You are on page 1of 85

Contracts

Supply Lot Sale Agreement


Start: Sun 01/06/08ID: 1
Finish: Sun 01/06/08
Dur: 0 days Milestone Date: Sun 01/06/08
Comp: 0% ID: 2

Supply Construction Agreement

Milestone Date: Sun 01/06/08


ID: 3

Secure Financing

Milestone Date: Sun 01/06/08


ID: 7

Construction Loan Settlement

Milestone Date: Sun 01/06/08


ID: 8
Document Review & Revision
Start: Mon 02/06/08
ID: 9
Finish: Fri 04/07/08Dur: 25 days
Comp: 0%

Bids & Contracts


Start: Mon 07/07/08
ID: 17
Finish: Thu 07/08/08
Dur: 24 days
Comp: 0%
Review Bids
Start: Fri 25/07/08 ID: 22
Finish: Thu 31/07/08
Dur: 5 days
Comp: 0%

Grading & Building Permits


Start: Mon 07/07/08
ID: 26
Finish: Tue 29/07/08
Dur: 17 days
Comp: 0%
Site Work
Start: Wed 23/07/08
ID: 42
Finish: Thu 31/07/08
Dur: 7 days
Comp: 0%
Foundation
Start: Fri 01/08/08 ID: 48
Finish: Wed 03/09/08
Dur: 24 days
Comp: 0%
Supply Contract Plans

Milestone Date: Sun 01/06/08


ID: 4

Supply Contract Specifications

Milestone Date: Sun 01/06/08


ID: 5

Supply Contract Site Plan

Milestone Date: Sun 01/06/08


ID: 6
Review & Finalize Plans
Start: Mon 02/06/08ID: 10
Finish: Fri 20/06/08 Dur: 15 days
Res: Builder

Review & Finalize Specifications


Start: Mon 02/06/08ID: 11
Finish: Fri 27/06/08 Dur: 20 days
Res: Builder
Review & Finalize Site Plan
Start: Mon 23/06/08ID: 12
Finish: Mon 23/06/08Dur: 1 day
Res: Builder

Print Construction Drawings


Start: Mon 30/06/08ID: 13
Finish: Fri 04/07/08 Dur: 5 days
Res: Builder
Approve Revised Plans

Milestone Date: Fri 04/07/08


ID: 14

Approve Revised Specifications

Milestone Date: Fri 04/07/08


ID: 15

Approve Revised Site Plan

Milestone Date: Fri 04/07/08


ID: 16

Make Copies of Plans


Start: Mon 07/07/08ID: 18
Finish: Wed 09/07/08Dur: 3 days
Res: Builder
Make Copies of Specifications
Start: Mon 07/07/08ID: 19
Finish: Tue 08/07/08Dur: 2 days
Res: Builder

Schedule lot stake-out Stake lot


Start: Mon 07/07/08ID: 27 Start: Fri 11/07/08 ID: 28
Finish: Mon 07/07/08Dur: 1 day Finish: Fri 11/07/08 Dur: 1 day
Res: Builder Res: Civil Engineer

File Grading Permit Application


Start: Mon 07/07/08ID: 29
Finish: Mon 07/07/08Dur: 1 day
Res: Builder
File Building Permit Application
Start: Mon 07/07/08ID: 30
Finish: Wed 09/07/08Dur: 3 days
Res: Builder
Distribute Plans & Specifications Receive Bids
Start: Thu 10/07/08ID: 20 Start: Fri 11/07/08 ID: 21
Finish: Thu 10/07/08Dur: 1 day Finish: Thu 24/07/08Dur: 10 days
Res: Builder Res: Builder
Post Lot Identification
Start: Mon 14/07/08ID: 31
Finish: Mon 14/07/08Dur: 1 day
Res: Builder
Meet Sediment Control Inspector
Start: Tue 15/07/08 ID: 32
Finish: Tue 15/07/08Dur: 1 day
Res: Builder

County Permit Process


Start: Thu 10/07/08ID: 38
Finish: Wed 23/07/08Dur: 10 days
Res: Department of Permits & Licenses
Sales
Start: Fri 25/07/08 ID: 23
Finish: Thu 31/07/08Dur: 5 days
Res: Builder

Construction
Start: Fri 25/07/08 ID: 24
Finish: Thu 31/07/08Dur: 5 days
Res: Builder

Execute Subcontractor Agreements


Start: Fri 01/08/08 ID: 25
Finish: Thu 07/08/08Dur: 5 days
Res: Builder
Walk Lot w/ Owner
Start: Wed 16/07/08ID: 33
Finish: Wed 16/07/08Dur: 1 day
Res: Builder

Install Construction Entrance


Start: Thu 17/07/08ID: 34
Finish: Thu 17/07/08Dur: 1 day
Res: Excavation Subcontractor

Install Sediment Controls


Start: Thu 17/07/08ID: 35
Finish: Fri 18/07/08 Dur: 2 days
Res: Excavation Subcontractor
Sediment Control Insp. Grading Permit Issued
Start: Mon 21/07/08ID: 36 Start: Tue 22/07/08 ID: 37
Finish: Mon 21/07/08Dur: 1 day Finish: Tue 22/07/08Dur: 1 day
Res: Sediment Control Inspector Res: Sediment Control Inspector
Building Permit Approved Pay Permit Fees and Excise Taxes
Start: Thu 24/07/08ID: 39 Start: Tue 29/07/08 ID: 40
Finish: Thu 24/07/08Dur: 1 day Finish: Tue 29/07/08Dur: 1 day
Res: Department of Permits & Licenses Res: Builder

Clear Lot Strip Topsoil & Stockpile


Start: Wed 23/07/08ID: 43 Start: Mon 28/07/08ID: 44
Finish: Fri 25/07/08 Dur: 3 days Finish: Mon 28/07/08Dur: 1 day
Res: Excavation Subcontractor Res: Excavation Subcontractor

Stake Lot for Excavation


Start: Mon 28/07/08ID: 45
Finish: Mon 28/07/08Dur: 1 day
Res: Civil Engineer
Building Permit Issued

Milestone Date: Tue 29/07/08


ID: 41
Rough grade lot
Start: Tue 29/07/08 ID: 46
Finish: Tue 29/07/08Dur: 1 day
Res: Excavation Subcontractor

Excavate for foundation


Start: Wed 30/07/08ID: 47
Finish: Thu 31/07/08Dur: 2 days
Res: Excavation Subcontractor
Layout footings Dig Footings & Install Reinforcing
Start: Fri 01/08/08 ID: 49 Start: Mon 04/08/08ID: 50
Finish: Fri 01/08/08 Dur: 1 day Finish: Mon 04/08/08Dur: 1 day
Res: Concrete Subcontractor Res: Concrete Subcontractor
Pour footings
Footing Inspection
Start: Tue 05/08/08 ID: 52
Milestone Date: Mon 04/08/08 Finish: Tue 05/08/08Dur: 1 day
ID: 51 Res: Concrete Subcontractor
Pin Footings Stock Block, Mortar, Sand
Start: Wed 06/08/08ID: 53 Start: Thu 07/08/08ID: 54
Finish: Wed 06/08/08Dur: 1 day Finish: Thu 07/08/08Dur: 1 day
Res: Civil Engineer Res: Block Masonry Subcontractor
Build Block Foundation
Foundation Certification
Start: Fri 08/08/08 ID: 55
Finish: Thu 28/08/08Dur: 15 days Milestone Date: Thu 28/08/08
Res: Block Masonry Subcontractor ID: 56

Fill Block Cores w/ Concrete


Start: Fri 29/08/08 ID: 58
Finish: Fri 29/08/08 Dur: 1 day
Res: Block Masonry Subcontractor
Draw #1 (Location Survey)

Milestone Date: Thu 28/08/08


ID: 57

Steel Delivery Set Lintels, Bolts, Cap Block


Start: Mon 01/09/08ID: 59 Start: Tue 02/09/08 ID: 60
Finish: Mon 01/09/08Dur: 1 day Finish: Wed 03/09/08Dur: 2 days
Res: Steel Supplier Res: Block Masonry Subcontractor

Lumber Delivery Waterproofing and Drain Tile


Start: Mon 01/09/08ID: 61 Start: Tue 02/09/08 ID: 62
Finish: Mon 01/09/08Dur: 1 day Finish: Tue 02/09/08Dur: 1 day
Res: Lumber Supplier Res: Waterproofing Subcontractor
Critical Summary Critical External

Noncritical Critical Inserted External

Critical Milestone Inserted Project Summary

Milestone Critical Marked Highlighted Critical

Critical Summary Marked Highlighted Noncritical

You might also like