ID Task Name Duration %

Complete
Start
1 RAWMILL-1 1ST CHAMBER & LCD PLATES REPLACEMENT
WORK
18 days 38% Sun 22-06-14
2 Mill Inlet chute & mill door removal 1 day 100% Sun 22-06-14
3 Grinding media unloading 1 day 100% Sun 22-06-14
4 Existing shell liners removal and shifting wor 4 days 90% Mon 23-06-14
5 New shell liners installation work 8 days 30% Fri 27-06-14
6 New Rubber plugs fixing work 2 days 0% Thu 03-07-14
7 Existing LCD grate plates & back side plates removal and
shifting work
1.5 days 0% Sat 05-07-14
8 New LCD grate plates & backside plates installation work 1.5 days 0% Sun 06-07-14
9 Grinding media loading in both the chamber 1 day 0% Tue 08-07-14
10 Mill Inlet chute & mill door fixing work 1 day 0% Wed 09-07-14
38%
100%
100%
90%
30%
0%
0%
0%
0%
0%
F S S M T W T F S S M T W T F S S M T W T F
22 J un '14 29 J un '14 06 J ul '14
Task
Split
Progress
Milestone
Summary
Project Summary
External Tasks
External Milestone
Deadline
RAWMILL-1 1ST CHAMBER & LCD PLATES REPLACEMENT WORK
Page 1
Project: COAL FEEDING PROJ ECT
Date: Wed 02-07-14