start

Milestone Date: Fri 29/05/15


ID: 1

preliminaries
Start: Fri 29/05/15 ID: 2
Finish: Thu 4/06/15Dur: 1 wk
Res:

Page 1

External wall
Start: Tue 9/06/15 ID: 3
Finish: Mon 29/06/15
Dur: 3 wks
Res:

Windows
Start: Wed 1/07/15ID: 4
Finish: Tue 14/07/15Dur: 2 wks
Res:

Internal walls
Start: Fri 17/07/15 ID: 5
Finish: Thu 6/08/15Dur: 3 wks
Res:

Doors
Start: Tue 11/08/15ID: 7
Finish: Mon 24/08/15
Dur: 2 wks
Res:

Internal Partitions and Screens


Start: Fri 17/07/15 ID: 6
Finish: Thu 30/07/15
Dur: 2 wks
Res:

Wall finishes
Start: Wed 26/08/15
ID: 8
Finish: Tue 15/09/15Dur: 3 wks
Res:

Page 2

Floor finishes
Start: Wed 16/09/15
ID: 9
Finish: Tue 29/09/15Dur: 2 wks
Res:

Fitments
Start: Thu 22/10/15ID: 11
Finish: Wed 4/11/15Dur: 2 wks
Res:

Electrical
Start: Thu 5/11/15 ID: 13
Finish: Wed 18/11/15
Dur: 2 wks
Res:

Ceiling Finishes
Start: Wed 30/09/15
ID: 10
Finish: Tue 20/10/15Dur: 3 wks
Res:

Plumbing and Drainage


Start: Thu 5/11/15 ID: 12
Finish: Wed 18/11/15
Dur: 2 wks
Res:

Fire Protection
Start: Fri 4/12/15 ID: 14
Finish: Thu 17/12/15
Dur: 2 wks
Res:

Equipment installation
Start: Fri 4/12/15 ID: 15
Finish: Thu 24/12/15
Dur: 3 wks
Res:

Page 3

Finish
Start: Thu 24/12/15ID: 16
Finish: Wed 30/12/15
Dur: 1 wk
Res:

Page 4

Project: Project3.mpp
Date: Thu 14/05/15

Critical

Summary

Critical External

Noncritical

Critical Inserted

External

Critical Milestone

Inserted

Project Summary

Milestone

Critical Marked

Highlighted Critical

Critical Summary

Marked

Highlighted Noncritical