A.

PEKERJAAN LANTAI 1

Pekerjaan Persiapan

Start: Thu 1/2/14 ID: 1

Start: Thu 1/2/14 ID: 2

Finish: Mon 6/23/14Dur: 165 days

Finish: Mon 1/6/14Dur: 5 days

Comp: 0%

Comp: 0%

Pekerjaan Tanah
Start: Tue 1/7/14 ID: 5
Finish: Sun 2/16/14Dur: 39 days
Comp: 0%

Pekerjaan Pondasi
Start: Sat 1/25/14 ID: 9
Finish: Mon 2/10/14Dur: 16 days
Comp: 0%

Pekerjaaan Beton
Start: Sat 1/25/14 ID: 12
Finish: Sat 4/5/14 Dur: 69 days
Comp: 0%

Page 1

Page 2

Page 3

Page 4

Page 5

Page 6

Page 7

Page 8

Pekerjaaan Dinding
Start: Sat 1/25/14 ID: 95
Finish: Sat 4/12/14 Dur: 76 days
Comp: 0%

Page 9

Page 10

Pekerjaaan Lantai
Start: Mon 5/12/14ID: 109
Finish: Mon 6/23/14Dur: 40 days
Comp: 0%

Pekerjaaan Kusen Pintu & Jendela


Start: Thu 2/20/14 ID: 122
Finish: Thu 2/27/14Dur: 8 days
Comp: 0%

Page 11

Page 12

Page 13

Pekerjaaan Atap & Plafond


Start: Mon 3/3/14 ID: 138
Finish: Sun 5/11/14Dur: 67 days
Comp: 0%

Pekerjaaan Pengecatan
Start: Sun 4/13/14 ID: 149
Finish: Sun 5/18/14Dur: 33 days
Comp: 0%

Pekerjaaan Sanitasi Air


Start: Wed 2/12/14ID: 156
Finish: Sun 4/13/14Dur: 60 days
Comp: 0%

Page 14

Page 15

Pekerjaaan Instalasi Listrik


Start: Mon 2/24/14ID: 170
Finish: Wed 5/7/14Dur: 70 days
Comp: 0%

Page 16

B. PEKERJAAN LANTAI 2

Pekerjaaan Beton

Start: Sun 3/30/14 ID: 180

Start: Wed 4/16/14ID: 181

Finish: Fri 7/11/14 Dur: 98 days

Finish: Sat 5/10/14 Dur: 23 days

Comp: 0%

Comp: 0%

Page 17

Page 18

Page 19

Pekerjaaan Dinding
Start: Mon 4/14/14ID: 214
Finish: Mon 6/9/14Dur: 52 days
Comp: 0%

Page 20

Pekerjaaan Lantai
Start: Wed 6/25/14ID: 222
Finish: Fri 7/4/14

Dur: 10 days

Comp: 0%

Pekerjaaan Kusen Pintu & Jendela


Start: Sun 4/20/14 ID: 227
Finish: Wed 4/30/14Dur: 11 days
Comp: 0%

Page 21

Page 22

Page 23

Pekerjaaan Atap & Plafond


Start: Tue 5/6/14 ID: 243
Finish: Tue 6/24/14Dur: 47 days
Comp: 0%

Pekerjaaan Pengecatan
Start: Fri 6/13/14 ID: 254
Finish: Sat 6/28/14 Dur: 16 days
Comp: 0%

Page 24

Pekerjaaan Sanitasi Air


Start: Sun 3/30/14 ID: 260
Finish: Tue 6/10/14Dur: 67 days
Comp: 0%

Page 25

Pekerjaaan Instalasi Listrik


Start: Tue 4/22/14 ID: 272
Finish: Sat 6/21/14 Dur: 57 days
Comp: 0%

Page 26

Pekerjaaan pekerjaan alumunium & besi


Start: Sat 7/5/14 ID: 283
Finish: Sun 7/6/14 Dur: 2 days
Comp: 0%

Page 27

Pekerjaaan Lain-lain
Start: Sun 7/6/14 ID: 285
Finish: Mon 7/7/14Dur: 2 days
Comp: 0%

Pekerjaaan Finishing
Start: Tue 7/8/14 ID: 287
Finish: Fri 7/11/14 Dur: 4 days
Comp: 0%

Page 28

Pembersihan Lahan
Start: Thu 1/2/14 ID: 3
Finish: Sun 1/5/14 Dur: 4 days
Res:

Pemasangan Bowplank
Start: Sun 1/5/14 ID: 4
Finish: Mon 1/6/14 Dur: 2 days
Res:

Page 29

Beton Bertulang Plat Setempat(140/140)


Start: Sat 1/25/14 ID: 14
Finish: Mon 1/27/14Dur: 3 days
Comp: 0%

Beton Bertulang Plat Setempat(120/100)


Start: Sat 1/25/14 ID: 17
Finish: Mon 1/27/14Dur: 3 days
Comp: 0%

Beton Bertulang Plat Setempat(100/100)


Start: Sat 1/25/14 ID: 20
Finish: Mon 1/27/14Dur: 3 days
Comp: 0%

Beton Bertulang Sloof(20/30)


Start: Tue 1/28/14 ID: 23
Finish: Sun 2/9/14 Dur: 12 days
Comp: 0%

Page 30

Beton Bertulang Sloof(20/40)


Start: Tue 2/4/14 ID: 27
Finish: Tue 2/11/14Dur: 8 days
Comp: 0%

Beton Bertulang Kolom(K1)


Start: Wed 2/19/14ID: 31
Finish: Sat 2/22/14 Dur: 4 days
Comp: 0%

Beton Bertulang Kolom(K2)


Start: Wed 2/19/14ID: 35
Finish: Sat 2/22/14 Dur: 4 days
Comp: 0%

Page 31

Beton Bertulang Kolom(K3)


Start: Fri 2/21/14 ID: 39
Finish: Mon 2/24/14Dur: 4 days
Comp: 0%

Beton Bertulang Kolom(K3L)


Start: Fri 2/21/14 ID: 43
Finish: Mon 2/24/14Dur: 4 days
Comp: 0%

Page 32

Beton Bertulang Kolom(K4)


Start: Sun 2/23/14 ID: 47
Finish: Tue 2/25/14Dur: 3 days
Comp: 0%

Beton Bertulang Kolom(K5)


Start: Sun 2/23/14 ID: 51
Finish: Tue 2/25/14Dur: 3 days
Comp: 0%

Beton Bertulang Kolom(K25)


Start: Thu 2/27/14 ID: 55
Finish: Sat 3/1/14 Dur: 3 days
Comp: 0%

Page 33

Beton Bertulang Kolom Praktis(150X150)


Start: Tue 2/25/14 ID: 59
Finish: Sat 3/1/14 Dur: 5 days
Comp: 0%

Beton Bertulang Balok(15/20)


Start: Sat 3/1/14 ID: 63
Finish: Tue 4/1/14 Dur: 31 days
Comp: 0%

Page 34

Beton Bertulang Balok(15/25)


Start: Sat 3/1/14 ID: 67
Finish: Wed 4/2/14Dur: 32 days
Comp: 0%

Beton Bertulang Balok(15/30)


Start: Tue 3/4/14 ID: 71
Finish: Thu 4/3/14 Dur: 30 days
Comp: 0%

Beton Bertulang Balok(20/30)


Start: Tue 3/4/14 ID: 75
Finish: Thu 4/3/14 Dur: 30 days
Comp: 0%

Page 35

Beton Bertulang Balok(20/35)


Start: Sat 3/15/14 ID: 79
Finish: Fri 4/4/14

Dur: 20 days

Comp: 0%

Beton Bertulang Balok(25/40)


Start: Sat 3/15/14 ID: 83
Finish: Fri 4/4/14

Dur: 20 days

Comp: 0%

Page 36

Beton Bertulang Plat Lantai


Start: Mon 3/17/14ID: 87
Finish: Fri 4/4/14

Dur: 18 days

Comp: 0%

Beton Bertulang Tangga


Start: Mon 3/17/14ID: 91
Finish: Sat 4/5/14 Dur: 19 days
Comp: 0%

Page 37

Page 38

Pek.Pas. Keramik Lantai KM/WC 20x20


Start: Mon 5/12/14 ID: 110
Finish: Wed 5/14/14Dur: 3 days
Res:

Pek.Pas. Keramik Lantai Gudang 20x20


Start: Fri 5/16/14 ID: 111
Finish: Fri 5/16/14 Dur: 1 day
Res:

PINTU
Start: Thu 2/20/14 ID: 123
Finish: Thu 2/27/14Dur: 8 days
Comp: 0%

Page 39

Page 40

JENDELA
Start: Thu 2/20/14 ID: 132
Finish: Mon 2/24/14Dur: 5 days
Comp: 0%

Page 41

Pek. Plamir Tembok Luar & Dalam


Start: Sun 4/13/14 ID: 153
Finish: Mon 4/14/14Dur: 2 days
Res:

Pek.Cat Dinding Baru bagian Dalam


Start: Thu 5/8/14 ID: 150
Finish: Sun 5/11/14 Dur: 4 days
Res:

Page 42

Instalasi Air Kotor pipa PVC 3"


Start: Wed 2/12/14 ID: 159
Finish: Wed 2/12/14Dur: 1 day
Res:

Page 43

Page 44

Beton Bertulang Kolom(K3)


Start: Wed 4/16/14ID: 182
Finish: Sun 4/20/14Dur: 4 days
Comp: 0%

Page 45

Beton Bertulang Kolom(K3L)


Start: Sun 4/20/14 ID: 186
Finish: Wed 4/23/14Dur: 4 days
Comp: 0%

Beton Bertulang Kolom(K4)


Start: Wed 4/23/14ID: 190
Finish: Fri 4/25/14 Dur: 3 days
Comp: 0%

Beton Bertulang Kolom(K5)


Start: Fri 4/25/14 ID: 194
Finish: Sun 4/27/14Dur: 3 days
Comp: 0%

Page 46

Beton Bertulang Kolom Praktis(KP)


Start: Sun 4/27/14 ID: 198
Finish: Wed 4/30/14Dur: 4 days
Comp: 0%

Beton Bertulang Ring Balok(15/20)


Start: Tue 5/6/14 ID: 202
Finish: Sat 5/10/14 Dur: 5 days
Comp: 0%

Page 47

Beton Bertulang Dek Conc/Block


Start: Fri 5/9/14

ID: 206

Finish: Sat 5/10/14 Dur: 2 days


Comp: 0%

Beton Bertulang Dek Canopi


Start: Fri 5/9/14

ID: 210

Finish: Sat 5/10/14 Dur: 2 days


Comp: 0%

Page 48

Pek.Pas. Keramik Lantai KM/WC 20x20


Start: Wed 6/25/14 ID: 223
Finish: Sat 6/28/14 Dur: 4 days
Res:

Pek.Pas. Keramik Kamar Pembantu 20x20


Start: Sun 6/29/14 ID: 224
Finish: Mon 6/30/14Dur: 2 days
Res:

PINTU
Start: Sun 4/20/14 ID: 228
Finish: Thu 4/24/14Dur: 5 days
Comp: 0%

Page 49

JENDELA
Start: Mon 4/21/14ID: 233
Finish: Wed 4/30/14Dur: 10 days
Comp: 0%

Page 50

Page 51

Pek. Plamir Tembok Dinding Baru Luar & dalam


Start: Sun 6/22/14 ID: 257
Finish: Sun 6/22/14 Dur: 1 day
Res:

Pek.Cat Dinding Baru


Start: Mon 6/23/14 ID: 255
Finish: Sat 6/28/14 Dur: 6 days
Res:

Page 52

Page 53

Page 54

Page 55

Page 56

Galian Tanah
Start: Tue 1/7/14 ID: 8
Finish: Fri 1/24/14 Dur: 17 days
Res:

Anstampeng
Start: Sat 1/25/14 ID: 10
Finish: Sat 1/25/14 Dur: 1 day
Res:

Lantai Kerja (f'c = 7,4 )


Start: Sat 1/25/14 ID: 13
Finish: Sun 1/26/14 Dur: 2 days
Res:

Page 57

Page 58

Page 59

Page 60

Page 61

Page 62

Page 63

Page 64

Page 65

Rolak
Start: Sat 1/25/14 ID: 107
Finish: Sat 1/25/14 Dur: 1 day
Res:
Page 66

Pek.Pas. Keramik Lantai Dapur 30x30


Start: Sat 5/17/14 ID: 112
Finish: Sun 5/18/14 Dur: 2 days
Res:

Pek.Pas. Keramik Lantai Garasi 30x30


Start: Mon 5/19/14 ID: 113
Finish: Thu 5/22/14 Dur: 4 days
Res:

Page 67

Page 68

Page 69

Pek.Cat Dinding Baru Bagian Luar


Start: Mon 5/12/14 ID: 151
Finish: Mon 5/12/14Dur: 1 day
Res:

Pek. Cat List Plafond


Start: Tue 5/13/14 ID: 152
Finish: Wed 5/14/14Dur: 2 days
Res:

Page 70

Instalasi Air Kotor pipa PVC 4"


Start: Wed 2/12/14 ID: 160
Finish: Wed 2/12/14Dur: 1 day
Res:

Instalasi Air Kotoran Pipa PVC 3"


Start: Wed 2/12/14 ID: 161
Finish: Wed 2/12/14Dur: 1 day
Res:

Page 71

Page 72

Page 73

Page 74

Page 75

Page 76

Pek.Pas. Keramik Lantai Kamar Tidur 30x30


Start: Tue 7/1/14 ID: 225
Finish: Wed 7/2/14 Dur: 2 days
Res:

Pek.Pas. Keramik Lantai Teras 30x30


Start: Thu 7/3/14 ID: 226
Finish: Fri 7/4/14 Dur: 2 days
Res:

Page 77

Page 78

Page 79

Pek. Cat List Plafond


Start: Mon 6/23/14 ID: 256
Finish: Mon 6/23/14Dur: 1 day
Res:

Page 80

Page 81

Page 82

Page 83

Page 84

Ps. Batu Kali (1 PC : 4 PP)


Start: Sun 1/26/14 ID: 11
Finish: Mon 2/10/14Dur: 15 days
Res:

Page 85

Pembesian
Start: Sat 1/25/14 ID: 15
Finish: Sat 1/25/14 Dur: 1 day
Res:

Pengecoran
Start: Mon 1/27/14 ID: 16
Finish: Mon 1/27/14Dur: 1 day
Res:

Pembesian
Start: Sat 1/25/14 ID: 18
Finish: Sat 1/25/14 Dur: 1 day
Res:

Pengecoran
Start: Mon 1/27/14 ID: 19
Finish: Mon 1/27/14Dur: 1 day
Res:

Pembesian
Start: Sat 1/25/14 ID: 21
Finish: Sat 1/25/14 Dur: 1 day
Res:

Pengecoran
Start: Mon 1/27/14 ID: 22
Finish: Mon 1/27/14Dur: 1 day
Res:

Page 86

Page 87

Page 88

Page 89

Page 90

Page 91

Page 92

Page 93

Page 94

Pek.Pas. Keramik Lantai Teras 30x30


Start: Fri 5/23/14 ID: 114
Finish: Sat 5/24/14 Dur: 2 days
Res:

Pek.Pas. Marmer Lantai Kamar Tidur 40x40


Start: Sun 5/25/14 ID: 115
Finish: Tue 6/3/14 Dur: 8 days
Res:

Page 95

Page 96

Page 97

Pek. Cat Plafon


Start: Fri 5/16/14 ID: 155
Finish: Sun 5/18/14 Dur: 3 days
Res:

Page 98

Instalasi Air Kotoran Pipa PVC 4"


Start: Wed 2/12/14 ID: 162
Finish: Wed 2/12/14Dur: 1 day
Res:

Pas. Closet Duduk


Start: Sun 4/13/14 ID: 163
Finish: Sun 4/13/14 Dur: 1 day
Res:

Page 99

Page 100

Page 101

Page 102

Page 103

Page 104

Page 105

Page 106

Page 107

Page 108

Page 109

Page 110

Pek. Pintu Pagar


Start: Sat 7/5/14 ID: 284
Finish: Sun 7/6/14 Dur: 2 days
Res:

Page 111

Page 112

Page 113

Bekesting
Start: Tue 1/28/14 ID: 24
Finish: Sat 2/1/14 Dur: 4 days
Res:

pembesian
Start: Tue 1/28/14 ID: 25
Finish: Mon 2/3/14 Dur: 6 days
Res:

Page 114

Bekesting
Start: Tue 2/4/14 ID: 28
Finish: Sun 2/9/14 Dur: 6 days
Res:

Page 115

Page 116

Page 117

Page 118

Page 119

Page 120

Page 121

Page 122

Pek.Pas. Marmer Lantai R.Keluarga 40x40


Start: Wed 6/4/14 ID: 116
Finish: Mon 6/9/14 Dur: 6 days
Res:

Pek.Pas. Marmer Lantai R.Makan 40x40


Start: Tue 6/10/14 ID: 117
Finish: Wed 6/11/14Dur: 2 days
Res:

Page 123

Page 124

Page 125

Page 126

Pas. BathTube
Start: Sun 4/13/14 ID: 164
Finish: Sun 4/13/14 Dur: 1 day
Res:

Pas. Wastafel
Start: Sun 4/13/14 ID: 165
Finish: Sun 4/13/14 Dur: 1 day
Res:

Page 127

Page 128

Page 129

Page 130

Page 131

Page 132

Page 133

Page 134

Page 135

Page 136

Page 137

Page 138

Page 139

Pek. Pagar
Start: Sun 7/6/14 ID: 286
Finish: Mon 7/7/14 Dur: 2 days
Res:

Page 140

Page 141

pengecoran
Start: Sat 2/8/14 ID: 26
Finish: Sun 2/9/14 Dur: 2 days
Res:

Page 142

pembesian
Start: Tue 2/4/14
Finish: Fri 2/7/14
Res:

ID: 29
Dur: 4 days

pengecoran
Start: Mon 2/10/14 ID: 30
Finish: Tue 2/11/14 Dur: 2 days
Res:

Page 143

Page 144

Page 145

Page 146

Page 147

Page 148

Page 149

Page 150

Pek.Pas. Keramik Dinding meja dapur 30x30


Start: Thu 6/12/14 ID: 118
Finish: Sat 6/14/14 Dur: 3 days
Res:

Pek.Pas. Marmer Lantai R.Tamu 40x41


Start: Sun 6/15/14 ID: 119
Finish: Sun 6/15/14 Dur: 1 day
Res:

Page 151

Page 152

Page 153

Page 154

Pas. Floor Drain


Start: Sun 4/13/14 ID: 167
Finish: Sun 4/13/14 Dur: 1 day
Res:

Pas.Hand Shower Spray


Start: Sun 4/13/14 ID: 166
Finish: Sun 4/13/14 Dur: 1 day
Res:

Page 155

Page 156

Page 157

Page 158

Page 159

Page 160

Page 161

Page 162

Page 163

Page 164

Page 165

Page 166

Page 167

Page 168

Urugan Sirtu (dipadatkan)


Start: Wed 2/12/14 ID: 6
Finish: Thu 2/13/14 Dur: 2 days
Res:

Urugan Pasir
Start: Fri 2/14/14 ID: 7
Finish: Sun 2/16/14 Dur: 3 days
Res:

Page 169

Page 170

Page 171

Page 172

Page 173

Page 174

Page 175

Page 176

Pek. Dinding Batu Bata Trasram 1/2 bata 1:3


Start: Fri 2/14/14 ID: 96
Finish: Sat 2/15/14 Dur: 2 days
Res:

Page 177

Page 178

Pek.Pas. Batu Alam Lantai CarPort


Start: Thu 6/19/14 ID: 120
Finish: Fri 6/20/14 Dur: 2 days
Res:

Pek.Pas. Batu Sikat Lantai CarPort


Start: Sat 6/21/14 ID: 121
Finish: Mon 6/23/14Dur: 3 days
Res:

Page 179

Page 180

Page 181

Page 182

Pas. Mixing Fitting


Start: Sun 4/13/14 ID: 168
Finish: Sun 4/13/14 Dur: 1 day
Res:

Page 183

Page 184

Page 185

Page 186

Page 187

Pek. Dinding Batu Bata Trasram 1/2 bata 1:3


Start: Mon 4/14/14 ID: 215
Finish: Mon 4/14/14Dur: 1 day
Res:

Page 188

Page 189

Page 190

Page 191

Page 192

Page 193

Page 194

Page 195

Page 196

Page 197

Page 198

Bekesting
Start: Wed 2/19/14 ID: 32
Finish: Fri 2/21/14 Dur: 3 days
Res:

Bekesting
Start: Wed 2/19/14 ID: 36
Finish: Fri 2/21/14 Dur: 3 days
Res:

Page 199

Bekesting
Start: Fri 2/21/14 ID: 40
Finish: Sun 2/23/14 Dur: 3 days
Res:

Bekesting
Start: Fri 2/21/14 ID: 44
Finish: Sun 2/23/14 Dur: 3 days
Res:

Page 200

Bekesting
Start: Sun 2/23/14 ID: 48
Finish: Mon 2/24/14Dur: 2 days
Res:

Bekesting
Start: Sun 2/23/14 ID: 52
Finish: Mon 2/24/14Dur: 2 days
Res:

Bekesting
Start: Thu 2/27/14 ID: 56
Finish: Fri 2/28/14 Dur: 2 days
Res:

Page 201

Bekesting
Start: Tue 2/25/14 ID: 60
Finish: Thu 2/27/14 Dur: 3 days
Res:

Bekesting
Start: Sat 3/1/14 ID: 64
Finish: Mon 3/3/14 Dur: 3 days
Res:

Page 202

Bekesting
Start: Sat 3/1/14
Finish: Sat 3/1/14
Res:

ID: 68
Dur: 1 day

Bekesting
Start: Tue 3/4/14 ID: 72
Finish: Thu 3/6/14 Dur: 3 days
Res:

Bekesting
Start: Tue 3/4/14 ID: 76
Finish: Fri 3/14/14 Dur: 11 days
Res:

Page 203

Bekesting
Start: Sat 3/15/14 ID: 80
Finish: Sat 3/15/14 Dur: 1 day
Res:

Bekesting
Start: Sat 3/15/14 ID: 84
Finish: Sun 3/16/14 Dur: 2 days
Res:

Page 204

Bekesting
Start: Mon 3/17/14 ID: 88
Finish: Sun 3/30/14 Dur: 14 days
Res:

Bekesting
Start: Mon 3/17/14 ID: 92
Finish: Tue 3/18/14 Dur: 2 days
Res:

Pek. Dinding Batu Bata Merah 1/2 bata 1:5


Start: Mon 2/17/14 ID: 97
Finish: Sun 3/2/14 Dur: 14 days
Res:

Page 205

Pek.Pemasangan Roster
Start: Mon 2/24/14 ID: 101
Finish: Tue 2/25/14 Dur: 2 days
Res:

Pek.Pas.Batu alam Dinding Depan


Start: Tue 2/25/14 ID: 103
Finish: Tue 2/25/14 Dur: 1 day
Res:

Pek.Pemasangan Ornamen
Start: Tue 2/25/14 ID: 104
Finish: Tue 2/25/14 Dur: 1 day
Res:

Pek. Plesteran Batu bata trasram 1/2 bata


Start: Sun 2/16/14 ID: 98
Finish: Tue 2/18/14 Dur: 3 days
Res:

Page 206

Pek. Pas. Kusen Kamper(P1)


Start: Thu 2/20/14 ID: 124
Finish: Thu 2/20/14 Dur: 1 day
Res:

Pek. Pas. Kusen Kamper(P2)


Start: Sat 2/22/14 ID: 125
Finish: Sat 2/22/14 Dur: 1 day
Res:

Pek. Pas. Kusen Kamper(P3)


Start: Sun 2/23/14 ID: 126
Finish: Sun 2/23/14 Dur: 1 day
Res:

Page 207

Pek. Pas. Kusen Kamper(P4)


Start: Sun 2/23/14 ID: 127
Finish: Sun 2/23/14 Dur: 1 day
Res:

Pek. Pas. Kusen Kamper(P5)


Start: Tue 2/25/14 ID: 128
Finish: Tue 2/25/14 Dur: 1 day
Res:

Pek. Pas. Kusen Kamper(P6)


Start: Wed 2/26/14 ID: 129
Finish: Wed 2/26/14Dur: 1 day
Res:

Pek. Pas. Kusen Kamper(P7)


Start: Wed 2/26/14 ID: 130
Finish: Wed 2/26/14Dur: 1 day
Res:

Pek. Pas. Kusen Kamper(PJ1)


Start: Thu 2/27/14 ID: 131
Finish: Thu 2/27/14 Dur: 1 day
Res:

Page 208

Pek. Pas. Kusen Kamper(J1)


Start: Thu 2/20/14 ID: 133
Finish: Thu 2/20/14 Dur: 1 day
Res:

Pek. Pas. Kusen Kamper(J2)


Start: Sat 2/22/14 ID: 134
Finish: Sat 2/22/14 Dur: 1 day
Res:

Pek. Pas. Kusen Kamper(J3)


Start: Sun 2/23/14 ID: 135
Finish: Sun 2/23/14 Dur: 1 day
Res:

Pek. Pas. Kusen Kamper(J4)


Start: Sun 2/23/14 ID: 136
Finish: Sun 2/23/14 Dur: 1 day
Res:

Pek. Pas. Kusen Kamper(BV1)


Start: Mon 2/24/14 ID: 137
Finish: Mon 2/24/14Dur: 1 day
Res:

Page 209

Pek. Kuda-Kuda 6/15


Start: Mon 3/3/14 ID: 143
Finish: Mon 3/3/14 Dur: 1 day
Res:

Instalasi Air Bersih pipa PVC 1/2"


Start: Mon 2/24/14 ID: 157
Finish: Mon 2/24/14Dur: 1 day
Res:

Page 210

Page 211

Pas. Stop Kontak


Start: Mon 2/24/14 ID: 171
Finish: Mon 2/24/14Dur: 1 day
Res:

Pas. Saklar Tunggal


Start: Mon 2/24/14 ID: 172
Finish: Mon 2/24/14Dur: 1 day
Res:

Pas. Saklar Ganda


Start: Wed 2/26/14 ID: 173
Finish: Wed 2/26/14Dur: 1 day
Res:

Pas. Antena TV Outlet


Start: Wed 2/26/14 ID: 174
Finish: Wed 2/26/14Dur: 1 day
Res:

Pas. Telepon Outlet


Start: Thu 2/27/14 ID: 175
Finish: Thu 2/27/14 Dur: 1 day
Res:

Page 212

Pas. KWH Meter


Start: Fri 2/28/14 ID: 176
Finish: Fri 2/28/14 Dur: 1 day
Res:

Pas. MCB
Start: Fri 2/28/14 ID: 177
Finish: Fri 2/28/14 Dur: 1 day
Res:

Bekesting
Start: Wed 4/16/14 ID: 183
Finish: Sat 4/19/14 Dur: 3 days
Res:

Page 213

Bekesting
Start: Sun 4/20/14 ID: 187
Finish: Tue 4/22/14 Dur: 3 days
Res:

Bekesting
Start: Wed 4/23/14 ID: 191
Finish: Thu 4/24/14 Dur: 2 days
Res:

Bekesting
Start: Fri 4/25/14 ID: 195
Finish: Sat 4/26/14 Dur: 2 days
Res:

Page 214

Bekesting
Start: Sun 4/27/14 ID: 199
Finish: Tue 4/29/14 Dur: 3 days
Res:

Bekesting
Start: Tue 5/6/14 ID: 203
Finish: Thu 5/8/14 Dur: 3 days
Res:

Page 215

Pek. Dinding Batu Bata Merah 1/2 bata 1:5


Start: Tue 4/15/14 ID: 216
Finish: Mon 5/5/14 Dur: 19 days
Res:

Bekesting
Start: Fri 5/9/14
Finish: Fri 5/9/14
Res:

ID: 207
Dur: 1 day

Bekesting
Start: Fri 5/9/14
Finish: Fri 5/9/14
Res:

ID: 211
Dur: 1 day

Pek.Pemasangan Roster
Start: Tue 4/22/14 ID: 219
Finish: Tue 4/22/14 Dur: 1 day
Res:

Page 216

Pek. Pas. Kusen Kamper(P3)


Start: Sun 4/20/14 ID: 229
Finish: Sun 4/20/14 Dur: 1 day
Res:

Pek. Pas. Kusen Kamper(P5)


Start: Mon 4/21/14 ID: 230
Finish: Mon 4/21/14Dur: 1 day
Res:

Pek. Pas. Kusen Kamper(P8)


Start: Wed 4/23/14 ID: 231
Finish: Wed 4/23/14Dur: 1 day
Res:

Page 217

Pek. Pas. Kusen Kamper(Pj2)


Start: Thu 4/24/14 ID: 232
Finish: Thu 4/24/14 Dur: 1 day
Res:

Pek. Pas. Kusen Kamper(J5)


Start: Mon 4/21/14 ID: 234
Finish: Mon 4/21/14Dur: 1 day
Res:

Pek. Pas. Kusen Kamper(J6)


Start: Tue 4/22/14 ID: 235
Finish: Tue 4/22/14 Dur: 1 day
Res:

Pek. Pas. Kusen Kamper(J7)


Start: Tue 4/22/14 ID: 236
Finish: Tue 4/22/14 Dur: 1 day
Res:

Pek. Pas. Kusen Kamper(J8)


Start: Wed 4/23/14 ID: 237
Finish: Wed 4/23/14Dur: 1 day
Res:

Page 218

Pek. Pas. Kusen Kamper(BV2)


Start: Fri 4/25/14 ID: 238
Finish: Fri 4/25/14 Dur: 1 day
Res:

Pek. Pas. Kusen Kamper(BV3)


Start: Fri 4/25/14 ID: 239
Finish: Fri 4/25/14 Dur: 1 day
Res:

Pek. Pas. Kusen Kamper(BV4)


Start: Sat 4/26/14 ID: 240
Finish: Sat 4/26/14 Dur: 1 day
Res:

Pek. Pas. Kusen Kamper(BV5)


Start: Mon 4/28/14 ID: 241
Finish: Mon 4/28/14Dur: 1 day
Res:

Pek. Pas. Kusen Kamper(BV6)


Start: Wed 4/30/14 ID: 242
Finish: Wed 4/30/14Dur: 1 day
Res:

Page 219

Pek. Kuda-Kuda 6/15


Start: Tue 5/6/14 ID: 248
Finish: Thu 5/8/14 Dur: 3 days
Res:

Page 220

Page 221

Pas. Stop Kontak


Start: Tue 4/22/14 ID: 273
Finish: Tue 4/22/14 Dur: 1 day
Res:

Pas. Saklar Tunggal


Start: Tue 4/22/14 ID: 274
Finish: Tue 4/22/14 Dur: 1 day
Res:

Pas. Saklar Ganda


Start: Tue 4/22/14 ID: 275
Finish: Tue 4/22/14 Dur: 1 day
Res:

Pas. Antena TV Outlet


Start: Thu 4/24/14 ID: 276
Finish: Thu 4/24/14 Dur: 1 day
Res:

Page 222

Pas. Telepon Outlet


Start: Thu 4/24/14 ID: 277
Finish: Thu 4/24/14 Dur: 1 day
Res:

Page 223

Page 224

Page 225

Page 226

pembesian
Start: Wed 2/19/14 ID: 33
Finish: Wed 2/19/14Dur: 1 day
Res:

pengecoran
Start: Sat 2/22/14 ID: 34
Finish: Sat 2/22/14 Dur: 1 day
Res:

pembesian
Start: Wed 2/19/14 ID: 37
Finish: Wed 2/19/14Dur: 1 day
Res:

Page 227

pengecoran
Start: Sat 2/22/14 ID: 38
Finish: Sat 2/22/14 Dur: 1 day
Res:

pembesian
Start: Fri 2/21/14 ID: 41
Finish: Sat 2/22/14 Dur: 2 days
Res:

pengecoran
Start: Mon 2/24/14 ID: 42
Finish: Mon 2/24/14Dur: 1 day
Res:

pembesian
Start: Fri 2/21/14 ID: 45
Finish: Sun 2/23/14 Dur: 3 days
Res:

pengecoran
Start: Mon 2/24/14 ID: 46
Finish: Mon 2/24/14Dur: 1 day
Res:

Page 228

pembesian
Start: Sun 2/23/14 ID: 49
Finish: Sun 2/23/14 Dur: 1 day
Res:

pengecoran
Start: Tue 2/25/14 ID: 50
Finish: Tue 2/25/14 Dur: 1 day
Res:

pembesian
Start: Sun 2/23/14 ID: 53
Finish: Sun 2/23/14 Dur: 1 day
Res:

pengecoran
Start: Tue 2/25/14 ID: 54
Finish: Tue 2/25/14 Dur: 1 day
Res:

pembesian
Start: Thu 2/27/14 ID: 57
Finish: Thu 2/27/14 Dur: 1 day
Res:

Page 229

pengecoran
Start: Sat 3/1/14
Finish: Sat 3/1/14
Res:

ID: 58
Dur: 1 day

pengecoran
Start: Sat 3/1/14
Finish: Sat 3/1/14
Res:

ID: 62
Dur: 1 day

pembesian
Start: Tue 2/25/14 ID: 61
Finish: Tue 2/25/14 Dur: 1 day
Res:

pembesian
Start: Sat 3/1/14 ID: 65
Finish: Sun 3/2/14 Dur: 2 days
Res:

Page 230

pembesian
Start: Sat 3/1/14
Finish: Sat 3/1/14
Res:

ID: 69
Dur: 1 day

pembesian
Start: Tue 3/4/14 ID: 73
Finish: Wed 3/5/14 Dur: 2 days
Res:

pembesian
Start: Tue 3/4/14 ID: 77
Finish: Tue 3/11/14 Dur: 8 days
Res:

Page 231

pembesian
Start: Sat 3/15/14 ID: 81
Finish: Sat 3/15/14 Dur: 1 day
Res:

pembesian
Start: Sat 3/15/14 ID: 85
Finish: Sat 3/15/14 Dur: 1 day
Res:

Page 232

pembesian
Start: Mon 3/17/14 ID: 89
Finish: Mon 3/17/14Dur: 1 day
Res:

pengecoran
Start: Tue 4/1/14
Finish: Fri 4/4/14
Res:

ID: 90
Dur: 4 days

pembesian
Start: Mon 3/17/14 ID: 93
Finish: Tue 3/18/14 Dur: 2 days
Res:

Pek. Plesteran Batu bata 1/2 bata


Start: Sun 3/2/14 ID: 99
Finish: Sat 3/29/14 Dur: 28 days
Res:

Page 233

Pek.Pemasangan Kaca Roster


Start: Mon 2/24/14 ID: 102
Finish: Mon 2/24/14Dur: 1 day
Res:

Page 234

Page 235

Page 236

Page 237

Pek. Gording
Start: Tue 3/4/14 ID: 144
Finish: Tue 3/4/14 Dur: 1 day
Res:

Pek. Reng & Usuk


Start: Wed 3/5/14 ID: 145
Finish: Thu 3/6/14 Dur: 2 days
Res:

Instalasi Air Bersih pipa PVC 3/4"


Start: Mon 2/24/14 ID: 158
Finish: Mon 2/24/14Dur: 1 day
Res:

Page 238

Page 239

Page 240

pembesian
Start: Wed 4/16/14 ID: 184
Finish: Wed 4/16/14Dur: 1 day
Res:

pengecoran
Start: Sun 4/20/14 ID: 185
Finish: Sun 4/20/14 Dur: 1 day
Res:

Page 241

pembesian
Start: Sun 4/20/14 ID: 188
Finish: Sun 4/20/14 Dur: 1 day
Res:

pengecoran
Start: Wed 4/23/14 ID: 189
Finish: Wed 4/23/14Dur: 1 day
Res:

pembesian
Start: Wed 4/23/14 ID: 192
Finish: Wed 4/23/14Dur: 1 day
Res:

pengecoran
Start: Fri 4/25/14 ID: 193
Finish: Fri 4/25/14 Dur: 1 day
Res:

pembesian
Start: Fri 4/25/14 ID: 196
Finish: Fri 4/25/14 Dur: 1 day
Res:

Page 242

pengecoran
Start: Sun 4/27/14 ID: 197
Finish: Sun 4/27/14 Dur: 1 day
Res:

pembesian
Start: Sun 4/27/14 ID: 200
Finish: Sun 4/27/14 Dur: 1 day
Res:

pengecoran
Start: Wed 4/30/14 ID: 201
Finish: Wed 4/30/14Dur: 1 day
Res:

pembesian
Start: Tue 5/6/14
Finish: Fri 5/9/14
Res:

ID: 204
Dur: 4 days

pengecoran
Start: Sat 5/10/14 ID: 205
Finish: Sat 5/10/14 Dur: 1 day
Res:

Page 243

pembesian
Start: Fri 5/9/14
Finish: Fri 5/9/14
Res:

ID: 208
Dur: 1 day

pengecoran
Start: Sat 5/10/14 ID: 209
Finish: Sat 5/10/14 Dur: 1 day
Res:

pembesian
Start: Fri 5/9/14
Finish: Fri 5/9/14
Res:

ID: 212
Dur: 1 day

pengecoran
Start: Sat 5/10/14 ID: 213
Finish: Sat 5/10/14 Dur: 1 day
Res:

Pek.Pemasangan Kaca Roster


Start: Tue 4/22/14 ID: 220
Finish: Tue 4/22/14 Dur: 1 day
Res:

Page 244

Pek. Plesteran
Start: Mon 4/21/14 ID: 217
Finish: Wed 6/4/14 Dur: 41 days
Res:

Page 245

Page 246

Page 247

Pek. Gording
Start: Fri 5/9/14
Finish: Fri 5/9/14
Res:

ID: 249
Dur: 1 day

Pek. Reng & Usuk


Start: Sat 5/10/14 ID: 250
Finish: Sun 5/11/14 Dur: 2 days
Res:

Page 248

Page 249

Page 250

Page 251

Page 252

Page 253

Page 254

Page 255

Page 256

Page 257

pengecoran
Start: Tue 4/1/14 ID: 66
Finish: Tue 4/1/14 Dur: 1 day
Res:

Page 258

pengecoran
Start: Wed 4/2/14 ID: 70
Finish: Wed 4/2/14 Dur: 1 day
Res:

pengecoran
Start: Thu 4/3/14 ID: 74
Finish: Thu 4/3/14 Dur: 1 day
Res:

Page 259

pengecoran
Start: Wed 4/2/14 ID: 78
Finish: Thu 4/3/14 Dur: 2 days
Res:

pengecoran
Start: Fri 4/4/14
Finish: Fri 4/4/14
Res:

ID: 82
Dur: 1 day

pengecoran
Start: Fri 4/4/14
Finish: Fri 4/4/14
Res:

ID: 86
Dur: 1 day

Page 260

pengecoran
Start: Sat 4/5/14
Finish: Sat 4/5/14
Res:

ID: 94
Dur: 1 day

Pek.Acian
Start: Sat 3/22/14 ID: 100
Finish: Thu 4/10/14 Dur: 19 days
Res:

Benangan Tali air


Start: Fri 4/11/14 ID: 105
Finish: Sat 4/12/14 Dur: 2 days
Res:

Page 261

Page 262

Pekerjaan Dinding septic tank


Start: Sun 4/6/14 ID: 108
Finish: Fri 4/11/14 Dur: 6 days
Res:

Page 263

Page 264

Page 265

Pek .genteng Keramik Glaz


Start: Fri 3/7/14
ID: 148
Finish: Sun 3/9/14 Dur: 3 days
Res:

Pek Wuwung
Start: Mon 3/10/14 ID: 147
Finish: Tue 3/11/14 Dur: 2 days
Res:

Page 266

Pek. Pas. Sumur Resapan & Bak Kontrol


Start: Sun 4/6/14 ID: 169
Finish: Thu 4/10/14 Dur: 5 days
Res:

Page 267

Page 268

Page 269

Page 270

Page 271

Page 272

Pek.Acian
Start: Mon 5/12/14 ID: 218
Finish: Sun 6/8/14 Dur: 25 days
Res:

Benangan Sudut Biasa


Start: Mon 6/9/14 ID: 221
Finish: Mon 6/9/14 Dur: 1 day
Res:

Page 273

Page 274

Page 275

Pek .genteng Keramik Glaz


Start: Mon 5/12/14 ID: 253
Finish: Wed 5/14/14Dur: 3 days
Res:

Pek Wuwung
Start: Fri 5/16/14 ID: 252
Finish: Fri 5/16/14 Dur: 1 day
Res:

Page 276

Instalasi Air Bersih pipa PVC 1/2"


Start: Sun 3/30/14 ID: 261
Finish: Tue 4/1/14 Dur: 1 day
Res:

Instalasi Air Bersih pipa PVC 3/4"


Start: Sun 3/30/14 ID: 262
Finish: Tue 4/1/14 Dur: 1 day
Res:

Instalasi Air Kotor pipa PVC 3"


Start: Sun 3/30/14 ID: 263
Finish: Tue 4/1/14 Dur: 1 day
Res:

Instalasi Air Kotoran Pipa PVC 3"


Start: Sun 3/30/14 ID: 264
Finish: Tue 4/1/14 Dur: 1 day
Res:

Pas. Closet Duduk


Start: Tue 6/10/14 ID: 265
Finish: Tue 6/10/14 Dur: 1 day
Res:

Page 277

Page 278

Page 279

Page 280

Page 281

Page 282

Page 283

Page 284

Page 285

Page 286

Page 287

Page 288

Page 289

Benangan Sudut Biasa


Start: Sat 4/12/14 ID: 106
Finish: Sat 4/12/14 Dur: 1 day
Res:

Page 290

Page 291

Page 292

Page 293

Pek. Nok
Start: Wed 3/12/14 ID: 146
Finish: Wed 3/12/14Dur: 1 day
Res:

Pek. Rangka Plafond


Start: Sat 4/26/14 ID: 142
Finish: Sat 5/3/14 Dur: 7 days
Res:

Page 294

Page 295

Page 296

Page 297

Page 298

Page 299

Page 300

Page 301

Page 302

Page 303

Pek. Nok
Start: Sat 5/17/14 ID: 251
Finish: Sat 5/17/14 Dur: 1 day
Res:

Page 304

Pas. Closet Jongkok


Start: Tue 6/10/14 ID: 266
Finish: Tue 6/10/14 Dur: 1 day
Res:

Page 305

Pas. Wastafel
Start: Tue 6/10/14 ID: 267
Finish: Tue 6/10/14 Dur: 1 day
Res:

Page 306

Pek. Penangkal Petir


Start: Sat 5/17/14 ID: 282
Finish: Sat 5/17/14 Dur: 1 day
Res:

Page 307

Page 308

Page 309

Page 310

Page 311

Page 312

Page 313

Page 314

Page 315

Page 316

Page 317

Page 318

Page 319

Page 320

Page 321

Pek. Plafond Gypsumboard 9 mm


Start: Mon 4/28/14 ID: 139
Finish: Tue 4/29/14 Dur: 2 days
Res:

Pek. Plafond Triplex 6 mm


Start: Wed 4/30/14 ID: 140
Finish: Sun 5/4/14 Dur: 4 days
Res:

Pek. Cat Rangka Plafon Di Cat Meni


Start: Mon 4/21/14 ID: 154
Finish: Sat 4/26/14 Dur: 5 days
Res:

Page 322

Page 323

Page 324

Page 325

Page 326

Page 327

Page 328

Page 329

Page 330

Page 331

Page 332

Pas. Floor Drain


Start: Tue 6/10/14 ID: 269
Finish: Tue 6/10/14 Dur: 1 day
Res:

Page 333

Pas. Shower
Start: Tue 6/10/14 ID: 268
Finish: Tue 6/10/14 Dur: 1 day
Res:

Page 334

Page 335

Page 336

Page 337

Page 338

Page 339

Page 340

Page 341

Page 342

Page 343

Page 344

Page 345

Page 346

Page 347

Page 348

Page 349

Pek. List Plafond Cornise 5/5 cm


Start: Mon 5/5/14 ID: 141
Finish: Sun 5/11/14 Dur: 7 days
Res:

Page 350

Page 351

Page 352

Pas. Titik Lampu


Start: Sun 5/4/14 ID: 178
Finish: Sun 5/4/14 Dur: 1 day
Res:

Pas. Down Light Lampu Pijar


Start: Mon 5/5/14 ID: 179
Finish: Wed 5/7/14 Dur: 3 days
Res:

Page 353

Page 354

Page 355

Page 356

Page 357

Page 358

Page 359

Pek.Rangka Plafond
Start: Mon 6/16/14 ID: 247
Finish: Thu 6/19/14 Dur: 4 days
Res:

Page 360

Pas. Kran Dinding


Start: Tue 6/10/14 ID: 270
Finish: Tue 6/10/14 Dur: 1 day
Res:

Pas. Bak Mandi


Start: Tue 6/10/14 ID: 271
Finish: Tue 6/10/14 Dur: 1 day
Res:

Page 361

Page 362

Page 363

Page 364

Page 365

Page 366

Page 367

Page 368

Page 369

Page 370

Page 371

Page 372

Page 373

Page 374

Page 375

Page 376

Page 377

Page 378

Page 379

Page 380

Page 381

Page 382

Page 383

Page 384

Page 385

Page 386

Page 387

Pek. Plafond Gypsumboard 9 mm


Start: Tue 6/17/14 ID: 244
Finish: Wed 6/18/14Dur: 2 days
Res:

Pek. Plafond Triplex 6 mm


Start: Thu 6/19/14 ID: 245
Finish: Fri 6/20/14 Dur: 2 days
Res:

Pek. Cat Plafon


Start: Fri 6/20/14 ID: 259
Finish: Sun 6/22/14 Dur: 2 days
Res:

Pek. Cat Rangka Plafon Di Cat Meni


Start: Fri 6/13/14 ID: 258
Finish: Wed 6/18/14Dur: 6 days
Res:

Page 388

Page 389

Page 390

Pas. Lampu Gantung / Chandellier


Start: Wed 6/18/14 ID: 278
Finish: Wed 6/18/14Dur: 1 day
Res:

Page 391

Page 392

Page 393

Page 394

Page 395

Page 396

Page 397

Page 398

Page 399

Page 400

Page 401

Page 402

Page 403

Page 404

Page 405

Page 406

Page 407

Page 408

Page 409

Page 410

Page 411

Page 412

Page 413

Page 414

Page 415

Pek. List Plafond Cornise 5/5 cm


Start: Sat 6/21/14 ID: 246
Finish: Tue 6/24/14 Dur: 4 days
Res:

Page 416

Page 417

Page 418

Pas. Lampu Sorot / Upspot Light


Start: Fri 6/20/14 ID: 279
Finish: Fri 6/20/14 Dur: 1 day
Res:

Pas. Titik Lampu


Start: Fri 6/20/14 ID: 280
Finish: Fri 6/20/14 Dur: 1 day
Res:

Pas. Down Light Lampu Pijar


Start: Sat 6/21/14 ID: 281
Finish: Sat 6/21/14 Dur: 1 day
Res:

Page 419

Page 420

Page 421

Page 422

Page 423

Page 424

Page 425

Page 426

Page 427

Page 428

Page 429

Page 430

Page 431

Page 432

Page 433

Page 434

Page 435

Page 436

Page 437

Page 438

Page 439

Page 440

Page 441

Page 442

Page 443

Page 444

Page 445

Page 446

Page 447

Pek. Pembersihan Lahan


Start: Tue 7/8/14 ID: 288
Finish: Fri 7/11/14 Dur: 4 days
Res:

Page 448

Project: Project Galau


Date: Tue 6/3/14

Critical

Summary

Critical External

Noncritical

Critical Inserted

External

Critical Milestone

Inserted

Project Summary

Milestone

Critical Marked

Highlighted Critical

Critical Summary

Marked

Highlighted Noncritical

Page 449