Preliminary G&G study to detect the seismic area Tender for 3D seismic Invitation

Start of Project
Start: Wed 12/20/23ID: 2 Start: Wed 3/13/24ID: 3 Start: Wed 3/13/24 ID: 4
Milestone Date: Wed 12/20/23 Finish: Tue 3/12/24 Dur: 60 days Finish: Wed 5/22/24Dur: 51 days Finish: Thu 3/21/24 Dur: 7 days
ID: 1 Res: Comp: 0% Res:

Permits
Start: Wed 3/13/24 ID: 8
Finish: Tue 7/16/24 Dur: 90 days
Res:

Page 1
Receive offer Technical evaluation Award
Start: Sun 3/24/24 ID: 5 Start: Sun 4/14/24 ID: 6 Start: Sun 5/5/24 ID: 7
Finish: Thu 4/11/24 Dur: 15 days Finish: Thu 5/2/24 Dur: 15 days Finish: Wed 5/22/24 Dur: 14 days
Res: Res: Res:

Seismic acquisition
Start: Wed 7/17/24 ID: 9
Finish: Sun 1/12/25 Dur: 180 days
Res:

Tender for Seismic processing


Start: Wed 7/17/24ID: 10
Finish: Wed 9/25/24Dur: 51 days
Comp: 0%

Page 2
Invitation Receive offer Technical evaluation Award
Start: Wed 7/17/24 ID: 11 Start: Sun 7/28/24 ID: 12 Start: Sun 8/18/24 ID: 13 Start: Sun 9/8/24 ID: 14
Finish: Thu 7/25/24 Dur: 7 days Finish: Thu 8/15/24 Dur: 15 days Finish: Thu 9/5/24 Dur: 15 days Finish: Wed 9/25/24 Dur: 14 days
Res: Res: Res: Res:

Page 3
Seismic processing Seismic interpretation Define prospects Rank prospect
Start: Mon 1/13/25 ID: 15 Start: Mon 9/22/25 ID: 16 Start: Mon 12/15/25ID: 17 Start: Sun 1/4/26 ID: 18
Finish: Sun 9/21/25 Dur: 180 days Finish: Sun 12/14/25 Dur: 60 days Finish: Thu 1/1/26 Dur: 14 days Finish: Wed 1/21/26 Dur: 14 days
Res: Res: Res: Res:

Page 4
Detect the first location to be drilled Approval Permits
End Seismic
Start: Thu 1/22/26 ID: 20 Start: Thu 1/22/26 ID: 21 Start: Wed 2/11/26 ID: 22
Milestone Date: Wed 1/21/26 Finish: Tue 12/1/26 Dur: 224 days Finish: Tue 2/10/26 Dur: 14 days Finish: Tue 6/16/26 Dur: 90 days
ID: 19 Comp: 0% Res: Res:

Page 5
Tendering for rigs and service company Purchasing the materials Drilling well base of design Cost estimate
Start: Wed 6/17/26 ID: 23 Start: Wed 7/29/26 ID: 25 Start: Wed 12/2/26 ID: 26 Start: Wed 1/13/27 ID: 27
Finish: Tue 7/28/26 Dur: 30 days Finish: Tue 12/1/26 Dur: 90 days Finish: Tue 1/12/27 Dur: 30 days Finish: Mon 2/1/27 Dur: 14 days
Res: Res: Res: Res:

Tender for materials


Start: Wed 6/17/26 ID: 24
Finish: Tue 7/28/26 Dur: 30 days
Res:

Page 6
Access road and Well site preparation Rig move Drilling well Drill the 500 ft section
Start: Tue 2/2/27 ID: 28 Start: Sat 4/3/27 ID: 29 Start: Sat 4/17/27 ID: 30 Start: Sat 4/17/27 ID: 31
Finish: Fri 4/2/27 Dur: 60 days Finish: Fri 4/16/27 Dur: 14 days Finish: Tue 6/1/27 Dur: 46 days Finish: Wed 4/21/27 Dur: 5 days
Res: Res: Comp: 0% Res:

Page 7
Run conductor casing Mix the mud for the second section Drill the second section Run surface casing & cement
Start: Thu 4/22/27 ID: 32 Start: Fri 4/23/27 ID: 33 Start: Sat 4/24/27 ID: 34 Start: Sun 5/2/27 ID: 35
Finish: Thu 4/22/27 Dur: 1 day Finish: Fri 4/23/27 Dur: 1 day Finish: Sat 5/1/27 Dur: 8 days Finish: Mon 5/3/27 Dur: 2 days
Res: Res: Res: Res:

Page 8
Rig up the BOP Mix the mud for the third section Drill the third section Run intermediate casing & cementing
Start: Tue 5/4/27 ID: 36 Start: Wed 5/5/27 ID: 37 Start: Thu 5/6/27 ID: 38 Start: Sun 5/16/27 ID: 39
Finish: Tue 5/4/27 Dur: 1 day Finish: Wed 5/5/27 Dur: 1 day Finish: Sat 5/15/27 Dur: 10 days Finish: Thu 5/20/27 Dur: 5 days
Res: Res: Res: Res:

Page 9
Mix the mud for the fourth section Drill the fourth section Run production casing & cementing Run the production liner
Start: Fri 5/21/27 ID: 40 Start: Sat 5/22/27 ID: 41 Start: Thu 5/27/27 ID: 42 Start: Sun 5/30/27 ID: 43
Finish: Fri 5/21/27 Dur: 1 day Finish: Wed 5/26/27 Dur: 5 days Finish: Sat 5/29/27 Dur: 3 days Finish: Sun 5/30/27 Dur: 1 day
Res: Res: Res: Res:

Page 10
Install the SSSV Install packer Perforate the promising interval
End Drilling
Start: Mon 5/31/27 ID: 44 Start: Mon 5/31/27 ID: 45 Start: Tue 6/1/27 ID: 46
Finish: Mon 5/31/27 Dur: 0.5 days Finish: Mon 5/31/27 Dur: 0.5 days Finish: Tue 6/1/27 Dur: 1 day Milestone Date: Tue 6/1/27
Res: Res: Res: ID: 47

Page 11
Test the well Commercial announce
End of Project
Start: Wed 6/2/27 ID: 48 Start: Wed 6/16/27 ID: 49
Finish: Tue 6/15/27 Dur: 14 days Finish: Thu 6/24/27 Dur: 7 days Milestone Date: Thu 6/24/27
Res: Res: ID: 50

Page 12
Critical Milestone Critical Inserted Marked Project Summary
Project: Project managment ga
Noncritical Critical Summary Inserted Critical External Highlighted Critical
Date: Wed 12/20/23
Critical Milestone Summary Critical Marked External Highlighted Noncritical

Page 13