start
Start: Wed 08/07/20ID: 2 Start: Mon 13/07/20ID: 4
Milestone Date: 08/07/20 Finish: Sat 11/07/20 Dur: 4 days Finish: Thu 16/07/20Dur: 4 days
ID: 1 Res: Res:
d
Start: Mon 13/07/20ID: 5
Finish: Fri 17/07/20 Dur: 5 days
Res:
b
Start: Wed 08/07/20ID: 3
Finish: Wed 15/07/20Dur: 6 days
Res:
Start: ID: 10
Finish: Dur:
Res:
Page 1
f
finish
Start: Fri 17/07/20 ID: 7
Finish: Thu 23/07/20Dur: 5 days Milestone Date: 24/07/20
Res: ID: 9
g
Start: Mon 20/07/20ID: 8
Finish: Thu 23/07/20Dur: 4 days
Res:
e
Start: Fri 17/07/20 ID: 6
Finish: Thu 23/07/20Dur: 5 days
Res:
Page 2
Critical Summary Critical External