ID Task

Mode
Task Name Duration Start Finish Predecessors
0
Horizontal Dryer P5 21,43 days Fri 16/05/14 Sun 08/06/14
1 ETA Factory 1 wk Fri 16/05/14 Thu 22/05/14
2 Centering 1 day Fri 23/05/14 Fri 23/05/14 1
3 Pasang modul
horizontal dryer
19 hrs Sat 24/05/14 Sun 25/05/14 2
4 Pasang piping gas dan
angin HD
1 wk Mon
26/05/14
Sun 01/06/14 3
5 Setting bearing dan
leveling bearing roll HD
4 days Mon
26/05/14
Thu 29/05/14 3
6 Setting gear roll HD 33 hrs Fri 30/05/14 Sun 01/06/14 5
7 Pemasangan roll dan
kapas roll HD
3 days Mon
02/06/14
Wed
04/06/14
6
8 Pemasangan cerobong
- cerobong chimney HD
1 day Thu 05/06/14 Thu 05/06/14 7
9 Pemasangan panel HD 1 day Wed
28/05/14
Wed
28/05/14
10 Pemasangan cable duct
berikut support
4 days Mon
26/05/14
Thu 29/05/14 3
11 Cabeling 26 hrs Fri 30/05/14 Sat 31/05/14 10
12 Wiring 35 hrs Sun 01/06/14 Tue 03/06/14 11
Teknisi (SMN)[300%];Sumono
Teknisi (SMN)[500%];Sumono
Teknisi (SMN)[600%];Sumono
Teknisi (SMN)[400%];Sumono
Teknisi (SMN)[300%];Sumono
Teknisi (SMN)[400%];Sumono
Teknisi (SMN)[500%];Sumono
Teknisi (SMSN)[300%];Samson
Teknisi (SMSN)[400%];Samson
Teknisi (SMSN)[400%];Samson
Teknisi (SMSN)[300%];Samson
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M
12 May '14 19 May '14 26 May '14 02 Jun '14 09 Jun '14 16 Jun '14
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 1
Project: Horizontal Dryer P5
Date: Fri 12/09/14
ID Task
Mode
Task Name Duration Start Finish Predecessors
13 Running test 33 hrs Fri 06/06/14 Sun 08/06/14 8
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M
12 May '14 19 May '14 26 May '14 02 Jun '14 09 Jun '14 16 Jun '14
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 2
Project: Horizontal Dryer P5
Date: Fri 12/09/14

You might also like