Professional Documents
Culture Documents
CONTENTS
1 Scope
2 Reference
3 Method
4 Tolerance
5 Documentation
(5b) Formats
00 18/08/2011
Page 1 of 5
LARSEN & TOUBRO LIMITED
ENGINEERING, CONSTRUCTION AND CONTRACTS
PROJECT QUALITY PLAN
SITE: SAMAKHIALI GANDHIDHAM ROAD PROJET
FROM 306.800 TO 362.420
QUALITY MANAGEMENT
(5b) Formats
MANPOWER REQUIRED:
1. Site Engineer
2. Supervisor
3. Operators
4. Workmen
EQUIPMENT REQUIRED:
Gantry 2 nos .each of 40 MT capacity, mould vibrators, needle vibrator, welding set,
gas cutting set, air compressor, prestressing jack/ pump, grouting pump/ agitator
etc., abrasive cutter, boom placer/ static concrete pump/ crane with concrete
bucket.
SCOPE OF WORK:
Page 2 of 5
1. Preparation of casting yard 25 m wide and 480 m long including rail track
for 2 nos. of 40 MT Gantry.
2. Yard will have two nos. of 40 MT capacity Gantry for shifting of PSC
girder from casting bed to stack yard and stack yard to dispatch.
3. Number of casting beds: 8 nos. for 26.5m girder and 8 nos. for 30.0 m
girder.
4. Reinforcement cage binding beds 16 nos. parallel to casting beds.
BED PREPARATION:
1. Between two Gantry tracks, area to be leveled and compacted.
3. Over GSB 100 mm thick PCC M-15 Grade with proper level ( PCC will be
done for casting area approx.. 250m length, stacking area will have a
compacted and leveled GSB layer )
CASTING BED:
2. Place the Pre-cast sleeper and level it properly, check and ensure its
proper level and line.
3. Fix bottom shutter over the B/B channel with 12 mm dia. bolt with nut.
4. Check the line and level once again, and then grout the Pre-cast
sleeper bottom for uniform contact.
5. Fix side shutter panels from center line of girder towards both ends.
Provide Sponge in between bottom shutter and side panel, and all the
joints of Side panels to prevent leakage of concrete slurry.
8. Lift Pre-fabricated cage by using lifting tackle and gantry and place it on
the casting bed in required position.
9. Support the cage with the vertical form work and detach the strong
back from Rebar cage.
Page 3 of 5
10. Place the metallic (GI coated) sheathing pipe inside the cage as per
approved cable profiling drawings. Sheathing pipe shall be joined by
using coupler in such a way that there will be an equal lap on either side
of joint. The joints of sheathing pipe should be wrapped well by insulation
tapes so as to prevent slurry entry while concreting.
11. Fix end block shutter on both sides fitted with tube unit.
12. Connect the sheathing to tube units and seal all joints of sheathing by
insulated tape properly.
14. Fix the second side shutter from centerline of the girder and proceed
both directions, provide tie rods in sleeves with PVC pipe.
15. Fix alignment angels/ tie rod at top and props/ turn buckles on both
sides. Align the shutter to required line / shape and plumb using props
and tie rods.
19. Arrange vibrator, needle, mould vibrator and high frequency vibrator.
20. Check all the equipments before starting the concrete from batching
plant.
21. Insert the dummy cable/ PVC duct within the sheathing pipe before
concreting and move it freely in the sheathing pipe while concreting by
moving it forward and backward from ends to prevent any type of
blockage.
22. Start pouring as per pour sequence attached with the pour card /
method statement.
25. Prepare construction joint after one hour from finishing of concrete
(roughen the concrete surface by wire brush or by some other mode.)
Page 4 of 5
26. Sprinkle water immediately after initial set.
27. Cover the concrete surface by wet Hessian cloth and start water
curing.
29. Cover the concrete immediately after de-moulding with Hessian cloth
and cure the concrete continuously for 14 days.
SAFETY PROCEDURE:
1. Proper PPEs viz, Safety shoes, Safety jackets etc. shall be used.
Page 5 of 5