You are on page 1of 1

ID Task

Mode
Task Name Duration Start Finish % Work Complete
0 Platform dan
Conveyor
69 days Tue 24/06/14 Mon 08/09/14 69%
1 ETA Factory 2 days Tue 24/06/14 Wed 23/07/14 100%
2 Persiapan 21,43 days Thu 26/06/14 Sat 19/07/14 100%
3 Pemasangan support
platform out silo
33 hrs Sun 20/07/14 Tue 22/07/14 0%
4 Pemasangan platform
out silo
82 hrs Tue 22/07/14 Tue 29/07/14 0%
5 Pemasangan support
dan frame conveyor
27,29 days Wed 16/07/14 Sun 24/08/14 100%
6 Pemasangan conveyor 404 hrs Thu 07/08/14 Mon 08/09/14 35%
7 Pemasangan motor
dan rantai, corong
295 hrs Mon 11/08/14 Tue 02/09/14 57%
8 Pemasangan cable
duct conveyor in dan
out silo
1,79 wks Mon 11/08/14 Fri 22/08/14 100%
9 Cabeling dan wiring 11,21 days Tue 19/08/14 Sat 30/08/14 100%
10 Running test 61 hrs Sun 31/08/14 Thu 04/09/14 0%
89%
100%
100%
100%
73%
91%
100%
100%
0%
T F S S M T WT F S S M T WT F S S M T WT F S S M T WT F S S M T WT F S S M T WT F S S M T WT F S S M T WT F S S M T WT F S S M T WT F S S M T WT F S S M T WT F S S M T WT F S S M T WT F S S M T WT F S S M T WT F S S M T WT F
12 May '14 19 May '14 26 May '14 02 Jun '14 09 Jun '14 16 Jun '14 23 Jun '14 30 Jun '14 07 Jul '14 14 Jul '14 21 Jul '14 28 Jul '14 04 Aug '14 11 Aug '14 18 Aug '14 25 Aug '14 01 Sep '14 08 Sep '14
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
Platformdan Conveyor
Page 1

You might also like