Kitsilano Neighborhood House Redevelopment Preliminary Construction Schedule

ID
1

Task Name
Tender Period

2
3

Februar March
Finish
Thu 28/03/13

Duration
20 days

Start
Fri 01/03/13

Bid Book/Contract Approval

10 days

Tue 02/04/13

Mon 15/04/13

Award Contract

14 days

Tue 16/04/13

Fri 03/05/13

Mobilization

10 days

Mon 06/05/13

Fri 17/05/13

Lift/Move Hay House

5 days

Mon 13/05/13

Fri 17/05/13

Excavation/Shotcrete

20 days

Mon 20/05/13

Fri 14/06/13

Site Services

30 days

Mon 27/05/13

Fri 05/07/13

Install Crane

5 days

Mon 10/06/13

Fri 14/06/13

Concrete

60 days

Mon 17/06/13

Fri 06/09/13

10

U/Slab R-in

15 days

Mon 10/06/13

Fri 28/06/13

11

Set Hay House

5 days

Mon 08/07/13

Fri 12/07/13

12

Framing

80 days

Mon 26/08/13

Fri 13/12/13

13

Masonry

20 days

Mon 07/10/13

Fri 01/11/13

14

Steel & Decking

15 days

Mon 21/10/13

Fri 08/11/13

15

Roofing

25 days

Mon 18/11/13

Fri 20/12/13

16

Elevator/Lift

100 days

Mon 09/12/13

Fri 25/04/14

17

Windows/Entrance

20 days

Mon 11/11/13

Fri 06/12/13

18

Envelope

60 days

Mon 25/11/13

Fri 14/02/14

19

Mech/Electrical R-in

85 days

Mon 07/10/13

Fri 31/01/14

20

Hard Landscaping

50 days

Mon 20/01/14

Fri 28/03/14

21

Concrete Topping

10 days

Mon 09/12/13

Fri 20/12/13

22

Insulation/Drywall/Tbar

50 days

Mon 16/12/13

Fri 21/02/14

23

Restoration Existing

40 days

Mon 24/02/14

Fri 18/04/14

24

Painting

87 days

Mon 27/01/14

Tue 27/05/14

25

Flooring

30 days

Mon 17/02/14

Fri 28/03/14

26

Door and Hardware

30 days

Mon 24/02/14

Fri 04/04/14

27

Millwork/Trim

30 days

Mon 03/03/14

Fri 11/04/14

28

Lanscaping/Play Equipment

40 days

Mon 14/04/14

Fri 06/06/14

29

Metal Railings

10 days

Mon 14/04/14

Fri 25/04/14

30

Specialties

20 days

Mon 31/03/14

Fri 25/04/14

31

Window Coverings

5 days

Mon 12/05/14

Fri 16/05/14

32

Appliances

10 days

Mon 28/04/14

Fri 09/05/14

33

Systems Finishing

85 days

Mon 03/02/14

Fri 30/05/14

34

Building Flush Out and Commissioning

30 days

Mon 02/06/14

Fri 11/07/14

35

Inspections

10 days

Mon 14/07/14

Fri 25/07/14

36

Occupancy

0 days

Fri 25/07/14

Fri 25/07/14

Thu 09/05/13

April

May

June

TENDER

July

August

Septem October Novemb Decemb January Februar March

April

May

June

July