 mm Satisfied


Km 0/420 R/S
Width 3.75m 3.75m Satisfied
0.90m from edge
Field Density > 100 % 100.40% Satisfied
FORM-1

FOR NON BITUMINOUS / BITUMINOUS WORKS (FIELD INSPECTION REPORT OFADE) FOR THE MONTH OF JUNE- 2017.

Name of Q.C division: Madurai

value Remarks
Name of Exe.Dn Km 0/420 R/S Item of work with
S Date of As per
Exe.sub. Name of work Test from
0.90m location
edge Name of As per test Satisfied / Not
No inspection Estimate /
dn Test (*) at site satisfied
JMF

Gradation - - Satisfied
FORM-2
FOR NON BITUMINOUS / BITUMINOUS WORKS (FIELD INSPECTION REPORT OF ADE) FOR THE MONTH OF JUNE- 2017.

Name of Item of work value Remarks


S Date of Exe.Dn with
Name of work Test location As per As per test Satisfied / Not
No inspection Exe.sub. Name of Test
dn (*) Estimate /JMF at site satisfied

NAME OF THE QC SUB DIVISION:MADURAI


BM

15.06.2017 Not Satisfied and


Gradation - -
then Rectified

Strengthening to Muruganeri road brg.from 9/2 of BM


Madurai C&M/
1 Km.3/0 of Subbulapuram-Sengulam road Km Thirumangalam Binder content 5.38+0.3% 5.17% Satisfied
Peraiyur C&M
17.06.2017 0/0-1/6 -Pallapatty road
150 C - 170 C
o o
Temperature 147 o C Satisfied
± 10 oC
BC
18.06.2017
Gradation - - Satisfied
BM
Gradation - - Satisfied
16.06.2017 Madurai Binder content 5.341+0.3% 5.20% Satisfied
2 C&M / Melur Strengthening to Keeranoor at Km 0/0-2/4 Melakottai 150oC - 170 o C
C&M Temperature 155 °c Satisfied
± 10 oC
BC
21.06.2017
Gradation - - Satisfied
DBM
Gradation - - Satisfied
Madurai 10/0 of
Strengthening to Madurai-Natham road Km
3 20.06.2017 C&M /Madurai Thirumangalam - Binder content 4.47+0.3% 4.32% Satisfied
0/0-1/0 (SH 72) .
C&M Pallapatty Road
150 C - 170 C
o o
Temperature 150 °c Satisfied
± 10 oC
BC

Not Satisfied and


Gradation - -
Madurai 10/0 of then Rectified
Strengthening to Madurai-Natham road Km
4 27.06.2017 C&M /Madurai Thirumangalam -
1/0-2/2 (SH 72)
C&M Pallapatty Road Binder content 5.38+0.3% 5.23% Satisfied
150 C - 170 C ±
o o
Temperature 144 0C Satisfied
10 oC
BM
Gradation
16.06.2017 Binder content 5.38+0.3% Satisfied
Madurai C&M/ 21/4 of 150oC - 170 o C
Strengthening of Buskkaranpatti- Temperature 145 C o
Satisfied
5 Usilampatti Thirumangalam - ± 10 oC
Kakkiveeranpatti road km 0/0-4/2
C&M Usilampatti road BC
Gradation - - Satisfied
26.06.2017 Binder content 5.38+0.3% Satisfied
150oC - 170oC ±
Temperature 148 o C Satisfied
10 oC
FORM-3
FOR CONCRETE WORKS (FIELD INSPECTION REPORT OF ADE) FOR THE MONTH OF JUNE- 2017.
Name of Q.C division: Madurai
Item of value Remarks
Name of
S Date of work with
Exe.Dn Name of work Name of Test (*) As per Codal As per test Satisfied / Not
No inspection Grade of
Exe.sub.dn Provision at site satisfied
concrete
NAME OF QC SUB DIVISION : Madurai
-- NIL --
FORM-4

FOR CONCRETE WORKS (AT READY MIX PLANT SITE ) FOR THE MONTH OF JUNE- 2017.

Name of Q.C division: Madurai

value Remarks
Ready Mix
Date of Name of Exe.Dn Grade of Name of Test
S No Name of work Plant As per As per test at
inspection Exe.sub.dn Concrete (*) Satisfied / Not
location codal Ready Mix
satisfied
Provision Plant site

Name of Q.C Subdivision: Madurai

- NIL -

Name of Q.C Subdivision: Dindigul (DINDIGUL (H) C&M)

- NIL -

Name of Q.C Subdivision: Dindigul (PALANI (H) C&M)

- NIL -

Name of Q.C Subdivision: Theni

- NIL -

Name of Q.C Subdivision: Sivagangai

- NIL -

Name of Q.C Subdivision: Ramanathapuram

- NIL -
ABSTRACT
INSPECTION REPORT FOR THE MONTH OF June 2015
Name of Q.C division: Madurai

Ready mix site


inspected at
No of tests conducted No. of test satisfied No.of test Not satisfied
Name of the

No of CMP /
Execution

No.of Works

inspected
Division

Gradation

Gradation

Gradation
Thickness

Thickness

Thickness
site
Remarks

Density

Density

Density
content

content

content
Binder

Binder

Binder
No

Madurai 2 Not satisfied


1 4 1 1 2 14 9 0 2 14 8 1 0 0 1
C &M then rectified-

Madurai RR

Dindigul C & 1 Not satisfied


2 5 2 4 2 8 3 3 2 8 3 1
M then rectified-

Dindigul RR

Theni 3 Not satisfied


3 C&M 3 2 4 2 1 1 1 2 1 1 3 then rectified-

Theni RR

4 Sivagangai 1 1 1 1 1 1 1
C&M
Paramakudi 1 Not satisfied
RR
1 1 1 then rectified-
Ramnad 1 Not satisfied
5 3 1 4 1 0 1 4 0 0 0 0 1 then rectified-
C& M

Total 17 5 10 8 28 15 4 8 28 13 6 0 0 2
ABSTRACT
DETAILS OF TESTS CONDUCTED BY THE ASSISTANT DIVISIONAL ENGINEER (QUALITY CONTROL) AS ON 30.06.2017
NAME OF QC DIVISION: MADURAI (H) QC CIRCLE : MADURAI (H) C&M
NO OF WORKS TOTAL NO OF TESTS NO OF TESTS NOT

RECTIFIED UPTO THIS Month


CHECKED CHECKED SATISFIED

TOTAL ( UPTO JUNE-2017)


UPTO PREVIOUS MONTH

UPTO PREVIOUS MONTH

UPTO PREVIOUS MONTH

DURING THE MONTH OF


DURING THE MONTH OF

DURING THE MONTH OF

NOT RECTIFIED
NO OF
SL.

JUNE-2017)
JUNE 2017

JUNE 2017
NAME OF DIVISIONS TESTS REMARKS
NO

TOTAL

TOTAL
SATISFIED

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
A CONSTRUCTION & MAINTENANCE DIVISION
1 Madurai 11 6 17 94 76 170 162 4 4 8 8 -
2 Dindigul

3 Palani

4 Theni

5 Sivagangai

6 Ramnad
B MADURAI (H) NABARD & RURAL ROADS DIVISION
1 Madurai -

2 Paramakudi -

TOTAL 11 6 17 94 76 170 162 4 4 8 8 -

Divisional Engineer (H)


Quality Control Division
Madurai